Schindler 3300MRL Part1-2

Schindler 3300

Installation and Commissioning

Welcome

Contents Sequence 0

y Course Objectives y Course Structure

Course Structure

y Installation Overview

y First Steps

y Hoistway Components AP y P31K-AP Car

y Safety Components

y FMB130 –4 Machine Sequence 1 Sequence 5 Sequence 2

Sequence 3 Sequence 4 Sequence 6

Course Structure

y Landing/Car Door System y LCE

y Shaft Information System Sequence 7 Sequence 8 Sequence 9

y System Overview and Hardware

Sequence 10

y Commissioning and First

Level Troubleshooting

Sequence 11

Contents Sequence 1

y Safety Advice y Basic Concept y Installation Method y Typical Daily Work Map

y Documentation

http://crd/tk/products/Default_elevators_en.htm

Safety Advice

Safety Equipment

Hardhat Safety Goggles Full Body

Safety Harness

Safety Shoes Protective Gloves

All persons involved must know and follow all company and local safety regulations.

In addition to protective clothing, use the shown safety equipment.

?Scaffolding methodology ?Electrical hoist for handling and hoisting ?Rails are provisionally stored in pit ?

Scaffolding methodology ?

Electrical hoist for handling and hoisting ?

Rails are provisionally stored in pit Model Case:800 kg car, 10 stops, no options, material on site, special

tools available, two fitters (instructed and documented)

1.Following the safety procedures

asee chapter “Installation Overview –Safety Advice”

Basic Sequences

Installation Method

2.Checking and preparing building site (Including scaffolding checking)asee chapter “First Steps –Building Site Control”

3.Distribution and packing of the material

asee chapter “First Steps –Material Logistic”4. Setting plumb lines

asee chapter “Hoistway Components –Plumb Lines”6.Guide rail brackets

asee chapter “Hoistway Components –Guide rail fastening”

5.Preparing and introducing rails into the hoistway asee chapter “Hoistway Components –Guide Rails”

Basic Sequences

Installation Method

8.Installing first set of rails

asee chapter “Hoistway Components –Guide Rails”9.Installing counterweight (partially filled)

asee chapter “Hoistway Components –Counterweight”10.Installing rest of guide rail fastenings

asee chapter “Hoistway Components –Guide Rail Fastenings”7.Installing pit set

asee chapter “Hoistway Components –Pit Set”12.Car suspension point

asee chapter “Hoistway Comp. –Car Suspension Point”

11.Installing Landing doors

asee chapter “Varidor 30 Landing doors”

Installation Method

Basic Sequences

13.Counterweight suspension point

asee chapter “Hoistway Comp. –Counterweight Suspension Point ”

14.Installation machine

asee chapter “FMB –4 Machine”

15.Installing converter

asee chapter “ACVF Biodyn 12C/25C/42C/BR”

16.Installing main electrical components

asee chapter “Commissioning”

17.Installing traction beam

asee chapter “P31K Car –GED15/20 Safety Gear / Floor Structure”

18.Installing car structure

asee chapter “P31K Car”

Installation Method

Basic Sequences

19.Installing LCE

asee chapter “LCE”

20.Installing car doors

asee chapter “Compact Car Door System”

21.Installing car decoration and COP

asee chapter “P31K Car”

22.Installing car peripherals and wiring

(shaft info kit, light barrier, light curtain, CCU, traveling cable etc.)

23.Installing rest of mechanical and electrical components (incl. wiring)

(traveling cable, sensor flag brackets, fixtures, pit ladder, CW filled etc.)

https://www.sodocs.net/doc/2d13781870.html,missioning

asee chapter “Commissioning”

25.Final works (cleaning, lubrication, CW balancing & screen, toe guard etc.)

Tasks

Dismantle the Scaffolding, Final operation of traction belt (PTFE-spray), Car decoration Car doors, Car peripherals and wiring, Rest of mechanical and electrical components (incl.

Rest of mechanical and electrical components (incl. wiring), Commissioning, Final works

Contents Sequence 2

y Building Site Control y Material Logistic

HSGmin.: Tol. +/-20 mm

The lifting points must be checked for sufficient load capacity.

Material Logistic

Packaging

Check the number of pallets according to the bill of delivery.

Retain the packing list of each package.Check the packages for external damages.

Car

Machine

Car Deco

CW

Mech 1

Elec & Belts

Mech 2

Car Front

Door