同沿高速公路刘家沟和堡子山隧道施工关键技术

摘要:在六盘山地区修建隧道,有着与其他地区修建隧道明显不同的特点,本文以刘家沟和堡子山隧道为背景,介绍了这两座隧道在浅埋土石混合新地质条件下的隧道施工关键技术,从洞口开挖和各种围岩条件下的隧道开挖,一直到支护、仰拱、二次衬砌、通风、照明、排水的施工,进行了详细的介绍,根据刘家沟和堡子山隧道的特殊水文地质条件,提出了这两座隧道的施工步距,这些对同类隧道的施工,具有一定的借鉴意义。

关键词:隧道;光面爆破;预裂爆破;仰拱施作;二次衬砌

Abstract: setsmic prospectlog in mount liupanshan region to build a tunnel, with and other areas to build a tunnel obviously different characteristics, this paper LiuGuGou and BaoZi mountain tunnel as the background, this paper introduces two cities in the shallow tunnel in earth-rock mixture new geological conditions of tunnel construction of key technologies, from the mouth of the cave excavation and all kinds of surrounding rock under the conditions of tunnel excavation, has been to support, Yang arch, the second lining, ventilation, lighting, drainage construction, is introduced in detail, and BaoZi mountain tunnel LiuGuGou according to the special hydrogeology conditions, put forward the two cities tunnel construction step distance, these to the similar tunnel construction, and has a certain significance.

Keywords: tunnel; Smooth blasting; Presplit blasting; Yang arch applied; The second lining

刘家沟隧道位于宁夏固原泾源县六盘山镇(原什字镇)刘家沟村东南约300米处,设计为上下行线分离式双洞隧道,上行线进、出口里程桩号为SK189+820、SK190+505,均位于大半径曲线上,长685米,单向坡,纵坡为1.6%;下行线进、出口里程桩号为XK190+470、XK189+780,长690米,纵坡为1.7%,其他基本同上行线。两轴线相距约50米,属浅埋土石混合型中隧道。

堡子山隧道位于宁夏固原泾源县六盘山镇(原什字镇)东山坡村东约150米处,设计为上下行线分离式双洞隧道,上行线进、出口里程桩号为SK192+630、SK193+240,均位于大半径曲线上,长610米,单向坡;下行线进、出口里程桩号为XK193+144.5、XK192+614.5,长614.5米,其他基本同上行线。两轴线相距约50~58米,亦属浅埋土石混合型中隧道。

1.开挖、支护方法

1.1洞口加强段

采用单侧壁导坑法(中隔墙法),小型挖掘机开挖为主,人工风镐开挖为辅。预留变形沉降量18cm,初期支护采用套拱超前大管棚预支护、砂浆锚杆、双层钢筋网、喷射混凝土、型钢拱架等。

高速公路隧道施工方案及步骤

高速公路隧道施工方案及步骤 按新奥法组织施工,左右洞身分别从两头掘进,无轨运输施工。Ⅲ类围岩采用小导管注浆及超前锚杆加固围岩,开挖采用台阶法,人工配合台车钻眼;Ⅳ类围岩开挖采用全断面法,台车钻眼。洞身衬砌砼采用集中拌合,砼运输车运输,砼输送泵配合液压衬砌台车施工。 一、掘进施工方案: 为防止左右洞在同一断面同时开挖,对两隧道之间围岩产生较大的影响,采用右洞从进口 主攻、左洞从出口主攻的方法开挖。 开挖采用钻爆法施工,采用光面爆破技术开挖。进出口主要各配备1台凿岩台车钻眼,1台挖掘机配合1台侧卸式装载机装碴。6台15T自卸汽车出碴。 Ⅲ类围岩采用短台阶法,台阶长度10-15m;Ⅳ类围岩采用全断面法施工。 二、初期支护施工方案: 洞口Ⅲ类围岩(S2)采用超前小导管(注浆)及超前砂浆锚杆(S3)、钢筋网喷射砼、钢拱架支护,Ⅳ类围岩采用组合锚杆、喷射钢纤维砼支护。 支护施工顺序为:超前支护(超前小导管、超前砂浆锚杆)开挖初喷锚杆、钢筋网、钢拱架复喷至设计厚度。超前支护在开挖之前施工,初期支护紧跟开挖施工。 超前砂浆锚杆采用钻机钻孔,采用高压注浆泵注浆,喷射砼采用湿喷机按湿喷工艺施作。 施工中应认真落实超前地质预报和监控量测工作,确保隧道施工不出现坍塌事故。 三、隧道衬砌施工方案: 二次衬砌施作时间根据监控量测数据确定,Ⅲ类围岩地段隧道衬砌适当紧跟初期支护,仰拱和回填应在二次衬砌之前进行;Ⅳ类围岩二次衬砌可适当滞后,在初期支护基本稳定后施作。 衬砌前按设计要求施工防水层和塑料盲管。防水层和塑料盲管采用自制作业台车施工,防 水层采用无钉铺设工艺,用热焊焊接固定。 洞内衬砌采用穿行式液压衬砌台车全断面施工,隧道进、出口端各配1台台车,考虑隧道处于曲线上的因素,选用长度为9m的台车。紧急停靠带的衬砌砼待全隧衬砌完成后,在台车钢模内加设活动的、带弧形的3015钢模板,并用特制的梳型模加固和调整尺寸,行人、行车横洞及其它预留洞室采用特制台架施工。砼采用S8(C25)防水砼,砼搅拌运输车运输(200m 以上),输送泵泵送砼灌注入模,拌合站集中拌制。 四、施工辅助设施方案: 1、施工用电: 隧道用电利用洞口安装的变压器供电。洞内利用电缆线接至工作面后使用,动力电采用 400V/380V,照明采用安全变压器(36V)供电。 2、施工用风: 在进出口洞口各设40m3供风站一个,供洞内开挖、支护、通风用风。 3、施工通风: 本隧道从两头掘进,单头掘进长度约714~825m,经分析计算,决定本隧道施工通风采用管道压入式通风方式,风管采用维尼龙布基风管,管径采用φ1000mm,进口右洞和出口左洞洞口各配置1台容量不小于1000 m3/min的轴流式通风机。

山岭隧道开挖与支护方法

2012年6月内蒙古科技与经济June2012 第11期总第261期Inner M o ngo lia Science T echnolo gy&Economy N o.11T o tal N o.261浅谈山岭隧道开挖与支护方法 姜利军,徐义芳 (内蒙古鄂尔多斯市东方路桥集团有限公司,内蒙古鄂尔多斯 017000) 摘 要:对山岭隧道常规施工工艺和方法进行了研究,包括矿山法(传统矿山法和新奥法)和掘进机法,并指出它们之间的优缺点。指出目前国内外应对山岭隧道不良地质(软弱围岩、高压富水断层破碎带、岩溶地区和岩爆地区)的某些技术措施。对山岭隧道的一些现状进行研究,并介绍了人工地层冻结法在山岭隧道的应用趋势,当前山岭隧道施工过程中的超前支护、初期支护和二次衬砌的设计和隧道检测技术的研究现状及其目前存在的问题和解决措施,还有山岭隧道施工对环境的影响。 关键词:山岭隧道;施工方法;开挖;支护 中图分类号:U455.4 文献标识码:B 文章编号:1007—6921(2012)11—0089—04 我国是一个多山的国家,山区公路建设需要修建大量隧道。隧道等地下工程,其核心问题,都归结在开挖和支护两个关键工序上。即如何开挖才能更有利于洞室稳定和便于支护;如何支护才能更有效地保证洞室稳定和便于开挖。 1 山岭隧道的常规施工方法 1.1 矿山法(钻爆法) 矿山法,顾名思义,就是最早应用于采矿中的隧道工法。其历史源远流长,是人们长期在施工实践中发展起来的。在矿山法中,多数情况下都需要采用钻眼爆破进行开挖,所以又称为钻爆法。从隧道工程的实际发展方向和现场条件限制的情况下,隧道的开挖要有入口,而钻爆法可以给我们因地制宜的突破口,所以笔者认为钻爆法仍然是以后山岭隧道中最常用的施工方法。例如:大瑶山隧道、秦岭铁路Ⅱ线隧道、白云山隧道等都是采用钻爆法施工的。根据地质水文条件和截面尺寸,隧道开挖能采用各种不同的开挖方法,例如:上下导坑先拱后墙法,下导坑先拱后墙法,反台阶法,正台阶法,全断面开挖法,半断面开挖法,逆衬砌法,复合衬砌法(新奥法),侧壁导坑法等。对于初期岩石支护,有喷浆、挂网、钢拱架等支护方法。 钻爆法施工的全过程可以概括为:钻爆,装载、出碴,喷锚支护,灌注衬砌。在通过不良地质时,常采用注浆、通风和排水等辅助措施。 1.1.1 传统矿山法。传统矿山法的核心内容是:稳定的围岩有自稳能力,不产生荷载;不稳定的岩体则可能坍塌,需要用支护结构予以支撑。它只将围岩视为被挖去的岩体,开挖后受爆破影响,造成岩体破裂形成松弛状态,随时都有可能坍落。基于这种松弛荷载理论依据,其施工方法是按分部顺序采取分割式一块一块的开挖,并要求边挖边撑以求安全,所以支撑复杂,木料耗用多。它是以木或钢构件作为临时支撑,等到隧道开挖完成后,逐步将临时支撑撤换下来,而用整体式后衬砌来代替它作为永久性支护的施工方法。 木构件支撑法,例如:方木接顶就是一种用于防止隧道落顶的方法,它具有取材方便,支护及时的特点。但是,由于其耐久性差和对隧道形状等实际情况的适应性差,支撑撤换工作既麻烦又不安全,甚至对围岩造成扰动,因此,目前已经很少采用。 相反的,钢构件支撑具有较好的耐久性和良好的对隧道形状等实际情况的适应性,施工中不用更换,所以较方便高效,更重要的是它安全性高。 1.1.2 新奥法。随着喷锚支护的出现,使分部数目得以减少,传统矿山法进而慢慢发展成新奥法。新奥法则把围岩视为承载单元,是围岩一支护体系的一部分,需尽可能地保护,发挥其自承作用。新奥法原理是以岩体力学理论为基础,以喷锚支护为代表的(但不是唯一的,而有多种手段),考虑支护与围岩共同作用,确保围岩稳定的现代支护理论。选择施工方法时,应遵循如下原则: 稳定开挖工作面是辅助措施的主要目的。方法很多,优先选择次序为:短台阶环形挖留核心土;锚杆超前支护;小导管注浆超前支护;钻孔(4m~6m)周边预注浆超前支护;长导管注浆超前支护;全断面封闭深孔注浆工作面等形式。 尽快形成一次支护封闭断面的快速施工做法,是防止变形、塌方的重要手段。 管超前、严注浆、短进尺、强支护、紧封闭、勤量测是18字施工的方针,不能违背。 它通过对隧道围岩变形的量测、监控,采用新型的支护结构,尽量利用围岩自承能力指导隧道设计和施工的方法。其特点是在开挖面附近及时施作密贴于围岩的薄层柔性喷射混凝土和锚杆支护,以便控制围岩的变形和应力释放,从而在支护和围岩的共同变形过程中,调整围岩应力重分布而达到新的平衡,以求最大限度地保持围岩的固有强度和利用其自承能力。因此,它也是一个具体应用岩体动态性质的完整力学方法,其目的在于促使围岩能够形成圆环状承载结构,故一般应及时修筑仰拱,使断面闭合成圆环。它适用于各种不同的地质条件,在软弱围岩中更为有效。新奥法的原理虽然可用于各种类型的支护,但是,最为适用的是喷锚支护。因此喷混凝土、锚杆、量测被认为是新奥法的三大要素。借助现场监测及其反馈信息,可以及时对原有设计方案进行调整和完善“正确指导施工,通过对测试成果的 ? 89 ? 收稿日期:2012-03-28

高速公路隧道施工技术及控制要点探析 于福光

高速公路隧道施工技术及控制要点探析于福光 发表时间:2018-10-28T14:26:09.767Z 来源:《建筑学研究前沿》2018年第18期作者:于福光 [导读] 对于高速公路的设计和施工单位来说,有一些因素必须充分考虑,如果没有对设计和施工给予特别的注意。 中国建筑土木建设有限公司北京丰台 100070 摘要:交通一直是促进和加强我国各区域间经济、文化交流的纽带和桥梁。随着经济的快速发展和技术的提高,我国对于交通建设事业一直大力扶植和发展,并且在高速公路以及其他交通渠道的建设上取得了很大的成就。但是,由于我国的国土面积辽阔,地形地势复杂多变,在某些地势险要的区域,在需要翻山越岭的过程中无法直接开展高速公路建设。因此,需要我们绕过复杂地形,通过借助隧道穿梭来完成道路的架设,从而使得隧道施工技术成为解决这一难题的关键和重点。文中对高速公路隧道施工技术及控制要点进行了分析。 关键词:高速公路;隧道施工;技术;控制 1高速公路隧道施工的工程特点 对于高速公路的设计和施工单位来说,有一些因素必须充分考虑,如果没有对设计和施工给予特别的注意,就容易引发大的安全问题,影响到施工进度和工程质量。这些影响因素主要表现为三个方面的问题。 1.1不可预料的意外因素比较多 因为隧道施工是在山体内部进行,具有一定的隐蔽性,即使已经比较充分地掌握了现场的地质条件,但施工的难度仍然很大,因为总会有一些不可控的外在因素会突然发作,这些因素基本都是一种动态的存在,没有办法实施精确的预测,比如泥石流爆发、围岩坍塌、溶洞侵蚀等的变化,都会造成工程的延误甚至停滞。 1.2存在较大的安全风险 高速公路隧道进行施工,大部分的施工工序在地下和山体内完成,又因为施工地域的地质变化进行预测准确度很低,加之施工中会发生的多道工序多种操作混合交叉施工的情况,操作现场的环境并不十分适宜。空间很小,操作工序很繁琐,一不注意就会造成巨大的损失,这无疑会给隧道施工带来不可低估的难度。在完成预埋件、开挖、支护以及防排水等各个环节一起进行施工时,头绪多,任务重,要是某环节因为操作和其他原因导致与工程要求的质量标准不符,就可能发生塌方等重大安全事故,这将影响到完成整个工程的进度和质量,更严重的是施工人员的生命安全受到巨大威胁。 1.3隐蔽工程比较多 就因为隧道工程的意外影响因素多,施工头绪多,所以在实际施工过程中,会发生许多原来没有准备的隐蔽工程。这些隐蔽工程与正常施工环节的工序相互依存,一处没有处理好就会影响到其他的施工环节,必须要依据施工顺序按部就班进行实际的施工,包括可能会有的隐蔽工程,都要认真完成,确保该工序没有质量隐患再开始后继的工序。 2高速公路隧道施工技术 2.1高速公路隧道洞口的施工 在目前所有的高速公路隧道建设施工技术中,高速公路隧道洞口的设计与建造是占据关键位置的,因为高速公路隧道洞口是高速公路隧道建设的第一道工序,洞口的设计施工直接决定整个隧道工程的建设。在洞口动工前期就应做好准备工作,古人言“工欲善其事必先利其器”所以准备工作在整个前期工作中的显得尤为重要,准备工作必须要求技术员对即将开设洞口及洞口位置附近的周围环境进行仔细勘查,勘察内容涵盖了洞口位置及其周边未知的地质环境、山体层、水文条件、施工期内天气状况等项目,在勘测完之后需要对隧道施工可能出现的相关问题进行风险预估并作出相关应急预案。 在施工时我们需要用挖掘机对洞口位置进行挖掘,在合理的位置布置供水、供电及材料堆放的场所保证施工顺利进行,在挖掘机挖掘时应以洞内需要为主,对工地进行施工挖掘。挖掘时采用的方法多为边坡、仰坡自上而下的挖掘方式进行挖掘,施工时,洞口的土地需要用机械装备进行平整压实以保证安全,在施工过程中遇到坚硬的石质地层,可以采用人工钻眼爆破的方式进行清理。施工时,建筑企业需根据现场实际情况,加强边仰坡的防护工作,如在调整锚杆之间的距离时,可以采用增大钢筋密度,增加喷混凝土厚度一次扩大增强支护强度等方式解决。施工中我们可以在边坡选取合适的沉降量和位移测点来解决加强仰坡稳定性的问题。 2.2钻爆施工技术 目前阶段我国高速公路建设过程中所使用的炸药多为硝铵炸药,在爆破施工过程中场地选择的多为大中空孔型或者是直眼型场地进行施工,但是在隧道施工中爆破需要根据实际情况而决定,因为在隧道中进行爆破任务危险性远大于在洞外进行爆破,所以在进行隧道施工的建筑企业必须对此严格把控,不可以盲目进行钻爆施工。在进行钻爆施工前,必须有技术员对隧道内的岩土结构性质等进行勘察,根据技术人员分析得出的结果决定爆破强度。在施工过程中必须有相关专业人士做好全程监控并做好防护措施,避免爆炸产生的落石造成人员伤害。 2.3防排水设施的构建 高速公路隧道建筑为地下工程,危险性极高。为防止突水、涌水等情况造成施工时的人员伤害及完工后对公路本身造成的伤害,所以高速公路隧道施工时防排水设施的构建也是一道至关重要的程序。在高速公路隧道防排水工程构建中我们应遵循预防为主的方针,采用“防、排、堵相结合”的方法,对隧道内施工缝等易变形的薄弱点进行处理,防止渗水漏水问题发生。在涉及隧道排水问题的工作人员设计时应充分考察隧道实际情况后进行设计,例如北方地区的道路建设中就可在中心位置设置大型水沟,主要排地下水保证水沟在冻结水平下,避免水沟水流冻结。 3高速公路隧道施工的控制要点 3.1加强施工图纸审核 高速公路施工过程中,图纸占据着极为重要的位置,特别是在隧道施工当中,其重要性尤为关键。若其出现错误则会造成施工问题的发现,更甚者会导致项目无法正常开展。所以,在项目施工前期,需按机器施工图纸的审核,及时发现其中存在的问题并给予有效的解决,保证图纸的科学性。同时,在审核一次后并未及时发现任何问题还需进行第二次复核,最大限度的保证项目万无一失。除此之外,在

山岭隧道开挖施工方法

1. 2. 3.选择隧道施工方法的指导思想与应遵循的原则 隧道施工符合安全环保、工艺先进、质量优良、进度均衡、节能降耗的要求,隧道施工应本着“安全、有序、优质、高效”的指导思想,按照“保护围岩、内实外美、重视环境、动态施工”的原则组织施工。其施工方法的选择应遵循以下原则: (1)、确保施工安全,改善施工环境。 (2)、应根据设计文件、施工调研情况、地质围岩级别、结合隧道长度、断面大小、纵坡情况、衬砌方法、工期要求、装备水平、队伍素质等综合因素决定。 (3)、地质变换频繁隧道应考虑其适应性,便于工序调整转换。 (4)、应尽量采用新技术、新工艺、新设备、新材料。 (5)、认真按照新奥法原理、掌握应用好光爆、喷锚、量测施工三要素。 2 选择隧道施工方法的基本要素 (1)、施工条件 它包括一个施工队伍所具备的施工能力、素质以及管理水平。目前我集团隧道施工队伍的素质和施工装备水平,有高有低,参差不齐,因此,在选择施工方法时,不能不考虑这个因素的影响。 (2)、围岩条件 围岩条件也就是地质条件,其中包括围岩级别、地下水及不良地质现象等。围岩级别是对围岩工程性质的综合判定,对施工方法的选择起着重要的甚至决定性的作用。 (3)、隧道断面积 隧道尺寸和形状,对施工方法选择也有一定的影响。目前隧道断面有向大断面方向发展的趋势,如公路隧道已开始修建3车道甚至4车道的大断面,水电工程中的大断面洞室,更是屡见不鲜。在这种情况下,施工方法必须适应其发展。在单线和双线的铁路隧道中,越来越多地采用了全断面法及台阶法;而在更大断面的隧道工程中,先采用各种方法修小断面的导坑,再扩大形成全断面的施工方法极为盛行。 (4)、埋深 隧道埋深与围岩的初始应力场及多种因素有关,通常将埋深分为浅埋和深埋两类,有时将浅埋又分为超浅埋和浅埋两类。在同样地质条件下,埋深的不同,施工方法也将有很大差异。 (5)、工期 作为设计条件之一的施工工期,在一定程度上会影响基本施工方法的选择。因为工期决定了在均衡生产的条件下,对开挖、运输等综合生产能力的基本要求,即对施工均衡速度、机械化水平和管理模式的要求。 (6)、环境条件 当隧道施工对周围环境产生如爆破振动、地表下沉、噪声、地下水条件的变化等不良影响时,环境条件也应成为选择隧道施工方法的重要因素之一,在城市市区条件下,甚至会成为选择施工方法的决定性因素。 完善施工方法标准化、模式化的重要条件是建立适应各种条件下的隧道施工机械化配套技术的标准模式。

高速公路隧道工程施工组织设计

XXX 施工组织设计 第1 章编制说明 根据建设单位标前会和答疑会精神以及现场的实地踏勘,结合我公司多年来在公路、市政道路、立交桥等类似市政工程施工中所积累的经验,依据我公司的施工、技术、机械装备和管理等综合水平编制标书,若中标我们将在此基础上遵循合同要求,进一步按照设计文件、技术规范和标准编制出详细的实施性施工组织设计,并严格按照经过批准的施工组织设计进行施工,确保工程实施。 1.1 编制依据 (1) 《XXX施工招标文件》。 ( 2 )招标文件中明文规定的技术规范和标准,以及有关现行的国家和省部级规范和标准。 (3)XXX工程扩大初步设计,宁镇公路立交图纸。 1.2 编制原则 ( 1 )充分遵循招标文件条款的原则。 ( 2)坚持实事求是的原则,根据我公司的施工能力和管理水平,坚持科学组织、合理安排、均衡生产,确保优质高效的履行合同。 ( 3)按照招标文件、技术规范和标准的要求,正确选择施工方案,实行全面质量管理。 ( 4 )“严格贯彻安全第一”原则。 5 坚持优化技术方案和推广应用“四新”成果的原则,在施工中发扬创新精神,以科技为先导,应用新技术、新材料、新工艺、新设备, 积极寻求为建设单位节约投资的合理化建议, 对技术方案进行不断的优化。 1.3 编制目的在满足建设单位各项要求条件的前提下,确保工程施工质量达到全优,力争施工工期提前,把施工对周边环境破坏和扰动控制在规定要求范围内。 第2 章工程概况 2.1 工程地理位置及范围 2.1.1 工程位置 XXX工程位于南京市主城东北部,南起宁镇公路与宁栖路交叉口,北止于纬一路,全 长3.78km。其中本标段A主线331.502m, B主线335.252 m及其他支线道桥。如附录1所示。 2.1.2 工程范围 (1)道路部分:A主线自A0+000?A0+184.902; B 主线自B0+000?B0+214.952。 (2)桥梁部分:A 主线自A0(A0+184.902)?A6(A0+331.502); B 主线自B0(B0+214.952)?B5(B0+335.252)。匝道 C D E、G H; F线 桥。 排水部分: 宁镇路边排水暗渠一条。 2.2 设计概况 2.2.1 桥梁工程 A 主线桥:里程桩号A0+184.902 ?A0+331.502,长146.6 m。 墩基础:钻孔浇筑端承桩,8根桩径1.2 m 12根桩径1.5 m桩长范围15.0?20.0 m 4个6.0m X2.4 m 矩形承台、3个5.2 m x 2.2m矩形承台,桥台处13.25 m X5.2 m 矩形承台。 下部结构:6个T型墩柱。 上部结构:箱梁146.6 m,一联5跨等高预应力混凝土连续箱梁,高1.4 m。桥面系:7cm的C25防水混凝土找平层、3cm中粒式沥青混凝土。 B 主线桥:里程桩号:B0+214.952 ?B0+335.252,长120.3m。 墩基础:钻孔浇筑端承桩,16根桩径1.2 m 6根桩径1.5 m桩长范围15.0?20.0 m 4个5.2m

高速公路工程重难点分析

高速公路工程重难点分析 根据本合同段的工程内容、数量以及施工难度,隧道工程**** 隧道为我合同段的控制性工程作为本合同段的重点、难点工程。本标段****隧道,设计为三车道(设计净宽14.5m),出口段500米设计净宽17米,并设有紧急停车带,工程地质情况复杂,进出口坡度相对较陡,坡面覆盖浅层坡基层,易坍塌;洞身 al+pl eol)硬)硬塑粉质粘土、下更新统(为第四系中更新统(QQ12塑黄土、第三系(N)粘土岩组成,岩土裂隙发育,遇水、暴露2易开裂崩解,具有膨胀性,在隧道开挖过程中需采用安全可靠的支护方案。隧道设计为分离式隧道:净宽14.5m,净高5米,为典型的大跨度黄土隧道,需采用大跨度黄土隧道施工技术。同时设有紧急停车带,三车道黄土大跨径黄土隧道设置紧急停车带为全国首例,施工难度大。 1.1技术难点分析 1、针对大跨度黄土隧道,如何保证开挖拱角不失稳坍塌是本工程的难点。 2、隧道结构复杂,洞口段、滑坡地段、正洞与横洞交叉处施工是隧道安全、顺利建成的关键。 、根据设计文件提供的地质水文调查,洞内有线状渗水,3. 如何解决洞内排水问题,避免水对隧底黄土的浸泡降低地基承载力的问题。

4、全国首例三车道设置紧急停车带,确定何种开挖工艺才能保证洞身安全和施工安全,安全渡过该段施工。 5、针对设计采用的双侧壁施工法和CD施工法,在较小的施工空间内如何在确保安全的前提下提高施工效率。 6、为满足施工进度的要求,需制订隧道冬季施工技术措施。1.2 控制工程技术要点(隧道工程) 1、首先做好洞顶、洞门及洞口的防排水系统工程,并妥善处理好陷穴、裂缝,以免地面积水浸蚀洞体周围,造成土体坍塌。 2、在含有地下水的黄土层施工时,洞内外排水沟应进行铺砌,必要时应配合井点降水等将地下水位降至隧道衬砌底部以下,以保施工顺利进行。 3、在干燥无水的黄土层中施工,应管理好施工用水,不使废水漫流。 4、如发现工作面有失稳现象,应及时用喷砼封闭,加设锚杆、架立钢支撑等加强支护。 5、施工时要特别注意拱脚与墙脚处断面,严禁超挖,若有超挖采用同标号喷射砼进行补平,如发现该处土体承载力不够,应立即加设锚杆或采取其它措施进行加固。 6、在开挖与浇筑仰拱时,为防止边墙向内位移,宜采取短进尺临支护。. 7、喷射机所用的压力,一般以不超过0.2Mpa为宜。 8、钻锚杆孔时,宜采用干钻,锚杆采用早强砂浆式锚杆、自进

山岭隧道工程施工设计方案模版

铁道大学四方学院毕业设计 施家梁右线五号隧道施工组织设计Construction Organization Design Of The SHIJIALIANG Tunnel Of Right line No.5 2013 届土木工程系 专业土木工程 学号 20095218 学生海琨 指导教师丽敏 于跃勋 完成日期 2013年5月30日

毕业设计成绩单

摘要 隧道施工设计是组织施工,指导施工活动,保证施工组织正常进行的重要技术经济文件,对工程的三大控制有极其重要的作用,是对实行科学管理的重要手段。本文以施家梁隧道为实例,对工程的施工方案进行了详细的规划,对施工时诸多因素尽可能充分的考虑,突出科学性、适用性是确保优质、低耗、安全、文明、高速完成全部施工任务的重要技术条件。 本设计针对山岭隧道隧道。设计包括以下容:编制依据、工程概况、隧道洞口洞身的施工、初期支护、二次衬砌、通风及防排水、爆破设计。针对工程的特点根据规编制出针对性的施工组织设计,切实可行的施工方案。以保证顺利完成本工程项目的建设,控制工程成本,创建优质工程。 关键字:支护爆破衬砌防排水

Abstract Tunnel construction design is to organize and guide the construction activities to ensure that the normal construction organization an important technical and economic documents, the project's three control has an extremely important role, is an important means of scientific management.Shi Liang tunnel design as an example, the detailed planning of the implementation plan, the fullest possible consideration of many factors in the construction, highlighting the scientific, applicability to ensure quality, low cost, safe, civilized, high-speed to complete all important economic and technical documentation of the construction tasks. The preparation of the design for the construction of mountain tunnel tunnel. The design includes the following: The basis for preparing project profiles, the construction of the tunnel entrance hole body, initial support, the secondary lining, ventilation and waterproofing and drainage, blasting design. Prepared according to the specifications on the characteristics of the project the targeted construction design, practical construction program. To guide the construction of the successful completion of the construction of the project, control the cost of the project, to create a high-quality project. Key words: Support Blasting Lining Waterproofing and drainage

高速公路隧道施工组织方案

高速公路隧道施工组织方案 第一章施工总部署 1.1施工组织 1.1.1施工组织管理机构 为安全、优质、按期完成本合同段的施工任务,本着精干、高效的原则,我们拟抽调理论和实践经验丰富、业务能力强、综合素质高的技术、管理人员及具有丰富施工经验的施工班组上场。组建本项目管理机构,成立“隧道施工队”,全面履行施工承包合同,直接组织工程施工。 队部设队长1人,副队长3人,技术主管1人,测量及技术员4人,下设开挖班、立架班、喷砼班、钢筋班、二衬班、出碴班、机械班及后勤保障部。 各班组按工种分工和职责范围,各负其责,密切配合,对工程进行有效、全面地监控和管理,后勤部承办各项业务工作,全面保证ISO9001:2000质量保证体系的有效运行和本项工程建设任务的优质、高效完成。 1.1.2队部人员安排 针对本项目工程特点,我们对队部人员进行了安排,队部各类人员共计40人,其中主要管理和技术人员15人,队部人员具体安排详见表1-1-01,施工任职主要人员见1-1-02。 队部人员配备表表1-1-01

施工主要任职人员表表1-1-02 1.1.3施工任务安排及劳动力组织 根据本项目的工程数量、工程特点、工期要求及本承包人企业定额水平现状,本工程拟安排三个隧道施工队和一个机械保障队负责本项目具体施工任务,人员实行弹性编制、动态管理,正常施工投入各类人员340人,其中熟练技工占50%,高级技工占11%。 施工队伍具体任务安排及劳力配备详见1-1-03。 施工队伍任务划分及劳力配备表表1-1-03 1.1.4劳动力上场计划详见表1-1-04。 劳动力上场计划详见表1-1-04

1.2施工计划安排 1.2.1总工期目标及总体施工进度计划 根据本工程的实际情况和我单位施工能力,本工程总工期目标是:15个月完成全部施工任务。2003年5月15日进场,2003年6月15日正式开工,2004年10月15日完工。 1.2.2阶段性工期目标 一、施工准备阶段 计划安排1个月(2003年5月15日~2003年6月15日)。 主要组织人员、主要机械设备、材料进场,完成施工便道、给水管道、递接高压线,安装变压器,修建生产及生活用房,交接桩橛和本项目控制测量,复核技术资料,办理征地拆迁、设计制作衬砌台车等工作。 二、主体工程施工阶段 计划安排15个月(2003年6月15日~2004年9月15日)。 主要完成本隧道的明洞、洞门工程、开挖、初支、仰拱、回填层、二次衬砌、砼路面及隧道装饰等项目的施工。 三、收尾配套阶段 计划安排20天(2004年10月1日~2004年10月20日)。 主要完成缺陷修复,设备、人员转场、场地恢复、竣工资料编制及验交等工作。 1.3施工总平面布与临时工程 本标段的施工总平面布置本着因地制宜,便于施工,少占农田,安全渡汛和有利于环境保护的原则进行布置。 沿线有电力线经过,在向电力部门申请后,于进口设二台800KV A变

浅谈高速公路隧道施工监理要点 (1)

浅谈高速公路隧道施工质量监理要点 福建省交通建设工程监理咨询公司许永兴 摘要:本文结合福建省漳诏高速公路、漳龙高速公路、龙长高速公路、永武高速公路的隧道工程施工监理经验,依据国家和行业的有关标准、规范,提出高速公路隧道工程质量监理控制措施,供同行参考。 关键词:高速公路隧道施工质量监理 改革开放以来,我国公路交通事业发生了历史性的巨变,公路交通已成为拉动国民经济增长的支柱产业和带动地方经济发展的龙头。在山岭和丘陵地区乃至越江过河的公路建设中,隧道方案以能缩短行车里程,提高线型标准,保障运营安全,保护生态环境等优点,得到普遍应用,并且越修越长,规模越来越大。在坚持可持续发展,切实保护生态环境和有限土地资源的战略指导下,长大隧道的建设必然任务越来越重,技术要求越来越高。保质保量完成工程项目是每个参建者的共同目标,而质量是工程的生命,如何加强管理确保工程质量是工程监理的职责所在。现结合本人十年现场实际工作经验,浅谈高速公路隧道施工(土建部分)质量的监理要点。 一、隧道监控量测监理要点 隧道监控量测贯穿于隧道施工的整个过程,通过收集、分析其量测结果,可以掌握施工中围岩和支护的力学动态信息及稳定程度,并及时反馈,用以指导隧道现场实际施工,保证施工安全,是隧道施工中不可缺少的一个关键环节。监理工程师在监控量测中应做好以下工作: 1、在施工前对承包商进行控制点(导线点、水准点)的复测工作及成果进行审核,指导隧道进洞施工放样。严格按规范要求的精度进行洞口投点,加强隧道洞内测量监控。对于必测项目,如周边收敛、位移量测、拱顶下沉量测、锚杆内力抗拔、掌子面地质素描等,必须严格按技术规范和图纸要求的监测频率进行布点监测;对于选测项目,如地表下沉量测、围岩内部变形量测、围岩压力量测、支护及衬砌应力量测等,则应根据图纸要求和各隧道的具体情况给予布点监测。 2、施工过程中应严格审查承包商内、外业测量成果;检查测量仪器的使用状况及检核情况;定期或不定期检查水准点及控制点情况,并对其进行校核;检

公路隧道施工安全技术控制 王浩

公路隧道施工安全技术控制王浩 发表时间:2018-11-09T17:38:22.507Z 来源:《防护工程》2018年第21期作者:王浩[导读] 如岩爆、塌方及涌水等。如在进行洞身开挖过程中,围岩地质条件突然出现断层、软弱夹层情况,会引起公路隧道工程出现塌方。中国建筑第七工程局有限公司总承包公司河南郑州 450004 摘要:公路隧道多为地下暗挖工程,容易发生各类安全质量事故,造成人员伤亡和财产损失。因此,探讨公路隧道施工安全技术控制,对于提高公路隧道施工质量与安全,有着重要意义。文中对公路隧道施工安全技术控制进行了分析。关键词:公路隧道;施工安全;技术控制1公路隧道施工安全的影响因素1.1地质方面 地质条件对公路隧道施工安全具有直接影响,但若未在施工前对公路隧道工程的地质条件进行严格勘察,就无法充分了解地质勘探的工作,会引起安全事故的发生,如岩爆、塌方及涌水等。如在进行洞身开挖过程中,围岩地质条件突然出现断层、软弱夹层情况,会引起公路隧道工程出现塌方。 1.2设计方面 地质资料是设计的重要依据,其完整性及准确性至关重要,在公路隧道设计过程中,若设计人员未严格按照地质资料进行设计,则会造成公路隧道设计的不科学及不合理,导致安全事故的发生。如在设计支护时,其参数偏小,不能保证开挖过程的稳定性;隧道洞口设计在断层也可能将隧道洞口设计在较大滑动体中,会引起洞口塌方问题的出现。 1.3施工方法与技术方面在公路隧道施工过程中,经常碰到地质较为复杂的情况,若未采取合理的施工方法及施工技术,则会造成质量问题的出现,引发公路隧道工程施工安全事故的发生。如在选择施工方法时,未充分考虑地质条件导致施工方法不符合隧道工程施工的实际情况,起不到良好的施工效果;在初期支护过程中,采用的锚杆长度以及锚杆间距不科学合理,无法保证围岩的稳定性。 1.4管理方面 在公路施工过程中,一些建筑企业过于重视经济效益,对安全管理工作不够重视,引发了许多管理问题,如管理不当,管理不到位的情况等,这就无法有效保证公路隧道施工的安全。而实际施工过程中,一些施工人员的安全意识较为淡薄,未严格按照施工要求进行施工,在施工时,总存在侥幸心理,使隧道工程施工存在许多安全隐患。2公路隧道施工安全技术控制原则隧道施工安全技术控制原则,可归纳为:保护围岩,内实外美,重视环境,三步紧跟、动态施工。 2.1保护围岩 一是少损伤围岩的固有支护能力,可通过机械开挖和控制爆破予以解决;二是通过支护、预加固等技术,增强围岩的自支护能力。 2.2内实外美 关键是做到混凝土密实、喷射混凝土密实、喷射混凝土与围岩密实、二次衬砌与初期支护密实。 2.3重视环境 一是内部环境,如通风集尘、防排水、降噪减震等;二是外部环境,如山岭便道、弃渣场、周边环境。 2.4三步紧跟 隧道开挖时,应做到初支紧跟、仰拱紧跟、二衬紧跟,其施工安全步距须根据围岩情况满足《公路工程施工安全技术规范》的相应要求。 2.5动态施工 隧道施工中的地质条件是不断变化的,其力学状态也是不断变化的。因此,施工中应遵循“岩变我变”的原则,结合超前地质预报和监控量测技术,探明围岩情况,确定科学的施工方法。3公路隧道施工技术3.1公路隧道洞口的施工在目前所有的公路隧道建设施工技术中,高速公路隧道洞口的设计与建造是占据关键位置的,因为高速公路隧道洞口是公路隧道建设的第一道工序,洞口的设计施工直接决定整个隧道工程的建设。在洞口动工前期就应做好准备工作,古人言“工欲善其事必先利其器”所以准备工作在整个前期工作中的显得尤为重要,准备工作必须要求技术员对即将开设洞口及洞口位置附近的周围环境进行仔细勘查,勘察内容涵盖了洞口位置及其周边未知的地质环境、山体层、水文条件、施工期内天气状况等项目,在勘测完之后需要对隧道施工可能出现的相关问题进行风险预估并作出相关应急预案。在施工时我们需要用挖掘机对洞口位置进行挖掘,在合理的位置布置供水、供电及材料堆放的场所保证施工顺利进行,在挖掘机挖掘时应以洞内需要为主,对工地进行施工挖掘。挖掘时采用的方法多为边坡、仰坡自上而下的挖掘方式进行挖掘,施工时,洞口的土地需要用机械装备进行平整压实以保证安全,在施工过程中遇到坚硬的石质地层,可以采用人工钻眼爆破的方式进行清理。施工时,建筑企业需根据现场实际情况,加强边仰坡的防护工作,如在调整锚杆之间的距离时,可以采用增大钢筋密度,增加喷混凝土厚度一次扩大增强支护强度等方式解决。施工中我们可以在边坡选取合适的沉降量和位移测点来解决加强仰坡稳定性的问题。 3.2钻爆施工技术 目前阶段我国公路建设过程中所使用的炸药多为硝铵炸药,在爆破施工过程中场地选择的多为大中空孔型或者是直眼型场地进行施工,但是在隧道施工中爆破需要根据实际情况而决定,因为在隧道中进行爆破任务危险性远大于在洞外进行爆破,所以在进行隧道施工的建筑企业必须对此严格把控,不可以盲目进行钻爆施工。在进行钻爆施工前,必须有技术员对隧道内的岩土结构性质等进行勘察,根据技术人员分析得出的结果决定爆破强度。在施工过程中必须有相关专业人士做好全程监控并做好防护措施,避免爆炸产生的落石造成人员伤害。 3.3防排水设施的构建

高速公路隧道施工技术及控制要点分析

高速公路隧道施工技术及控制要点分析 摘要:我国高速公路建设规模逐渐扩大,不仅为人们的日常出行提供了便利, 而且促进了交通运输业的发展,从而使区域间的经济交流日益密切。高速公路隧 道施工是整个工程建设中的重要环节之一,由于隧道施工所面临的复杂自然环境,从而给施工人员带来了一定的困难。因此,只有加强先进施工技术的应用,明确 施工技术控制要点,才能提升施工质量。 关键词:高速公路;隧道;施工技术;控制要点 隧道是高速公路的关键构成部分,随着高速公路里程的增长,隧道的数量也 由此增多,在这样的发展环境下,为了保证隧道施工的安全,必须严格遵守安全 制度,做好项目的施工技术和控制是促进这一目标得以实现的重要举施,需相关 人员给予高度重视。本文重点论述了高速公路隧道施工技术及控制要点。 一、高速公路隧道施工的特点 1、隐蔽工程多。隧道施工属于地下工程的范畴,工程结构难以掌握,加之隧道施工的各工序间联系紧密,一道工序的完成质量直接影响下一工序,同时,地 下施工的检查效果相对较差,会带来更多的隐蔽工程。在隧道施工过程中,若不 能及时发现施工工序中存在的问题,将给施工安全带来极大的威胁。 2、施工环境受限。隧道施工场地狭小,在施工过程中会有高危作业、交叉作业存在,从而带来很大的风险。如开挖、支护、排水等环节同时施工,还存在挖掘、高空作业、受限空间等高危作业,每个环节处理不当均会导致严重后果。 3、地质条件复杂。高速公路隧道施工项目往往穿越山体,在施工过程中会遇到各种地质条件,无法准确判断具体的地质情况。同时,无法有效评估地下水、 溶洞等因素对项目施工的影响程度,从而对施工造成较大影响。 二、控制隧道施工技术的重要性 虽然在公路建设工程中一直有“金遂银桥”的说法,但对从事隧道施工的专业 人员而言,隧道施工条件复杂,安全系数低,隧道越长,面临的突发事件越多, 危险系数也越高,这给隧道施工管理及技术的实施带来了一定的阻碍。每次施工 前对施工现场的地质、水文、瓦斯等的考察,增加了施工成本。另外,因山体地 质状况的不同,若支护技术实施不到位,很可能会造成山体塌方,从而危及施工 人员的安全。隧道工程不是一个简单的独立施工工程,有很多隐蔽工程,洞口支护、洞身挖掘、隧道整体排水建设等相互关联,一旦一个施工环节的施工技术未 得到良好的控制,就会影响到后续的施工进程。施工项目较强的关联性,要求施 工人员要熟练掌握施工技术,以保证每个项目的施工质量。 三、高速公路隧道施工技术 1、明洞开挖技术及边仰坡技术。在实施该技术前,首先要测量放线,这是一项基础性工作。测量人员在放线时,不仅要准确测量明洞边坡及仰坡的顶线,还 要掌握放线精确度,这一过程之所以如此严格,主要原因是坡顶要设一个截水沟;在施工过程中,尽量缩短边仰坡暴露在阳光下的时间,这就需要施工队在适当的 时间安排工人进行施工。一旦发生紧急情况,防护力量需扩大,因而需增加支护 力量。而施工中支护主要依靠调整拱架间距、加密钢筋网、增加喷射混凝土厚度。挖掘机是隧道开挖过程中使用的主要工具,需人力配合的刷坡,通常需风钻打孔,并在爆破时会使用少量炸药。 2、钻爆施工技术。在隧道开挖期间,如何选择和使用合适的爆破设备十分重要。通常,硝铵炸药的使用频率较高,但如何科学使用,应严格按实际要求运用,

山岭隧道两种常规施工方法的综述及比较

山岭隧道两种常规施工方法的综述及比较 摘要: 针对山岭隧道两种常规的施工方法:传统的矿山法和“新奥法”,本文介绍了它们的施工方法和理念并进行了对比,给出了两者的主要差别。最后简述了山岭隧道施工方法的发展趋势。 关键词: 隧道工程新奥法传统矿山法松弛荷载理论岩承理论 0 引言 传统矿山法是山岭隧道常规施工方法,因最早应用于采矿坑道而得名。隧道等地下工程,其核心问题,都归结在开挖和支护两个关键工序上。即如何开挖才能更有利于洞室稳定和便于支护;如何支护才能更有效地保证洞室稳定和便于开挖。在矿山法中,坑道开挖后的支护方法,大致可以分为钢木构件支撑和锚杆喷射混凝土支护两类。习惯上将采用钻爆开挖加钢木构件支撑的施工方法称为“传统矿山法”;而将采用钻爆开挖加锚喷支护的施工方法称之为“新奥法”。“新奥法”与“传统矿山法”相比,在在理论基础、对围岩及支护的认识等方面都有很大的不同。 1隧道设计施工的两大理论及其发展过程 二十世纪以来,人类对地下空间的需求越来越多,因而对地下工程的研究有了一个突飞猛进的发展。在大量的地下工程实践中,人们普遍认识到,隧道及地下洞室工程,其核心问题,都归结在开挖和支护两个关键工序上。即如何开挖,才能更有利于洞室的稳定和便于支护:若需支护时,又如何支护才能更有效地保证洞室稳定和便于开挖。这是隧道及地下工程中两个相互促进又相互制约的问题。在隧道及地下洞室工程中,围绕着以上核心问题的实践和研究,在不同的时期,人们提出了不同的理论并逐步建立了不同的理论体系,每一种理论体系都包含和解决(或正在研究解决)了从工程认识(概念)、力学原理,工程措施到施工方法(工艺)等一系列工程问题。 1.1 松弛荷载理论 一种理论是二十世纪20年代提出的传统的“松弛荷载理论”。其核心内容是:稳定的岩体有自稳能力,不产生荷载:不稳定的岩体则可能产生坍塌,需要用支护结构予以支撑。这样,作用在支护结构上的荷载就是围岩在一定范围内由于松弛并可能塌落的岩体重力。这是一种传统的理论,其代表人物有泰沙基和普氏等人。它类似于地面工程考虑问题的思想,至今仍被广泛的应用着。传统矿山法是松弛荷载理论在隧道工程实践中的代表方法。

高速公路隧道施工技术

高速公路隧道施工技术 发表时间:2018-11-19T10:44:20.797Z 来源:《科技研究》2018年9期作者:张德斌 [导读] 隧道是高速公路的重要组成部分,在隧道施工过程中的质量控制和施工技术要点是高速公路隧道施工过程中的工作要点 成都市路桥工程股份有限公司 摘要:隧道是高速公路的重要组成部分,在隧道施工过程中的质量控制和施工技术要点是高速公路隧道施工过程中的工作要点,同高速公路施工项目的整体质量以及各使用功能能否充分发挥有着密切的联系。我国一直以来在高速公路施工建设事业上获得了较快的进展,高速公路隧道施工技术也获得了越来越多的关注及重视。为了进一步提升高速公路施工质量,应当对其施工技术及施工质量进行进一步的完善和优化。文章分析了高速公路隧道施工的特点并提出了高速公路隧道施工技术的控制措施。 关键词:高速公路;隧道施工;施工技术 引言 近几年,我国社会经济水平得到了迅速的发展,在这一发展过程中,社会及经济对于交通运输体系的质量要求也越来越高。高速公路是当前我国交通运输体系当中的重要部分之一,高速公路的修建进一步加强了全国各个区域之间的相互交流和沟通,为社会群众提供便捷的交通渠道。而在高速公路建设的过程当中,大多会通过山区、丘陵等地貌,为了缩短路程,减少运输成本,修建隧道是重要方法之一。因此,高速公路隧道建设的管理人员以及施工人员等都应当增加对隧道施工技术的重视程度,注重对施工要点及施工质量的控制,保障高速公路隧道施工质量,保障人民群众的生命财产安全。 一、高速公路隧道施工技术特点 高速公路隧道施工是高速公路施工项目的重要环节,由于高速公路隧道自身的特殊性,使得施工难度以及复杂程度都相对较高。在高速公路隧道施工中的几个施工特点如下: 首先,隧道施工过程中会有许多不可见的影响因素,其中,地质条件这一因素具有较高的不可预见性,同时也是十分显著的特点之一。通常,在隧道施工的准备阶段,较难对隧道内的地质情况有准确的预测,对于地下水、泥石流等不良地质情况也无法进行预测,使得高速公路隧道施工存在较大的不确定性。其次,隧道施工的风险较大,正是由于该施工过程不可预见性的特点,使得隧道中的地质情况无法进行预测,施工过程中容易出现塌方事故。再次,隐蔽的工程较多,由于隧道施工是一项地下工程,且具有特殊的结构,使得隧道施工过程中的各项施工环节是相互衔接的,于是存在较多的隐蔽工序,若这些施工环节出现问题,在竣工验收时无法及时发现并采取措施进行补救,对整个隧道施工的质量造成不良影响。另外,施工环境具有特殊性,使得施工操作更加困难。例如,施工过程中通常需要在开挖之后立即开展施工进行相应处理,整个施工过程具有较强的时效性,施工难度大;施工环境通常为半封闭的狭小空间,各项施工操作交叉作业导致施工环境差,施工难度较大。 可见,高速公路中的隧道施工对于施工技术有较高的要求,施工单位以及管理人员应当对施工技术加以重视,对施工技术进行严格的控制,改善施工环境,优化施工工序,才能保障隧道施工质量。 二、高速公路隧道施工技术控制要点 2.1 洞口及明洞的施工技术 隧道施工技术中,洞口的设计是十分关键的,这一阶段要进行隧道坡土的开挖,因此是隧道施工的首要阶段。洞口开挖前的准备工作对于洞口开挖质量是很重要的。对于开挖区域的地质结构、水文环境以及山体等应当进行全面的调研,勘察设计人员应当及时对勘测信息和数据进行分析,对施工过程中可能出现的风险问题进行预测和评估,并根据这些问题制定合理的补救措施。另外,应当合理地对截水沟位置进行设置,对明洞边坡等进行合理放线,合理利用挖掘机等施工设备来进行洞口地施工操作。明洞施工中,应当加强支护,才能保障岩体结构具有稳定性和较高地承载力,保障高速公路整体施工质量。 2.2 钻爆施工技术 隧道施工过程中,钻爆施工是较常用的施工方法之一,主要是对施工隧道进行钻爆。在这一施工过程中,应当选择合理的钻爆方式,根据施工现场实际的岩体结构来进行钻爆方式的选择,且所选用的方法应当符合施工设计方案中的要求。另外,选择合理的设备及工具也是至关重要的,例如,支护工具以及炸药的选取等。我国高速公路隧道施工爆破过程中所选择的炸药主要为硝铵炸药。为了保障隧道施工的稳定性以及安全性,在进行钻爆工作之前应当对施工现场进行支护,并根据岩体实际结构来选择合理支护形式。 2.3 防水排水施工技术 隧道施工对于高速公路的施工质量具有重要的影响作用,且隧道施工具有较高的难度,为了保证隧道施工的质量,还应当严格做好防水排水的施工建设工作。由于隧道中的防排水系统通常较容易受到外部环境影响,容易出现隧道内部积水的情况。因此,在隧道的防排水系统进行施工时,施工人员应当对隧道内部的实际结构进行充分的考虑,在中心位置可以设置一个较大的水沟,保证水沟位置在冻结的水平之下,避免出现水流冻结,阻碍地下水的顺畅排除。另外,隧道渗漏现象是导致隧道内部积水的重要原因之一,因此施工过程中还应当对隧道墙体进行严格的防渗漏施工,出现变形缝或是施工缝等则应当及时进行修补。 2.4 锚杆施工技术 在高速公路隧道施工技术当中,锚杆施工技术是重要部分之一,对于该施工技术的严格控制对于隧道施工质量具有重要意义。在锚杆专控过程中,可以运用岩凿机来进行钻孔,将岩凿机设置到预设点的位置,在施工操作前应当将该设备当中的污垢以及杂质等进行全面清理,对锚杆孔洞进行清洁,保证其清洁度能够符合相关标准。锚杆安装后及时进行挂网作业,先在洞外作成网片,铺网时注意网片搭接宽度,并固定牢固,网片挂好后进行复喷混凝土到设计厚度。锚杆施工应当将提前准备的药包放置孔洞中,在这一过程中应当合理控制顶入的力度,要将药包固定在孔洞中,也要避免药包泄漏。 2.5隧道衬砌施工技术 初期支护不仅是临时支护,加强围岩自承力,形成一个支护体系,也是复合式衬砌的重要组成部分,必须按设计规范作好,并作好量测工作,用量测数据指导施工,必要时采取补强措施。初期支护采用φ25中空锚杆@100×100cm,L=3.5m,然后挂φ6钢筋网

相关主题