Project Budget Monitor and Control

Author:Yin Guo-li

Nationality:American

Derivation:Management Science and Engineering. Montreal: Mar 20, 2010 .

With the marketing competitiveness growing, it is more and more critical in budget control of each project. This paper discusses that in the construction phase, how can a project manager be successful in budget control. There are many methods discussed in this paper, it reveals that to be successful, the project manager must concern all this methods.

1. INTRODUCTION

The survey shows that most projects encounter cost over-runs (Williams Ackermann, Eden, 2002,pl92). According to Wright (1997)'s research, a good rule of thumb is to add a minimum of 50% to the first estimate of the budget (Gardiner and Stewart, 1998, p251). It indicates that project is very complex and full of challenge. Many unexpected issues will lead the project cost over-runs. Therefore, many technologies and methods are developed for successful monitoring and control to lead the project to success. In this article, we will discuss in the construction phase, how can a project manager to be successful budget control.

2. THE CONCEPT AND THE PURPOSE OF PROJECT CONTROL AND MONITOR

Erel and Raz (2000) state that the project control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliver the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it. The purpose of monitor and control is to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target。

3. SETTING UP AN EFFICIENT CONTROL SYSTEM

For the purpose of achieving cost target, the manager need to set up an efficient management framework including: reporting structure, assessing progress, and communication system. The employees' responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).

4. COST MONITOR AND CONTROL

4.1 Ranking the priority of monitoring

In construction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determined by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Secondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are

committed elsewhere. Thirdly, monitoring the activities with less than a specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).

4.2Methods of cost control

The main cost of a project includes staff cost, material cost and delay cost. To control these cost, managers should first set up a cost control system to: a) Allocate responsibilities for administration and analysis of financial data 2

b) Ensure all costs are properly allocated against project codes

c) Ensure all costs are genuinely in pursuit of project activities

d) Check that other projects are not using the budget.

Then, managers should monitor and control change to the project budget. It means the following things:

a) Concerned with key factors that cause changes to the budget

b) Controlling actual cost changes as they occur

- Monitor cost performance to detect variances

- Record all appropriate changes accurately in the cost baseline

- Preventing incorrect, unauthorized changes being included in the cost baseline

- Determine positive and negative variances

- Integrated with all other control processes (scope, change, schedule, quality)

As a project is dynamic, sometimes the project managers know the project is going out off target by monitoring, but don't know the best action to take. In this circumstance, net present value (NPV) should be used as an ongoing monitor and control mechanism, because NPV takes account of the time element and discounts future cash flows, it is the result of the time effect on cash

4.3 Change monitor and control

Voropajev (1998) states that dynamic changes of project environment will influence the process of project implementation, the project itself and may cause heightened risk. When carried out some activities, the methods different from that in the original plan must be used to keep the process moving forward (as experienced under practice). Therefore, changes are inevitable and need to be managed during project life-cycle (Voropajev. 1998,p 16-17) .An effective change control system should be established to ensure change procedure is clear and unambiguous and easy for employee to request a change. And the following things need to be concerned:

a) Monitoring and forecasting most probable changes Key factors that generate change to ensure good results; make sure that change must be checked by suitable person.

b) Changes should take place once it is approved and be monitored to check whether it worked as expected

c) All changes in project should be recorded in the project documentation (Voropajev, 1998,pl8).

5. CONCLUSION

This article shows the best methods of budget control. First, an efficient control system must be set up. Secondly, It is required to recognize and rank the important factors affecting budget target. Thirdly, manager should combine different control techniques to reach the success of a project.

项目成本减少与控制

作者:Yin Guo-li

国籍:美国

出处:管理科学与工程.2010.03.20

随着市场竞争的激烈性越来越大,在每一个项目中,进行成本控制越发重要。本文论述了在施工阶段,项目经理如何成功地控制项目预算成本。本文讨论了很多方法。它表明,要取得成功,项目经理必须关注这些成功的方法。

1.简介

调查显示,大多数项目会碰到超出预算的问题(Williams Ackermann, Eden, 2002,pl92)。据Wright(1997)的研究,一个好的经验法则就是相比首次成本预算至少会增加50%(Gardiner and Stewart, 1998, p251)。这表明,项目是非常复杂并且充满挑战的。很多意想不到的因素会导致项目成本的增加。因此,许多科学技术和方法被应用于监测和控制成本来促使项目的成功。在这篇文章中,我们将讨论在施工阶段,项目经理如何才能成功控制预算成本。

2.项目控制和监测的概念和目的

Erel and Raz (2000)指出项目控制周期包括测量成本是实际情况,将施工成本的实际值和计划值进行比较,对比较结果进行分析,并采取适当的措施来纠正偏差。项目在施工阶段的监测和控制对于项目的成功是至关重要的。为了采取正确的纠偏措施需要建立项目监测机制,同时这样做也可以有时间来采取措施。通过监测手段,项目团队可以分析偏差产生的原因以及决定纠偏措施并采取行动。监控的目的就是纠偏措施的实施,确保项目控制在计划目标内或者使已经偏离计划的回到目标范围内。

3.建立一个有效的控制体系

为了实现预算成本的目标,项目管理者需要建立一个高效的管理框架,包括:报告的结构,评估的进展情况以及沟通体系。在报告结构中,雇员的责任和权力应该要清楚地被定义。正式的和非正式的评估可以帮助实际和目标之间大体上保持一致,且这对于确定什么是风险以及哪些需要被监测和控制是非常有帮助的。项目成功与良好的沟通密切相关,一个高效率的沟通体系有利于团队协作并促进问题的解决( Diallo and Thuillier, 2005)。

4.成本费用的检测和控制

4.1对检测的优先顺序进行排序

在施工阶段,很多施工活动是基于原来的计划。它需要清楚什么样的活动或者哪些东西是最有可能导致项目延误和不受控制的。因此,第一步就是要对这些活动进行优先排序。由于项目的工期是由关键路径上的关键工作的总时间决定的,任何关键路径上工作的延迟将导致项目工期的拖延(Ackermann Eden, Howick and Williams,2000,p295)。因此,关键路径上的工作应该首先进行检测和控制。其次,检测没有自由时差浮动的工作,任何没有自由时差工作的延误将导致其后续工作的拖延,这些后续工作的延误将对资源分配安排带来影响,有些资源被分配到特定的工作是不可以变更利用的。第三,检测具有较少浮动时间的工作,因为,如果一个工作具有非常少的浮动时间,那么当它偏离目标的时候很有可能在还没有采取控制措施前就将浮动时间用完了。第四,项目管理者应该检测高风险活动,高风险活动最有可能超支。第五,管理者应该检测项目活动中使用的关键资源,有些资源由于是非常昂贵和有限的而至关重要(Cotterell and Hughes, 1995)。

4.2成本控制的方法

一个项目的主要费用包括员工成本、材料成本以及工期延误的成本。为了控制这些成本费用,项目管理者首先应该建立一个成本控制系统:

a) 为财务数据的管理和分析工作落实责任人员

b) 确保按照项目的结构来合理分配所有的成本

c) 确保所有成本都是项目进展过程中各项活动的真实支出

d) 检查其它工程项目没有使用此项目预算

然后,项目管理者应该对项目预算进行监督和控制变更。这意味着以下几点:a) 关注可以引起成本变化的主要因素

b) 控制实际成本的变化

--监测成本发生情况来发现它的变化

--在成本控制线上准确地记录所有恰当的成本变动

--为防止出现错误,没有经过允许的成本变化也应该体现在成本控制线上--确定积极地和消极的成本变化

--与其它控制目标(范围、变更、进度、质量)相结合

由于一个工程项目是动态变化的,有时项目经理通过监测知道项目成本正在偏离预算,但是却不知道采取什么措施来控制。在这种情况下,净现值(NPV)能够被用来作为一种持续监控的方法,因为净现值考虑了时间的因素来对未来现金流折现,它是现金流考虑时间价值影响后的结果。

4.3变化的检测和控制

Voropajev (1998)指出,施工环境的动态变化将会影响项目的实施过程、项目本身以及增加项目风险的可能性。当在开展施工活动的时候,不同于原计划的各种方法必须被应用来保持项目向前推进(根据实践经验)。因此,变化是不可避免的,需要在项目的整个生命周期过程中管理和控制变化(Voropajev. 1998,p 16- 17)。为了确保变更程序是明确和毫不含糊的以及方便施工人员提出要求发生改变,应该建立一个有效的变更控制体系。可以从以下几个方面考虑:

a) 为确保良好的结果,应检测和预测最有可能发生变更的主要因素,应该保证变更必须由合适的人员检查

b)一旦被批准,变更应该发生并对此进行监测以检查是否按预期工作

c)项目的所有变更应该被记录在项目文件资料中(Voropajev, 1998,pl8)

5.结论

本文介绍了控制预算的最佳方法。首先,必须建立一个高效率的监管控制体系;其次,它必须包括影响成本预算目标的主要因素并将它按照重要性排序;第三,项目管理者应该结合不同的科学控制方法以达到项目的成功。

工程管理中英文对照外文翻译文献

中英文对照外文翻译文献 中英文对照外文翻译 The Internet is Applicated in Real Estate The Real Estate Industry and the World Wide Web: Changing Technology, Changing Location.The Internet, in its Web based graphics version, has captured the imagination of both consumers and businesses. Its convenience, speed, low cost and versatility are being exploited on a daily basis in ever-changing ways. Together with its capacity to transform existing businesses, promote new businesses and facilitate exchange of information and data, its other striking attribute has been the speed with which this new technology has spread throughout the global economy. Keywords:The internet;Real Estate;Applicated The number of computer hosts grew by more than ten-fold between 1995 and early 1999. The number of Web sites increased almost 100-fold, to over two million, between 1995 and 1998.By the year 2000, there will be approximately 400-500 million Internet users in the world, and the total number of Web sites will exceed five million. This new technology has the potential for affecting the real estate industry directly and indirectly. Directly, it may become a tool that allows a real estate business to expand its information and sales network. Indirectly, it may change the location equation where and how firms do business which in turn will affect the role of firms involved in real estate development, investment and transactions. Measuring the Spread of the Web

【机械类文献翻译】步进电机和伺服电机的系统控制

Step Motor Motor&&Servo Motor Systems and Controls Motion Architect?Software Does the Work for You...Configure,Diagnose,Debug Compumotor’s Motion Architect is a Microsoft?Windows?-based software development tool for6000Series products that allows you to automatically generate commented setup code,edit and execute motion control programs,and create a custom operator test panel.The heart of Motion Architect is the shell,which provides an integrated environment to access the following modules. ?System Configurator—This module prompts you to fill in all pertinent set-up information to initiate motion.Configurable to the specific6000Series product that is selected,the information is then used to generate actual6000-language code that is the beginning of your program. ?Program Editor—This module allows you to edit code.It also has the commands available through“Help”menus.A user’s guide is provided on disk. ?Terminal Emulator—This module allows you to interact directly with the6000product.“Help”is again available with all commands and their definitions available for reference.?Test Panel—You can simulate your programs,debug programs,and check for program flow using this module. Motion Architect?has been designed for use with all6000Series products—for both servo and stepper technologies.The versatility of Windows and the6000Series language allow you to solve applications ranging from the very simple to the complex. Motion Architect comes standard with each of the6000Series products and is a tool that makes using these controllers even more simple—shortening the project development time considerably.A value-added feature of Motion Architect,when used with the6000 Servo Controllers,is its tuning aide.This additional module allows you to graphically display a variety of move parameters and see how these parameters change based on tuning values. Using Motion Architect,you can open multiple windows at once.For example,both the Program Editor and Terminal Emulator windows can be opened to run the program,get information,and then make changes to the program. On-line help is available throughout Motion Architect,including interactive access to the contents of the Compumotor6000Series Software Reference Guide. SOLVING APPLICATIONS FROM SIMPLE TO COMPLEX Servo Control is Yours with Servo Tuner Software Compumotor combines the6000Series servo controllers with Servo Tuner software.The Servo Tuner is an add-on module that expands and enhances the capabilities of Motion Architect?. Motion Architect and the Servo Tuner combine to provide graphical feedback of

酒店服务质量管理外文文献翻译

文献出处:Borkar S, Koranne S. Study of Service Quality Management in Hotel Industry [J]. Pacific Business Review International, 2014, 6(9): 21-25. 原文 Study of Service Quality Management in Hotel Industry Borkar; Sameer Abstract It is an attempt to understand the role of quality improvement process in hospitality industry and effectiveness in making it sustainable business enterprise. It is a survey of the presently adopted quality management tools which are making the hotels operations better focused and reliable and meet the customer expectations. Descriptive research design is used to know the parameters of service quality management in hospitality industry. Exploratory research design is undertaken to dig out the service quality management practices and its effectiveness. Data analysis is done and presented; hypothesis is tested against the collected data. Since the industry continuously tries to improve upon their services to meet the levels of customer satisfaction; Study presents tools for continuous improvement process and how it benefits all the stake holders. It can be inferred from the study that the hotel implement continuous improvement process and quality management tools to remain competitive in the market. The study involves hotels of highly competitive market with limited number of respondents. This limits the study to hotel industry and has scope of including other hospitality service providers as well. Keywords:Customer Satisfaction, Perception, Performance Measurement, Continuous, Improvement Process. Introduction It has brought paradigm shifts in the operations of hospitality industry. The overall perspective of the industry is changed due to introduction of new techniques

数控加工外文翻译

数控加工中心技术发展趋势及对策 原文来源:Zhao Chang-ming Liu Wang-ju (CNC Machining Process and equipment, 2002,China) 一、摘要 Equip the engineering level, level of determining the whole national economy of the modernized degree and modernized degree of industry, numerical control technology is it develop new developing new high-tech industry and most advanced industry to equip (such as information technology and his industry, biotechnology and his industry, aviation, spaceflight, etc. national defense industry) last technology and getting more basic most equipment. Numerical control technology is the technology controlled to mechanical movement and working course with digital information, integrated products of electromechanics that the numerical control equipment is the new technology represented by numerical control technology forms to the manufacture industry of the tradition and infiltration of the new developing manufacturing industry, Keywords:Numerical ControlTechnology, E quipment,industry 二、译文 数控技术和装备发展趋势及对策 装备工业的技术水平和现代化程度决定着整个国民经济的水平和现代化程度,数控技术及装备是发展新兴高新技术产业和尖端工业(如信息技术及其产业、生物技术及其产业、航空、航天等国防工业产业)的使能技术和最基本的装备。马克思曾经说过“各种经济时代的区别,不在于生产什么,而在于怎样生产,用什么劳动资料生产”。制造技术和装备就是人类生产活动的最基本的生产资料,而数控技术又是当今先进制造技术和装备最为核心的技术。当今世界各国制造业广泛采用数控技术,以提高制造能力和水平,提高对动态多变市场的适应能力和竞争能力。此外,世界上各工业发达国家还将数控技术及数控装备列为国家的战

供应商质量管理文献翻译(外文翻译-中英对照)

互利共赢的供应商质量控制 前言 近年来,随着对供应链的重视,供应商管理正逐渐成为企业和学术界的关注对象,IS09000族标准以及QS 9000标准都对供应商的管理提出了相应的要求,与供应商管理有关的研究成果正逐渐增多,一些软件巨头也推出了供应商关系管理的软件,但是在这些研究成果和应用软件中,涉及到的供应商质量控制的内容只是一些最基本的要求,而供应商质量控制恰恰是供应商管理的最基本、最重要的内容。另一方而,质量管理界对质量控制的研究取得了大量的成果,遗憾的是这些成果大多依然局限于企业的内部控制,仅仅研究从企业内部各环节如何改善产品的质量,而基于供应链的角度来研究质量控制的成果尚不多见。因此,系统地研究经济全球化形势下供应商质量控制的理论与方法,将有助于推动我国企业产品质量的快速提高和供应链竞争优势的形成与巩固。 1、质量与企业共存 质量一直是一个随着时代的变化而不断变化的概念,人们对质量的认识也往往因关注点不同而有所不同。如,早在1908年,通用汽车公司的工程师们在皇家汽车俱乐部会员们的面前拆解了3辆凯迪拉克轿车,并把这些零件混在一起,而后从中选择零件重新组装成车,然后驾车绝尘而去。这令在场的会员极为震惊,认为凯迪拉克车质量之高令人惊叹。显然在当时,汽车零件具有互换性是一种了不起的质量特性,这也是福特公司的N型车和T型车取得辉煌成功的重要原因.时至今日,即使农用三轮车的零部件也具有极高的互换性,零部件的标准化和互换性已经是理所当然的事情,不再是吸引顾客的重要质量特性.可见质量的内涵是不断变化的.那么究竟什么是质量呢? (1)市场竟争就是企业间对“顾客”的争夺,在日益激烈的“顾客"争夺战中,质量、价格、交付(交付日期、方式和手段)和服务是企业常用的四个法宝,其中质量是根本,离开质量其他三项将变得毫无意义,因此可以说质量己成为市场竞争的焦点.它反映了产品是否能够反映顾客需求、能否满足顾客需求,从面决定了产品的市场前途。有鉴于此,质量己成为一项全球性运动,世界上所有优秀企业无一不把质量作为企业战略的关键内容,从战略的角度来规划质量。 (2)对于企业经营者来说,认识到质量对企业的重要意义只是经营企业的第一步,重要的是如何利用科学的方法来保证产品和服务的质量,使顾客满意,来保证过程和工作的质量来获互利共炭的供应商质量控制得良好的业绩。 众所周知,企业管理是社会生产力发展到一定程度的历史产物,质量管理作为企业管理的组成部分,同样也是社会发展的客观要求,特别是顾客处于主导地位的今天,要使顾客满意,就必须有过硬的产品质量和服务质量,这就要求企业积极推行先进的质量管理理论与方法,不断进行质量管理创新. 2、企业与供应商质量控制 随着生产社会化的不断发展,企业的生产活动分工越来越细,专业化程度越来越强,促使生产技术水平越来越高,产品质量得到大幅度改善。通常,某一产品不可能由一个企业从最初的原材料开始加工直至形成顾客最终使用的产品,往往是通过多个企业分工协作来完成.另外,先进生产方式的广泛应用,如准时生产、敏捷制造、零库存等,使企业与供应商的关系愈加紧密,企业与供应商的关系也由单纯的买卖关系向互利共底的合作关系演变。 ISO 9000族标准自1987年诞生以来受到了世界各国的一致追捧,全球约50多万家企业通过ISO9001质量管理体系认证足以说明这套管理标准在引领国际管理潮流方面的巨大成功。在备受企业欢迎的新版标准ISO9000:2000中,互利的供应商关系被作为八项质量管理原则之一,充分体现了供应商关系管理在企业经营实践中的作用和价值。企业要贯彻这一原则,就必须

外文文献翻译——参考格式

广东工业大学华立学院 本科毕业设计(论文) 外文参考文献译文及原文 系部经济学部 专业经济学 年级 2007级 班级名称 07经济学6班 学号 16020706001 学生姓名张瑜琴 指导教师陈锶 2011 年05月

目录 1挑战:小额贷款中的进入和商业银行的长期承诺 (1) 2什么商业银行带给小额贷款和什么把他们留在外 (2) 3 商业银行的四个模型进入小额贷款之内 (4) 3.1内在的单位 (4) 3.2财务子公司 (5) 3.3策略的同盟 (5) 3.4服务公司模型 (6) 4 合法的形式和操作的结构比较 (8) 5 服务的个案研究公司模型:厄瓜多尔和Haiti5 (9)

1 挑战:小额贷款中的进入和商业银行的长期承诺 商业银行已经是逐渐重要的运动员在拉丁美洲中的小额贷款服务的发展2到小额贷款市场是小额贷款的好消息客户因为银行能提供他们一完整类型的财务的服务,包括信用,储蓄和以费用为基础的服务。整体而言,它也对小额贷款重要,因为与他们广泛的身体、财务的和人类。如果商业银行变成重的运动员在小额贷款,他们能提供非常强烈的竞争到传统的小额贷款机构。资源,银行能廉宜地发射而且扩张小额贷款服务rela tively。如果商业广告银行在小额贷款中成为严重的运动员,他们能提出非常强烈的竞争给传统的小额贷款机构。然而,小额贷款社区里面有知觉哪一商业银行进入进入小额贷款将会是短命或浅的。举例来说,有知觉哪一商业银行首先可能不搬进小额贷款因为时候建立小额贷款操作到一个有利润的水平超过银行的标准投资时间地平线。或,在进入小额贷款,银行之后可能移动在-上面藉由增加贷款数量销售取利润最大值-或者更坏的事,退出如果他们是不满意与小额贷款的收益性的水平。这些知觉已经被特性加燃料商业银行的情形进入小额贷款和后来的出口之内。在最极端的,一些开业者已经甚至宣布,”降低尺度死!”而且抛弃了与主意合作的商业银行。 在最 signific 看得到的地方,蚂蚁利益商业银行可能带给小额贷款,国际的ACCION 发展发射而且扩张的和一些商业银行的关系小额贷款操作。在这些情形的大部分方面, ACCION 和它的合伙人正在使用方法,已知的当做服务公司模型,表演早答应当做一个能工作的方法克服真正的。 商业银行的障碍进入和穿越建立长命的小额贷款操作一个商业银行 这论文描述如何服务公司模型、住址商业银行中的主要议题进入进小额贷款,监定成功建立的因素动作井小额贷款服务公司,和礼物结果和小额贷款的课servic e 公司用最长的经验,在海地和审判官席 del 的 SOGEBANK│ SOGESOL 初期结果指出那这服务公司模型表现一重要的突破在促成商业银行进入和留在小额贷款。在厄瓜多尔的 Pichincha│ CREDIFE。初期结果指出服务公司模型在促成商业广告中表现一次重要的突破银行进入而且留在小额贷款。

伺服电机外文文献翻译

伺服电机 1. 伺服电机的定义 伺服电动机又称执行电动机,在自动控制系统中,用作执行元件,把所收到的电信号转换成电动机轴上的角位移或角速度输出。分为直流和交流伺服电动机两大类,其主要特点是,当信号电压为零时无自转现象,转速随着转矩的增加而匀速下降。伺服电机在伺服系统中控制机械元件运转的发动机. 是一种补助马达间接变速装置。伺服电机可使控制速度, 位置精度非常准确。将电压信号转化为转矩和转速以驱动控制对象。转子转速受输入信号控制,并能快速反应,在自动控制系统中作执行元件,且具有机电时间常数小、线性度高、始动电压低等特点。 2. 伺服电机工作原理 1.伺服主要靠脉冲来定位,基本上可以这样理解,伺服电机接收到1 个脉冲,就会旋转1 个脉冲对应的角度,从而实现位移,因为,伺服电机本身具备发出脉冲的功能,所以伺服电机每旋转一个角度,都会发出对应数量的脉冲,这样,和伺服电机接受的脉冲形成了呼应,或者叫闭环,如此一来,系统就会知道发了多少脉冲给伺服电机,同时又收了多少脉冲回来,这样,就能够很精确的控制电机的转动,从而实现精确的定位,可以达到0.001mm有刷电机成本低,结构简单,启动转矩大,调速范围宽,控制容易,需要维护,但维护方便(换碳刷),产生电磁干扰,对环境有要求。无刷电机体积小,重量轻,出力大,响应快,速度高,惯量小,转动平滑,力矩稳定。控制复杂,容易实现智能化,其电子换相方式灵活,可以方波换相或正弦波换相。电机免维护,效率很高,运行温度低,电磁辐射很小,长寿命,可用于各种环境。 2. 交流伺服电机也是无刷电机,分为同步和异步电机,目前运动控制中一般都用同步电机,它的功率范围大,可以做到很大的功率。大惯量,最高转动速度低,且随着功率增大而快速降低。因而适合做低速平稳运行的应用。 3. 永磁交流伺服电动机简介 20 世纪80 年代以来,随着集成电路、电力电子技术和交流可变速驱动技术的发展,永磁交流伺服驱动技术有了突出的发展,各国著名电气厂商相继推出各自的交流伺服电动机和伺服驱动器系列产品并不断完善和更新。交流伺服系统已成为当代高性能伺服系统的主要发展方向,使原来的直流伺服面临被淘汰的危机。90 年代以后,世界各国已经商品化了的交流伺服系统是采用全数字控制的正弦

质量管理文献综述

关于企业质量管理文献综述 摘要:随着新世纪的到来,特别是我国加入WTO后,中国将进一步融入世界经济的主流,质量将成为我国广大企业抓住机遇、迎接严峻挑战的关键。要拓展海外市场,必须靠有竞争力的质量;要保护国内的市场,不再有高关税和政府的过渡保护,也要靠质量的较量。随着科学技术的进步,质量管理的理论和方法有了更大发展。本文综合了质量管理的发展历程,并简要评价,提出看法,以便为企业的质量管理和理论研究提供参考。 关键词:质量管理、管理改进 21世纪是质量的世纪”。随着经济全球化和信息革命的迅猛发展,竞争日益加剧。在“数量”问题已解决的今天,人们将越来越追求和依赖于高质量的产品和服务,而且质量的领域不断拓宽,生活的质量、环境的质量、文化的质量、经济增长的质量更加受到全社会的关注。质量已成为竞争的焦点,不仅关系到企业的生存发展,而且影响到国家经济实力的增强和民族的形象。质量已成为全球经济发展战略的核心问题。 一、质量管理理论的回顾 (一)、质量管理的发展阶段 (1)质量检验阶段(20世纪20-30年代) 生产力迅猛发展,生产过程分工细化、日益复杂,许多美国企业按照泰勒的管理模式,纷纷设立检验部门,使检验与生产分离开来,其最大特点为“事后把关”。(2)统计质量阶段(20世纪40-50年代) 早在20世纪20年代,美国贝尔实验室工程师休哈特就提出“控制与预防缺陷”的概念。主要是利用数理统计原理,预防产生废品并检验产品质量,在方式上由专业质量控制工程师和技术人员承担。但这种方法只是保证生产过程中的产品质量,而不能提高产品本身的质量。 (3)全面质量管理阶段(20世纪60年代至今) 美国的费根堡姆提出,“全面质量是为了能够在最经济的水平上,并考虑到充分满足顾客要求的条件下进行生产和提供服务,将企业各部门研制质量、维持质量和提高质量的活动构成为一体的一种有效体系”。 (二)、质量管理的理论流派 1、事后检验 20世纪,美国工程师泰勒提出“科学管理理论”,1911 年泰勒出版了专

工程管理专业研究建设项目的工程造价大学毕业论文外文文献翻译及原文

毕业设计(论文) 外文文献翻译 文献、资料中文题目:研究建设项目的工程造价 文献、资料英文题目: 文献、资料来源: 文献、资料发表(出版)日期: 院(部): 专业:工程管理 班级: 姓名: 学号: 指导教师: 翻译日期: 2017.02.14

科技文献翻译 题目:研究建设项目的工程造价 研究建设项目的工程造价 摘要 在工程建设中,中国是拥有世界最大投资金额和具有最多建设项目的国家。它是一 项在建设项目管理上可以为广泛的工程管理人员进行有效的工程造价管理,并合理 确定和保证施工质量和工期的条件控制施工成本的重要课题。 在失去了中国建筑的投资和技术经济工程,分离的控制现状的基础上,通过建设成 本控制的基本理论为指导,探讨控制方法和施工成本的应用,阐述了存在的问题在 施工成本控制和对决心和施工成本的控制这些问题的影响,提出了建设成本控制应 体现在施工前期,整个施工过程中的成本控制,然后介绍了一些程序和应用价值工 程造价的方法在控制建设项目的所有阶段。 关键词:建设成本,成本控制,项目 1.研究的意义 在中国,现有的工程造价管理体系是20世纪50年代制定的,并在1980s.Traditional 施工成本管理方法改进是根据国家统一的配额,从原苏联引进的一种方法。它的特 点是建设成本的计划经济的管理方法,这决定了它无法适应当前市场经济的要求。 在中国传统建筑成本管理方法主要包括两个方面,即建设成本和施工成本控制方法 的测定方法。工程造价的确定传统的主要做法生搬硬套国家或地方统一的配额数量 来确定一个建设项目的成本。虽然这种方法已经历了20多年的改革,到现在为止,计划经济管理模式的影响仍然有已经存在在许多地区。我们传统的工程造价控制的

中英文文献翻译-加工中心数控技术

加工中心数控技术 出处:数控加工中心的分类以及各自特点 出版社:化学工业出版社; 第1版 (2009年3月16日) 作者:徐衡、段晓旭 加工中心是典型的集高技术于一体的机械加工设备,它的发展代表了一个国家设计制造的水平也大大提高了劳动生产率,降低了劳动成本,改善了工人的工作环境,降低了工人的劳动强度。本文经过对不同运动方案和各部件的设计方案的定性分析比较确定该教立式加工中心的进给传动方案为:采用固定床身,电主轴通过安装座安装在床身导轨的滑座上,床身导轨采用滚动导轨,可以实现Y 方向的进给运动。由X-Y双向精密数控工作台带动工件完成X,Y两个方向的进给运动;X,Y,Z三个方向的进给运动均滚珠丝杠,并由交流伺服电机驱动。导轨、滚珠丝杠有相应的润滑、防护等装置。 加工中心(英文缩写为CNC 全称为Computerized Numerical Control):是带有刀库和自动换刀装置的一种高度自动化的多功能数控机床。在中国香港,台湾及广东一代也有很多人叫它电脑锣。 工件在加工中心上经一次装夹后,数字控制系统能控制机床按不同工序,自动选择和更换刀具,自动改变机床主轴转速、进给量和刀具相对工件的运动轨迹及其他辅助机能,依次完成工件几个面上多工序的加工。并且有多种换刀或选刀功能,从而使生产效率大大提高。 加工中心数控机床是一种装有计算机数字控制系统的机床,数控系统能够处理加工程序,控制机床完成各种动作。与普通机床相比,数控机床能够完成平面曲线和空间曲面的加工,加工精度和生产效率都比较高,因而应用日益广泛。 数控机床的组成 一般来说,数控机床由机械部分、数字控制计算机、伺服系统、PC控制部分、液压气压传动系统、冷却润滑和排泄装置组成。数控机床是由程序控制的,零件的编程工作是数控机床加工的重要组成部分。伺服系统是数控机床的驱动部分,计算机输出的控制命令是通过伺服系统产生坐标移动的。普通的立式加工中心有三个伺服电机,分别驱动纵向工作台、横向工作台、主轴箱沿X向、Y向、Z向运动。X、Y、Z是互相垂直的坐标轴,因而当机床三坐标联动时可以加工空

工程管理专业外文翻译--项目成本控制剖析(可编辑修改word版)

项目成本控制 1施工企业成本控制原则 施工企业的成本控制是以施工项目成本控制为中心,施工项目成本控制原则是企业成本管理的基础和核心,施工企业项目经理部在对项目施工过程进行成本控制时,必须遵循以下基本原则。 1.1成本最低化原则。施工项目成本控制的根本目的,在于通过成本管理的各种手段,促进不断降低施工项目成本,以达到可能实现最低的目标成本的要求。在实行成本最低化原则时,应注意降低成本的可能性和合理的成本最低化。一方面挖掘各种降低成本的能力,使可能性变为现实;另一方面要从实际出发,制定通过主观努力可能达到合理的最低成本水平。 1.2全面成本控制原则。全面成本管理是全企业、全员和全过程的管理,亦称“三全”管理。项目成本的全员控制有一个系统的实质性内容,包括各部门、各单位的责任网络和班组经济核算等等,应防止成本控制人人有责,人人不管。项目成本的全过程控制要求成本控制工作要随着项目施工进展的各个阶段连续进行,既不能疏漏,又不能时紧时松,应使施工项目成本自始至终置于有效的控制之下。 1.3动态控制原则。施工项目是一次性的,成本控制应强调项目的中间控制,即动 态控制。因为施工准备阶段的成本控制只是根据施工组织设计的具体内容确定成本目标、编制成本计划、制订成本控制的方案,为今后的成本控制作好准备。而竣工阶段的成本控制,由于成本盈亏已基本定局,即使发生了偏差,也已来不及纠正。 1.4目标管理原则。目标管理的内容包括:目标的设定和分解,目标的责任到位和执行,检查目标的执行结果,评价目标和修正目标,形成目标管理的计划、实施、检查、处理循环,即 PDCA 循环。 1.5责、权、利相结的原则。在项目施工过程中,项目经理部各部门、各班组在肩负成本控制责任的同时,享有成本控制的权力,同时项目经理要对各部门、各班组在成本控制中的业绩进行定期的检查和考评,实行有奖有罚。只有真正做好责、权、利相结合的成本控制,才能收到预期的效果。

机械手外文翻译 修改版

密级 分类号 编号 成绩 本科生毕业设计 (论文) 外文翻译 原文标题Simple Manipulator And The Control Of It 译文标题简易机械手及控制 作者所在系别机械工程系 作者所在专业xxxxx 作者所在班级xxxxxxxx 作者姓名xxxx 作者学号xxxxxx 指导教师姓名xxxxxx 指导教师职称副教授 完成时间2012 年02 月 北华航天工业学院教务处制

译文标题简易机械手及控制 原文标题 Simple Manipulator And The Control Of It 作者机电之家译名JDZJ国籍中国 原文出处机电之家 中文译文: 简易机械手及控制 随着社会生产不断进步和人们生活节奏不断加快,人们对生产效率也不断提出新要求。由于微电子技术和计算软、硬件技术的迅猛发展和现代控制理论的不断完善,使机械手技术快速发展,其中气动机械手系统由于其介质来源简便以及不污染环境、组件价格低廉、维修方便和系统安全可靠等特点,已渗透到工业领域的各个部门,在工业发展中占有重要地位。本文讲述的气动机械手有气控机械手、XY轴丝杠组、转盘机构、旋转基座等机械部分组成。主要作用是完成机械部件的搬运工作,能放置在各种不同的生产线或物流流水线中,使零件搬运、货物运输更快捷、便利。 一.四轴联动简易机械手的结构及动作过程 机械手结构如下图1所示,有气控机械手(1)、XY轴丝杠组(2)、转盘机构(3)、旋转基座(4)等组成。 图1.机械手结构 其运动控制方式为:(1)由伺服电机驱动可旋转角度为360°的气控机械手(有光电传感器确定起始0点);(2)由步进电机驱动丝杠组件使机械手沿X、Y轴移动(有x、y轴限位开关);(3)可回旋360°的转盘机构能带动机械手及丝杠组自由旋转(其电气拖动部分由直流电动机、光电编码器、接近开关等组成);(4)旋转基座主要支撑以上3部分;(5)气控机械手的张合由气压控制(充气时机械手抓紧,放气时机械手松开)。 其工作过程为:当货物到达时,机械手系统开始动作;步进电机控制开始向下

质量管理文献综述

食品质量管理文献综述 工程114 31111420 王春月 摘要:针对今年我国食品安全事件的频发,本文主要从食品质量管理的定义、现状原因、体系结构、对策及趋势展望等方面对食品质量管理进行了研究,将众多学者对食品质量管理的一些观点进行梳理,以期全面的认识食品质量管理。同时也求得人们的广泛关注,实现真正的食品安全。 关键词:食品安全质量管理 引言:20世纪90年代以来,消费者对的食品质量安全问题越来越重视,然而近些年我国的食品质量安全问题却不容乐观,作为一个发展中国家,我国的食品质量安全问题表现尤为突出。“毒奶粉”、“瘦肉精”、“地沟油”、“染色馒头”、“塑化剂”等字眼铺天盖地而来,人们几乎达到了谈“食”色变的地步。这些食品安全事件的爆发激起了全社会对食品企业社会责任的关注,对食品质量管理的重视。从整个战略层面看,这一系列重大食品质量安全事件威胁的不仅仅是人们的身心健康和生命安全,更为严重的是它严重损害我国食品生产与贸易的健康持续发展,降低了我国食品的国际信誉,制约了其国际竞争力的提升。为了从根本上解决食品质量安全问题,创造一个良好的食品消费环境就必须进行食品质量管理。 一、相关概念 食品安全指食品无毒、无害,符合应当有的营养要求,对人体健康不造成任何急性、亚急性或者慢性危害。李正明(2003)认为,所有食品在正常摄取时必须确保安全,任何不符合卫生要求的东西,不能成为合法销售的食品。因此不存在普通食品、有机食品、绿色食品、谁比谁更安全的问题。 食品质量的定义,高新宇(2011)认为,食品是用来满足不同消费者,明确的或者隐含的食品的全部特性。食品质量策划、食品质量控制、食品质量保证与改进实施的全部管理职能的所有活动,高新宇将这些活动统称为食品的质量管理。食品质量管理体系的目标是:第一、管理部门要及时预防食源性疾病的产生,从而保护公众健康;第二、通过杜绝有误导倾向的食品、不卫生的、甚至是有毒

工程造价管理论文中英文对照资料外文翻译文献

中英文对照资料外文翻译文献 工程造价管理前沿 摘要:工程造价管理的基本内容,确定合理和有效控制工程造价。描述现阶 段的工程造价管理的情况,加强了各阶段的工程造价管理工作的重要性,并 提出了若干关键性举措。 关键词:建设成本;建设工程造价管理的地位;市场经济条件下管理投资 的决策阶段;设计阶段;实施阶段; 1前言 即使在世贸组织和中国加入世界大家庭, 是中国建筑业如何有效地控制工程造价的建设和管理的一个重要组成部分。然而,目前的年度预算为建设项目-概算,预算,超预算的"三超"现象仍然普遍存在,最终导致了严重失控项目投资。工程造价管理的基本内容,就是合理确定和有效控制工程造价。 作为这项工程的费用,以项目贯穿整个过程中, 按阶段可分为:投资决策阶段,设计和实施阶段。所谓工程造价的有效控制, 在优化建设方案,设计方案的基础上,在建设过程的所有阶段使用某些方法和措施,以降低工程成本有一个合理控制的范围和成本的核定限额。 2 工程造价管理工作的现状 工程造价管理制度形成于50年代, 80年代成熟起来,表现为国家直接参与管理经济活动。规定在设计阶段,以不同的概算或预算的编制以及政府,没有有关部门制订财政预算案、内容、方法和审批, 这份预算案将提供固定费用、设备和材料,采用固定价格的预算编制、审批、管理权限,等等。 随着历史进程经过恢复、改革和发展,形成了比较完备的概预算定额管理制度。但是,随着社会主义市场经济的发展,制度的许多问题也暴露出来。一般来说,预算是基于直接参与管理国家的经济活动作为先决条件,企业并不是实际的

经济实体,由于特征的计划经济体制,并在当时的条件下,生产力必将成为短缺经济。 严重的商品短缺的情况下,只要有一定程度的投资将产品产出。在这种环境下,项目的规划和技术论证就不可能有经济分析。国家控制的项目成本构成要素的设备和材料价格。在这种相对稳定的经济环境,财政预算的制度,核定工程造价, 帮助政府进行投资计划方面发挥了重大作用。 随着社会主义市场经济体制的确立,要求我们以预测项目的投资和控制。近年来,国际投资项目的发展要求,事前预控,事中控制。中国传统的做法,从客观的角度对事业的决策,执行重,轻经济。 首先,由于技术人员的工程技术和经济观念和意识淡薄成本控制,成本管理,使质量难以提高。工程造价控制是很难达到的长远目标。 第二,各个阶段的项目管理鉴于上述情况,我国在八十年代提出了全过程的 成本管理与控制的概念,建设部门将进行可行性研究和项目的预算和决算等,以 扩大两国的请求的相应规定,我们把成本管理的观念和方法提到了一个新高度。 我们现在的任务是要与现代成本管理的,符合中国国情的市场经济的系统目标,借鉴先进发达国家的经验, 建立健全市场经济规律的工程造价管理体系,努 力提高工程造价的水平。 投资决策阶段的工程造价管理建设项目投资决策阶段是提出项目建议书, 进行了可行性研究,确定投资估算,最终编制设计任务。在这个阶段,项目的技术和经济决策, 对建设项目工程造价的工程完成后的经济效益有着决定性的影响,建造成本是一个重要的阶段控制。 我国现阶段的工程造价进行的项目管理的目的是出清价,只注重施工过程的成本控制, 忽略开始的项目投资决策阶段的成本控制。投资决策阶段的投资项目,估计是一个重要的决策依据。它直接影响到国民经济及财务分析结果的可靠性和准确性。因为这个阶段是工程的前期工作,信息不能完全, 同类作品或多或少地积累的资料比较少,估计不够全面,不科学。使工程造价管理和成本工人现阶段很难有所作为。 各个阶段的工程造价控制在决策阶段的工程造价控制。权项目规划阶段的成本,许多业主有错误的理解,降低成本,更好。控制成本,而不是单方面问题,而应该是一个多因素的影响,结合实际,全面考虑。建设项目的投资决策阶段,项目的技术和经济决策,工程造价后,工程的竣工和经济效益,有决定性作用,在项目成

建筑行业全面质量管理外文文献翻译2019-2020

建筑行业全面质量管理外文翻译2019-2020 英文 The Total Quality Management (TQM) journey of Malaysian building contractors Idris Othman, Siti Ghani, Shim Woon Choon Abstract Malaysian Government has announced that for construction industry to transform by 2020, quality in construction is needed to be improved. Total Quality Management (TQM) could facilitate this motive. Thus, the purpose of this research is to identify, rank and analyze the factors affecting TQM implementation in a construction company so that industrial practitioners avoid poor quality products. A case study concept was used and a questionnaire survey was collected from 32 respondents. The reliability test was conducted using Cronbach's Alpha Coefficient. Employee related factor was identified to be the most crucial factors affecting TQM implementation. Contractor group of respondents showed excellent level of internal consistency (overall reliability) with the validation value of 0.956 using Cronbach’s Alpha Coefficient. In conclusion this research able to give a series of recommendation and a clear quality management which can be followed by the industry practitioners to ensure that Total Quality Management can be implemented.

相关主题