1、钢结构工程Steel Project

1.1钢结构焊接 Welded Steel

1.1.1工艺流程作业准备→电弧焊接(平焊、立焊、横焊、仰焊)→焊缝检查

Process Ready to work→Arc Weld(Flat Welding、Stand Welding、

Sidelong Welding 、Welding belief) →Weld inspection

1.1.2钢结构电弧焊接:

Arc Welding Steel:

1.1.

2.1平焊:选择合适的焊接工艺,焊条直径,焊接电流,焊接速度,焊接电弧长

度等,通过焊接工艺验证;清理焊口:焊前检查坡口、组装间隙是否符合要求,定位焊是否牢固,焊缝周围不得有油污、锈物;烘焙焊条应符合规定温度与时间,从烘箱中取出的焊条,放在焊条保温桶内,随用随取;焊拉电源:根据焊件厚度、焊接层次、焊条型号、直径、焊工熟练程度等因素,选择适宜的焊接电流;

引弧:角焊缝起落弧点应在焊缝端部,宜大于10㎜,不应随便打弧,打火引弧

后应立即将焊条从焊缝区拉开,使焊条块结合与构件间保持2~4㎜间隙产生电

弧。对接焊缝及对接和角接组合焊缝,在焊缝两端设引弧板和引出板,必须在

引弧板上引出后再焊到焊缝区,中途接头则应在焊缝接头前方15~20㎜处打

火引弧,将焊件预热后再将焊条退回到焊缝起始处,把熔池填满到要求的厚度后,方可向前施焊;焊接速度:要求等速焊接,保证焊缝厚度、宽度均匀一致,从面罩内看熔池中铁水与熔渣保持等距离(2~3㎜)为宜;焊接电弧长度:根

据焊条型号不同而确定,一般要求电弧长度稳定不变,酸性焊条一般为3~4㎜,碱性焊条一般为2~3㎜为宜;焊接角度:根据两焊件的厚度确定,焊接角度有两个方面,一是焊条与焊接前进方向的夹角为60~75°;二是焊条与焊接左右

夹角有两种情况,当焊件厚度相等时,焊件与焊件夹角为45°;当焊件厚度不

等时,焊条与较厚焊件一侧夹角应大于焊条与薄焊件一侧夹角;收弧:每条焊缝焊到末尾,应将弧坑填满后,往焊接方向相反的方向带弧,使弧坑甩在焊道貌岸然里边,以防弧坑咬肉。焊接完毕,应采用气割切除弧板,并修磨平整,不许用锤击落;清渣:整条焊缝焊完后清除熔渣,经焊工自检(包括外观及焊缝尺寸等)确无问题后,方可转移地点继续焊接。

Flat Welding : choice of welding technology, electrode diameter, welding current, welding speed, the length of arc welding, weld process verification; Welding : welding inspection clearance groove, assembly space whether it meets the requirements, positioning it firmly welding, weld around is not oil, rust; Electrode temperature and baking time should be required, the rod removed from the oven.

tempreture-constant drum on the electrode, then used as admission;

Latin America : welding supply welding thickness, welding levels and electrode type and diameter, skilled welders and other factors, and to select appropriate welding current; fillet weld arc : fluctuations in the point arc weld end, they are advised more than 10 mm, is not hard arc, sparking arc weld zone from the electrode should be started immediately. Component integration and maintaining so-rod pieces have 2-4 mm gap arc. Butt Weld and docking and corner

combinations Weld, in Weld ends located arc plate and extraction plate in igniting board then leads to the welding seam, joint halfway shall weld joints in front of 2.0 mm Department Firing arc, welding pieces after preheating rod will return to weld the origin, pool filled to the required thickness, before forward welding; Welding speed : Isokinetic welding requirements to ensure weld thickness, width uniform, which masks to look for hot metal and slag bath equidistance (2-3 mm)%; Arc welding rod length : different models and determined that the general requirements of arc length is stable, acid electrode generally 3-4 mm, 2-3 mm normally alkaline electrode%; Welding perspective : According to determine the thickness of two pieces of welding, welding angle has two aspects : First, the angle between the direction of the rod and welding of 60-75 °; The second is the angle between two electrodes and welding around, the same thickness as welding, welding and welding pieces incident angle of 45 °; When the thickness ranging from welding, welding electrode and thick and thin pieces of welding electrode side angle greater than the angle between the side pieces; Arc : admission to the end of each weld should be filled crater, in the direction opposite to the direction of the back-arc welding, arc welding unchanged inside pit in 1974, to prevent the crater bite of meat. Welding completed, should be removed arc OFC boards and grinding formation, while the hammer down; Slag : After removal of the entire weld slag, welders self (including weld appearance and si ze, etc.) there is no problem, before relocation to continue welding

1.1.

2.2立焊:基本操作工艺过程与平焊相同,但应注意下述问题:在同等条件下,焊接电源比平焊电流小10%~15%;采用短弧焊接,弧长一般为2~3㎜;焊条角度根据焊件厚度确定.两焊件厚度相等,焊条与焊条左右方向夹角均为45°;两焊件厚度不等时,焊条厚度不等时,焊条与较厚焊件一侧的夹角应大于较薄一侧的夹角.焊条应与垂直面形成60°~80°角,使电弧略向上,吹向熔池中心;收弧:当焊到末尾,采用排弧法将弧坑填满,把电弧移至熔池中央停弧.严禁使弧坑甩在一边.为了防止咬肉,应压低电弧变换焊条角度,使焊条与焊件垂直或由弧稍向下吹.

Welding process and the peace operati on : basic welding, but they should pay attention to the following issues : under the same conditions, welding current and friction over the plate short-arc welding, arc length is generally 2-3 mm; According to determine perspective welding electrode thickness. Welding two pieces of equal thickness, electrode and the electrode are around 45 ° angle direction; Two welding thickness ranges, electrode thickness ranges, with thick welding rod side of the incident angle and the angle is larger than the thinner side. with the vertical plane electrode formed 60 ° to 80 °angle, arc slightly upward, towards the pool; Arc welding : admission to the end of the paper that will crater filled arc, arc moved to the

central pool stopped arc. T o prevent occlude, Transformation should lower electrode arc angle, or vertical rod and welding pieces of blowing down slightly from the arc.

1.1.

2.3横焊:基本与平焊相同,焊接电流比同条件平焊的电流小10%~15%,

电弧长2~4㎜.焊条的角度,横焊时焊条应向下倾斜,其角度为70°~80°,防止

铁水下坠.根据两焊件的厚度不同,可适当调整焊条角度,焊条与焊接前进方向为

70°~90°.

Sidelong Welding same: basic welding, the welding current conditions compared with the current level of welding small beeswax, 2-4 mm long arc. Electrode angle, horizontal welding rod should be balancing its angle of 70 ° to 80 ° to prevent the fall of molten iron. According to the thickness of two different welding pieces, it would be appropriate to adjust electrode perspective welding electrode and the direction of

70 ° -90 °

1.1.

2.3仰焊:基本与立焊、横焊相同,其焊条与焊件的夹角和焊件厚度有关,焊

条与焊接方向成70°~80°角,宜有小电流、短弧焊接。

Welding belief 、Sidelong Welding and Stand Welding: the same horizontal welding, the welding electrode and the incident angle and thickness of the welding, welding electrode and the direction of 70 °to 80 ° angle are advised to a small current, short-arc welding

1.1.3冬期低温焊接:在环境温度低于0℃条件下进行电弧焊时,除遵守常温焊接

的有关规定外,应调整焊接工艺参数,使焊缝和热影响区缓慢冷却.风力超过4级,

应采取挡风措施;焊后未冷却的接头,应避免碰到冰雪;钢结构为防止焊接裂纹,

应预热以控制层间温度.当工作地点温度在0℃以下时,应进行工艺试验,以确定

适当的预热,后热温度.

Welding : In the winter low temperature environment under the conditions of temperature below 0℃, in addition to compliance with the relevant provisions of temperature welding, the welding parameters should be adjusted so that weld heat affected zone and slow cooling. Wind over four levels, measures should be taken to wind;

Not the cooling weld joints should avoid encountered snow; T o prevent steel welding cracks. interlayer preheating temperature to be controlled. When the temperature is below zero degree work should be carried out when a process test to determine appropriate preheating, heat temperature.

1.2普通紧固件连接工程施工工艺

General Parts Construction T echnology

(1)成品进场

Refined Approach

普通螺栓、铆钉、自攻螺钉、拉铆钉、射钉、锚钉(膨胀型和化学试剂型)、地脚锚栓等坚固标准件及螺母、垫圈等等标准配件,其品种、规格、性能等符合现行国家产品标准和设计要求。

Ordinary bolts, rivets, and self-drilling screws, rivets (expansion and

chemical reagents), to such strong legs stud and nut standard parts, gaskets, etc. standard accessories, variety, specifications, and other products with existing national standards and design requirements.

(2)螺栓实物复验

Complex and bolts kind experience

普通螺栓作为永久性连接螺栓使用时,当设计有要求或对其质量有疑义时,应进行螺栓实物最小拉力载荷复验,其结果符合国家标准《坚固件机械性能、螺栓、螺钉和螺柱》(GB3098)的规定。

Ordinary bolt connecting bolts as a permanent use, when the design requirements or questions about its quality should be carried out when the smallest lag bolts kind complex load testing and the results were consistent with national standard《mechanical fasteners, bolts, screws and stud》(GB3098).

(3)匹配及间距

Matching and spacing

连接薄钢板采用的自攻螺钉、拉铆钉、射钉等其尺寸与被连接钢板相匹配,其间距、边距等应符合设计要求。

Thin plate connecting the self-drilling screws, rivets, such as its size and connecting plate by matching their distance, should comply with the design requirements and other fringe.

(4)螺栓坚固

Solid bolts

永久性普通螺栓紧固应牢固、可靠,外露丝扣不应少于2扣。

Ordinary bolt should be firmly secured permanent, reliable, not less than two exposed screw deduction.

(5)外观质量

Appearance Quality

自攻钉、钢拉铆钉、射钉等与连接钢板应紧固密贴,外观排列整齐。

Since the attack nails, rivets Steel, Steel Nailing should be secured so closely connected with stickers topology neat appearance.

1.4零件及部件加工工程施工工艺

Components and parts processing Construction T echnology

(1)材料进场

Materials approach

钢材、钢铸件的品种、规格、性能等应符合现行国家产品标准和设计要求。进口钢材产品的质量应符合设计和合同规定标准的要求。

Steel, and steel castings variety of specifications, such products should be consistent with existing national standards and design requirements. The quality of imported steel products should comply with the design standards and the requirements of the contract.

(2)钢材复检

Following the steel complex

抽样复验结果应符合现行国家产品标准和设计要求。

Complex sample testing results should be in line with existing national product standards and design requirements

(3)切面质量

The quality of plane

钢材切割面或剪切面应无裂纹、夹渣、分层和大于1㎜的缺棱。

Steel cutting surface or shear surface should have no cracks, slag, stratification and the lack of greater than 1 mm Prism.

(4)矫正和成型

correct and prototyping

碳素结构钢在环境温度低于-16℃、低合金结构钢在环境温度低于-12℃时,不应进行冷矫正和冷弯曲。碳素结构钢和低合金结构钢在加热矫正时,加热温度不应超过900℃。低合金结构钢在加热矫正后应自然冷却。当零件采用热加工成型时,加热温度应控制在900~1000℃;碳素结构钢和低合金结构钢在温度分别下降到700℃和800℃之前,应结束加工;低合金结构钢应自然冷却。

Carbon steel in environmental temperature is below -16 ° C and low alloy steel in environmental temperature is below -12 ° C, and the correction should not cold cold bending. Carbon steel and low alloy steel correction in the heating, the heating temperature should not exceed 900 ℃. Low alloy steel and natural heating, cooling should be corrected. When the thermal processing molding components, the temperature should be controlled between 900 ~ 1000 °C; Carbon steel and low alloy steel and the temperature dropped to 700 ° C and 800 °C, respectively, should end processing; Low alloy steel cooling naturally.

(5)边缘加工

Edge processing

气割或机械剪切的零件,需要进行边缘加工时,其刨削量不应少于2.0㎜. Mechanical shear components, the need for edge processing, shaving its capacity of not less than 2.0 mm.

(6)A.B级螺栓孔(l类孔)应具有H12的精度,孔壁表面粗糙度Ra不应大于12.5m.其孔径的允许偏差应符合规范的规定.C级螺栓孔(Ⅱ类孔),孔壁表面粗糙度Ra不应大于25M,其允许偏差应符合规范规定.

Bolt hole level to B (l category Hole) is the H12 accuracy wall surface roughness Ra should not exceed 12.5m. Its diameter deviation should be allowed to meet the norms. C bolt hole (Class II Hole), the wall surface roughness Ra should not exceed 78, the deviation should be allowed to meet the norms.

(7)材料规格尺寸

Size specifications

钢板厚度及允许偏差应符合其产品标准的要求.型钢的规格尺寸及允许偏差应符合其产品标准的要求.

Allow plate thickness and standard deviation shall meet the requirements for their products. Beam deviation should be allowed to meet the si ze and specifications of their products standards.

(8)钢材表面质量

Steel surface quality

钢材表面的外观质量除应符合国家现行有关标准的规定外,尚应符合规范的规定.

In addition to the exterior surface of steel quality standards should be consistent with the existing provisions of the state, there should be in line with norms.

(9)切割精度

Cutting Accuracy

气割的允许偏差应符合规范的规定.机械剪切的允许偏差应符合规范的规定. Deviation should be allowed to comply with the norms. The shear machine error should be allowed to meet the norms.

(10)矫正质量

Correction quality

矫正后的钢材表面,不应有明显的凹面或损伤,划痕深度不得大于0.5㎜,且不应大于该钢材厚度负允许偏差的1/2.冷矫正和冷弯曲的最小弯曲率半径和最大矢高应符合规范的规定.钢材矫正后的允许偏差,应符合规范的规定.

After correction of the steel surface and concave or injury should be clear, scratch depth not greater than 0.5 mm, and should not be allowed to outweigh the negative deviation of the thickness of the steel half. Cold cold bending and rectify the minimum and maximum bending radius vector high rate should be in line with norms. After the error correction allows steel, should conform to norms.

(11)边缘加工精度

Edge machining accuracy

边缘加工允许偏差应符合规范的规定.

Edge processing deviation should be allowed to meet the norms.

(12)制孔精度

Precision Drilling

螺栓孔孔距的允许偏差应符合规范的规定.螺栓孔孔距的允许偏差超过规范规定的允许偏差时,应采用与母材材质相匹配的焊条补焊后重新制孔.

Bolt Hole Spacing should be consistent with the allowable deviation of norms. Bolt Hole Spacing over the allowable deviation of the standard deviation to allow that should be matched with base metal electrode material re-hole fix.

1.5单层钢结构安装施工工艺

Installation Process Steel monolayer

(1)基础

Foundation

建筑物的定位轴线、基础轴线和标高、地脚螺栓的规格及其紧固应符合设计要求。基础顶面直接作为柱的支承面和基础顶面预埋钢板或支座作为柱支承面时,其支承面、地脚螺栓(锚栓)位置的允许偏差应符合规范的规定。

Axis positioning buildings, infrastructure and elevation axes, anchor bolt fastening should conform to the specifications and design requirements. T op - directly as a basis and foundation of the bearing surface as the top-embedded steel bearings or bearing surface, the supporting surface, the

anchor bolt (Anchor) position should be consistent with the allowable deviation of norms.

(2)构件

Components

钢构件应符合设计要求和规范的规定。运输、堆放和吊装等造成的钢构件变形及涂层脱落,应进行矫正和修补。

Steel components should comply with the design requirements and norms. Transport, storage and loading of the steel components, such as deformation and peeling coating, repair and should be corrected.

(3)顶紧接触面

The top tight contact

设计要求顶紧的节点,接触面不应少于70%紧贴,且边缘最大间隙不应大于0.8㎜. T op tight design requirements of the node, not less than 70% of close contact, and the gap should not exceed 0.8 mm greatest risk.

(4)垂直度和侧弯曲

Vertical and lateral bending

钢屋架的垂直度和侧向弯曲的允许偏差应符合规范的规定.

Vertical and lateral bending of the steel roof of the deviation should be allowed to meet the norms.

(5)主体结构尺寸

The size of the main structure

主体结构的整体垂直度和整体平面弯曲的允许偏差应符合规范的规定.

Verticality and the main structure of the overall total deviation should be allowed to meet the plane bending norms.

(6)地脚螺栓精度

Anchor bolt precision

地脚螺栓(锚栓)尺寸的偏差应符合规范的规定.地脚螺栓的螺纹应受到保护. Anchor Bolt (Anchor), the error should be consistent with the size norms. Thread the anchor bolt should be protected.

(7)标记

Marker

钢柱等主要构件的中心线及标高基准点等标记应齐全.

Steel and other major components such as marking the centerline and elevation benchmarks should be complete.

(8)梁、柱、檩条等安装精度

Beams and columns, purlines installation accuracy

梁、柱、檩条的安装的允许偏差应符合规范的规定。

Beams and columns and purlines deviation should be allowed to meet the norms.

(9)平台等安装精度

Platforms installation accuracy

钢平台、钢梯、栏杆安装等应符合现行国家标准《固定式钢直梯》(GB4053.1)、《固定式钢斜梯》(GB4053.2)、《固定式防护栏杆》、(GB4053.3)和《固定式钢平台》(GB4053.4)的规定.钢平台、钢梯和防护栏杆安装的允许偏差应符合规范的规定。

Steel platforms, ladders, railings installation should comply with the national standard 《fixed straight staircase 》(GB4053.1), 《fixed steel ladder》(GB4053.2), 《a permanent protective railings》, (GB4053.3) and the 《fixed steel platform》(GB4053.4). Steel platform, and the installation of protective railings maximum deviation should be allowed to meet the norms.

(10)现场组对精度

Precision Group to the scene

现场焊缝组对间隙的允许偏差应符合规范的规定。

Weld scene deviation should allow the group to meet clearance norms. (11)结构表面

Surface structure

钢结构表面应干净,结构主要表面不应有疤痕、泥沙等污垢。

Steel surface should be clean, not a scar on the major surface structures, such as silt dirt.

1.6压型金属板安装施工工艺

Pressed metal plate Installation Process

(1)压型金属板进场

Pressed metal plate approach

金属压型板及制造金属压型板所采用的原材料,其品种、规格、性能等应符合现行国家产品标准和设计要求。压型金属泛水板、包角板、和零配件的品种、规格以及防水密封材料的性能应符合现行国家产品标准和设计要求。

Metal plate and metal plate used in the manufacture of raw materials, varieties and specifications, and other products should be consistent with existing national standards and design requirements. Pressed metal pan of water boards, Angle plates, and a variety of spare parts, and sealing materials specifications should conform to the performance of existing national product standards and design requirements.

(2)基板裂纹

Substrate cracks

压型金属板成型后,其基板不应有裂纹。

Pressing sheet metal forming, its substrate should be crack.

(3)涂(镀)层缺陷

Coating errors

有涂层、镀层的压型金属板成型后,涂、镀层不应有肉眼可见的裂纹、剥落和擦痕等缺陷。

A coating, the coating - pressure molding of sheet metal, the coating should be visible to the naked eye, cracked concrete and scratches error.

(4)现场安装

Field Installation

压型金属板、泛水板和包角板等应固定可靠、牢固,防腐涂料涂刷和密封材料敷设完好,连接件数量、间距应符合设计要求和国家现行有关标准规定。

Pressed metal plates, the water board and the whole board should be fixed angle reliable, strong, anti-corrosion coatings and sealing material coating

installation intact, connector size, spacing and the state should comply with the design requirements of the standard.

(5)搭接

Lap

压型金属板应在支承构件上可靠搭接,搭接长度应符合设计要求且不应小于规范的数值。Pressing sheet metal components in supporting reliable lap, lap length comply with design requirements and should not be less than the numerical standards.

(6)端部锚固

Anchorage end

组合楼板中压型板与主体结构(梁)的连接,其锚固支承长度应符合设计要求且应小于50㎜,端部锚固件连接应可靠,设置位置应符合设计要求。

Floors were plate with the main structure (beam) link, the length of anchor support should comply with the design requirements and should be less than 50 mm, will be a reliable link anchor pieces, location should meet the design requirements.

(7)压型金属板精度

Pressure-precision sheet metal

压型金属板的尺寸及允许偏差、表面质量、涂层质量等应符合设计要求和规范的规定。Pressed metal plate size and allow deviation, surface quality, quality coating should comply with the design requirements and norms.

(8)轧制精度

Rolling accuracy

压型金属板的尺寸允许偏差应符合规范的规定。压型金属板施工现场制作的允许偏差符合规范的规定。

Pressed metal plates the size of deviation should be allowed to meet norms. Pressure produced by the metal plates to allow the construction site with a standard deviation requirements.

(9)表面质量

Surface Quality

压型金属板成型后,表面应干净,不应有明显的凹凸和皱褶。

Pressing sheet metal forming, the surface should be clean, there should be clear and convex fold.

(10)安装质量

Installation Quality

压型金属板安装应平整、顺直,板面不应有施工残留物和污物。檐口和墙下端应呈直线,不应有未经处理的错钻孔洞。

Pressure should be the formation of metal plates installed, straight, there should be no construction of the plate surface residue and dirt. Eave wall and the bottom should shoot and should not be handled without drilling holes in the wrong.

(11)安装精度

Installation accuracy

压型金属板安装的允许偏差应符合规范的规定。

Pressure to allow the installation of metal plates with a standard deviation should be required

1.7防腐涂料涂装施工工艺

Anticorrosion coating Construction T echnology

1.7.1工艺流程

Process

基面清理→底漆涂装→面漆涂装→检查验收

Surface cleaning up→Painting Primer→Painting→Inspection and acceptance 1.7.2基层清理

Surface cleaning up

建筑钢结构工程的油漆涂装应在钢结构安装验收合格后进行.油漆涂刷前,应将需涂装部位的铁锈、焊缝药皮、焊接飞溅物、油污、尘土等杂物清理干净。

基面清理除锈质量的好坏,直接关系到涂层质量的好坏。因此涂装工艺的基面除锈质量分为一级和二级,见表5-25的规定

Paint steel construction project after acceptance in the installation of steel. Paint coating, should take the rust coating parts, weld coating, welding spatter materials, oil, dust and other debris cleared. Surface cleaning up derusting quality has a direct bearing on the quality of the coating. Thus the base coating process is divided into primary and secondary derusting quality, the table 5-25

钢结构除锈质量等级(表5-25)

Derusting quality steel grades (T able 5-25)

等级Grad 质量标准Quality Standards 除锈方法Derusting method

1 钢材表面露出金属色泽喷砂、抛丸、酸洗

Steel exposed metal surface color Sandblasting, peen, pickling

2 钢材表面允许存留干净的轧制表皮一般工具(钢丝刷、砂布)清除

Allow the surface to keep skin clean steel rolling General Instruments (wire brush and emery cloth) Elimination

为了保证涂装质量,根据不同需要可以分别用以下除锈工艺

喷砂除锈,它是利用压缩空气的压力,连续不断地用石英砂或铁砂冲击钢构件的表面,把钢材表面的铁锈、油污等杂物清理干净,露出金属钢材本色的一种除锈方法。这种方法效率高,除锈彻底,是比较先进的除锈工艺。

人工除锈,是由人工用一些比较简单的工具,如刮刀、砂轮、砂布、钢丝刷等工具,清除钢构件上的铁锈。这种方法工作效率低,劳动条件差,除锈也不彻底。

T o ensure the quality of coating, according to the different needs of each of the following can Derusting Sand-blasting, which is using compressed air pressure, worked with quartz sand or steel pellets impact of the component surface, the surface of the rusted steel, oil and other debris to clean up the col or of a rust-removing method steel exposed metal. This method is highly efficient, derusting completely rust-removing technology is more advanced. Artificial derusting are some relatively simple manual tools such as Drag and abrasive, emery cloth, and tools such as wire brush to

remove rust on the steel members. This approach is inefficient, poor labor conditions, derusting not complete.

1.7.3底漆涂装

Painting Primer

调合红丹防锈漆,控制油漆的粘度、稠度、稀度,兑制时应充分的搅拌,使油漆色泽、粘度均匀一致。

刷第一层底漆时涂刷方向应该一致,接搓整齐。

刷漆时应采用勤沾、短刷的原则,防止刷子带漆太多而流坠。

待第一遍刷完后,应保持一定的时间间隙,防止第一遍未干就上第二遍,这样会使漆液流坠发皱,质量下降。

待第一遍干燥后,再刷第二遍,第二遍涂刷方向应与第一遍涂刷方向垂直,这样会使油漆均匀一致。

底漆涂装后起码需4~8H后才能达到表干、表干前不应涂装面漆。

Blending Hongdan anti-rust paint, paint control the viscosity, density, rare, the system should be fully covered by mixing, paint color, viscosity uniform. Brush the first layer when brushing paint the same direction, then wake neat.

Painting Peregrine adopted when James and the short brush, brush to prevent the flow with too many southbound crash.

Brush question groove, the gap should maintain a certain amount of time to prevent the groove was dry on the second time, it would crash fat from the surface flow, the decline in the quality.

When groove dry, paint the second time, the second time brushing direction perpendicular direction with bead coating, it would paint uniform.

After the primer coating can be applied at least take 4~8H dry table, T able dry before painting not finish.

1.7.4面漆涂装

Painting

建筑钢结构涂装底漆与面漆一般中间间隙较长.钢结构件涂装防锈漆后送到工地去组装,组装结束后才统一涂装面漆.这样在涂装面漆前需对钢结构表面进行清理,清除安装焊缝焊药,对烧去或碰去漆的构件,还应先补漆.

面漆的调制应选择颜色完全一致的面漆,兑制的稀料应适合,面漆使用前应充分搅拌,保持色泽均匀.其工作粘度、稠度应保证涂装时不流坠,不显刷纹。

面漆在使用过程中应不断搅和,涂刷的方法和方向与上述工艺相同。

涂装工艺采用喷涂施工时,应调整好喷嘴口径、喷涂压力,喷枪胶管能自由拉伸到作业区域,空气压缩机气压应在0.4~0.7N/m㎡.

喷涂时应保持好喷嘴与涂层的距离,一般喷枪与作业面距离应在100㎜左右,喷枪与钢结构基面角度应该保持垂直,或喷嘴略为上倾为宜.

喷涂时喷嘴应该平行移动,移动时应平稳,速度一致,保持涂层均匀.但是采用喷涂时,一般涂层厚度较薄,故应多喷几遍,每层喷涂时应待漆膜已经干燥时进行.

Painting primer and finish among the general steel construction space longer. Steel anti-rust paint coating to the work site after the assembly assembly before the end of reunification coating finish.

Thus, the steel surface before coating finish screen installed weld removal of

medicine, or drop out of the burned out section of the component should first touch-up painting.

T opcoat modulation should choose exactly the same color finish, and against the system of rare material should fit, finish mixing before use should be fully maintain uniform color. Its viscosity and consistency to ensure flow coating not crash, no significant brush profile.

T opcoat mix in the use of the process should continue, brushing methods and the same direction with the above process.

Coating Process spraying construction, we should readjust the nozzle diameter and spraying pressure jet hose to the free operation of regional tension, pressure air compressor in 0.4~0.7N/m m 2.

Spray nozzle and a good coating to keep a distance from the surface in the general Lance with about 100 mm, steel base and Lance vertical angle should be maintained, or slightly tilted suitable nozzle.

Spray nozzles should be parallel when moving should be smooth, speed consistency and uniform coating. But when spraying generally thin coating thickness, it should be sprayed several times, and each level should be sprayed coating has been drying time.

1.7.5涂层检查与验收

Coating inspection and acceptance

表面涂装施工时和施工后,应对涂装过的工件进行保护,防止飞扬尘土和其它杂物.

涂装后的处理检查,应该是涂层颜色一致,色泽鲜明光亮,不起皱皮,不起疙瘩.

涂装漆膜厚度的测定,用触点式漆膜测厚仪一般测定3点厚度,取其平均值.

Surface Finishing construction and after construction, painting of the workpiece to deal with protection against dust and other debris floated. Painting the inspections should be coating color, bright color clear, wrinkle-free skin, not knots.

Coating thickness of the coating determined using point-3:00 measured the thickness of the coating thickness gauge general, the living.

1.8钢屋架安装施工工艺

Installation of the Steel Frame T echnology

1.8.1工艺流程

Process

作业准备→屋架组拼→屋架安装→连接与固定→检查验收

Ready to work →Roof group fight→Roof installation→Join and immobility →Inspection and acceptance

1.8.2安装准备

Ready to install

复验安装定位所用的轴线控制点和测量标高使用的水准点.

放出标高控制线和屋架轴线的吊装辅助线.

复验屋架支座及支撑系统的预埋件,其轴线、标高、水平度、预埋螺栓位置及露出长度等,超出允许偏差时,应做好技术处理。

检查吊装机械及吊具,按照施工组织设计的要求搭设脚手架或操作平台。

屋架腹杆设计为拉杆,但吊装时由于吊点位置使其受力改变为压杆时,为防止构件变形、失稳,必要时应采取加固措施,在平行于屋架上、下弦方向采用钢管、方木或其它临时加固措施。

测量用钢尺应与钢结构制造用的钢尺校对,并取得计量法定单位检定证明。

A post-mortem has complicated the installation of the axis positioning control points and the elevation of the standard of measurement points. Roof released elevation of the line of control and the loading axis auxiliary line.

Roof Support and Support System testing complex embedded parts, its axis, elevation, degree level, and his position bolt length in excess of allowable deviation, we should do a good job handling technology.

Sling hoisting machinery and inspection, in accordance with the requirements of placing construction organization design platform or scaffold. Roof belly bar designed for the stick, but when hoisting hanging position because it forces changes to Pressure Bar, the components to prevent deformation and instability, reinforcement measures shall be taken, where necessary, in parallel to the roof, and last quarter the direction of using steel, wood or other temporary side reinforcement measures.

Be used for the manufacture of steel and steel ruler measurement of the steel ruler proofreading and obtain statutory measurement units approval and certification.

1.8.3屋架组拼

Roof group fight

屋架分片运至现场组装时,拼装平台应平整.组拼时应保证屋架总长及起拱尺寸的要求.焊接时焊完一面检查合格后,再翻身焊另一面,做好施工记录.经验收后方准吊装.屋架及天窗架也可以在地面上组装好一次吊装,但要临时加固,以保证吊装时有足够的刚度. Roof patch shipped to the scene assembly, and assembly platform formation. Assembling and bagging chief roof should guarantee size requirements. Welding Welding End side pass the inspection, then stand up and welded the other hand, do construction records. Lifting the rear prospective admission experience. Roof and rain can also be a lifting assembled on the ground, but temporary reinforcement. Hoisting to ensure we have the necessary stiffness

1.8.4屋架安装

Roof installation

吊点必须设在屋架三汇交节点上.屋架起吊时离地50㎝时暂停,检查无误后再继续起吊. Three points must be located in the roof hanging intersection nodes. Roof lifting at 50 cm from the suspended after inspections continue lifting unmistakable.

1.8.5构件连接与固定

Join and immobility

构件安装采用焊接或螺栓连接的节点,需检查连接节点,合格后方能进行焊接或紧固.

安装螺栓孔不允许用气割扩孔,永乆性螺栓不得垫两个以上垫圈,螺栓外露丝扣长度不少于2~3扣.

安装定位焊缝不需承受荷载时,焊缝厚度不少于设计焊缝厚度的2/3,且不大于8㎜,焊缝长度不宜小于25㎜,位置应在焊道内.安装焊缝全数外观检查,主要的焊缝应按设计要求用超声波探伤检查内在质量.上述检查均需做出记录.

焊接及高强螺栓连接操作工艺详见该项工艺标准.

屋架支架支座、支撑系统的构造做法需认真检查,必须符合设计要求,零配件不得遗漏。Component installation of nodes connected by bolts or welding required inspection Connecti ons after passing before welding or fastening. Installing bolts allowed to use gas cutting bore hole and never more than two gaskets pad not sexual bolts, exposed screw bolt length of not less than 2-3 deduction.

Weld positioning under load without installation, seam thickness of the seam thickness of not less than two-thirds of the design, not to exceed 8 mm, should not be less than 25 mm in length Weld, located in welds inside. Weld full appearance of the installation and inspection of weld made major design requirements using ultrasonic flaw detecti on inspection quality. Need to make a record of these checks.

Join welding technology and high-strength bolts details of this technology standards.

Roof support bearings, and the support systems needed structural inspection practices must meet design requirements, not missing parts

1.8.6检查验收

Inspection and acceptance

屋架安装后首先检查现场连接部位的质量.

屋架安装质量主要检查屋架跨中对两支座中心竖向面的不垂直度;屋架受压弦杆对屋架竖向面的侧面弯曲,必须保证上述偏差不超过允许偏差,以保证屋架符合设计受力状态及整体稳定要求.

屋架支座的标高、轴线位移、跨中挠度,经测量做出记录。

First, inspect the site after the installation of roof connecting quality. Cross-check the main roof truss roof installation quality of the surface is not perpendicular to the vertical center two blocks; Roof surface pressure chord of the roof truss vertical bending side, we must ensure that such errors do not exceed the allowable deviation to ensure roof stability and comply with the design requirements of the state by force.

Roof Support elevation, the axis displacement and cross-deflection, the measurement made by the record.

1.8.7除锈、涂料

Removing rust and paint

连接处焊缝无焊渣、油污、除锈合格后方可涂刷涂料。

涂层干漆膜厚度应符合设计要求或施工规范的规定。

Connection weld without welding slag, oils, derusting pass before brushing paint. Coating thickness of the coating should conform to the standard design or construction requirements.

1.9钢结构防火涂料涂装施工工艺

Fire coating steel construction technology

1.9.1工艺流程

Process

作业准备→防火涂料配料、搅拌→喷涂→检查验收

Ready to work →Fireproof coating ingredients, stirring→Spraying →Inspection and acceptance

1.9.2防火涂料配料、搅拌

Fireproof coating ingredients, stirring

粉状涂料应随用随配。以ST1-A型配合比如下(表5-27)

With powder coatings should be allocated and used. For example, under a tie-ST1-A (T able 5-27)

表5-27

T able 5-27

涂料层数施工配合比每㎡用量

Paint rise Construction Mix Dosage/㎡

1 防火涂料:高强胶粘剂:钢防胶:水=1:0.05:0.17:0.8

Fireproof coating : High strength steel anti-adhesive glue : Water

2~3 防火涂料:钢防胶:水=1:0.17:0.85

Fire prevention : steel coating plastic water

搅拌时先将涂料倒入混合机加水水拌合2min后,再加胶粘剂及钢防充分搅拌5~5min,使稠度达到可喷程度.

Mixing paint into the mixer when the first increase in water mixture 2 minutes, stirring 5~5min fully with anti-adhesive and steel, jet can achieve consistency level.

1.9.3喷涂

Spraying

一般设计要求厚度为经耐火试验达到耐火极限厚度的1.2倍,以耐火极限为梁2h,柱3h,其设计厚度为梁30㎜,柱35㎜.第一层厚度为1㎝左右,晾干七~八成再喷第二层,第二层厚1~1.2㎝左右为宜,晾干七~八成后再喷第三层达到所需厚度为止.

喷涂时喷枪要垂直于被喷钢构件,距离6~10㎝为宜,喷涂气压应保持0.4~0.6Mpa,喷完后进行自检,厚度不够的部分再补喷一次.

正式喷涂前,应试喷一建筑层(段),经消防部门、质监站核验合格后,再大面积作业。施工环境温度低于+5℃时不得施工,应采取外围封闭,加温措施,施工前后48h保持+5℃以上为宜。

Thickness on the general design requirements for fire resistance test to achieve maximum thickness of 1.2 times the limit for the beam to fire 2h - 3h, and its design beam thickness of 30 mm, 35-mm. The first layer thickness of 1 cm around 70 ~ 80% dry then sprayed the second floor, around 2 cm thickness 1~1.2 suitable. 70 ~ 80% dry and then spray the third so far to achieve the required thickness.

Lance must be perpendicular to the jet spraying steel components, from 6-10 cm wide margin, spraying pressure must be maintained 0.4~0.6Mpa, after spray for self-thickness not part of a jet refilling.

Official spraying, spraying test of a construction zone (above), the fire

department, pertaining to quality supervision station after passing another large-scale operations.

Construction may not begin at +5 ° C below ambient temperature to be taken outside closed, the heat, maintain +5 ° C and over 48 hours before and after.

1.9.3检查验收

Inspection and acceptance

喷完一个建筑层经自检合格后,将施工记录送交监理核查。用带

刻度的钢针抽查厚度,如发现厚度不够,补喷或铲掉重喷,用锤子敲击检查空鼓,发现空鼓应重喷。合格后,办理隐蔽工程验收手续。

End level on the self-constructi on of a jet after passing records will be sent to the Commissioner of construction inspectors.

Belt Calibration checks the wire thickness, thickness found enough to make up for re-jet spray or shoveled away with a hammer percussion hollowing inspection found hollowing should re-sprayed. After passing inspection procedures for covert projects.

2、建筑工程(组合楼板)钢筋混凝土

Construction (Floors) reinforced concrete

2.1钢筋加工

Steel Bar processing

2.1.1钢筋除锈

Steel Bar derusting

钢筋除锈采用冷拉和手工除锈,这样较为省力,可以确保除锈质量.

Rust Remover and cold-drawn steel used manual derusting, this is more economical, we can ensure that quality derusting.

2.1.2钢筋调直

Straightening

采用钢筋调直机对钢筋进行调直,根据钢筋的直径选用调直模,并正确掌握调直模的偏移量.

Steel reinforcing bars used to direct planes to conduct direct, according to the diameter steel Straightening mode selection and correct use Straightening-scale displacement.

2.1.3钢筋切断

Steel cut

将同规格钢筋根据不同长度长短搭配,统筹排料;应先断长料,后断短料,减少短头,减少损耗.

断料时应避免用短尺量长料,防止在量料中产生累计误差。为此,宜在在工作台上标出刻度线并设置控制断料尺寸用挡板。

箍筋弯后的平直部分长度:对一般结构,不宜小于箍筋直径的5倍;对有抗震等要求的结构,不应小于箍筋直径的10倍。

Steel Bar with different specifications to match the length of the length overall layout; Should continue long expected, by cutting short expected to reduce short head, reducing wear and tear.

Cutting should avoid using short-foot long amount of material to

prevent the volume of the whole people have accumulated error.

Therefore, it would be desirable to set up in the table shows the

calibration and control the size of break with baffle.

Stirrup bend the straight part of the general structure : length,

diameter of not less than five times the stirrups; Seismic

requirements for the structure, not less than 10 times the diameter of

the stirrup.

2.1.3弯曲成型

Bending

钢筋弯曲前,对形状复杂的钢筋(如弯起钢筋),根据钢筋料牌上标明的尺寸,用

石笔将各弯曲点位置划出.划线时应注意:

根据不同的弯曲角度扣除弯曲调整值,其扣法是从相邻两段长度中各扣一半;

钢筋端部带半圆弯钩时,该段长度划线时增加0.5d(d为钢筋直径);

划线工作宜从钢筋中线开始向两边进行;两边不对称的钢筋,也可以从钢筋一端

开始划线,如划到另一端有出入时,则应重新划线.

Bending steel, the steel complex of shapes (such as curved steel),

according to the size indicated on the license reinforced materials

used Tutcheria spectabilis bending to the position draw. Crossed

when :

The bending angle is the effect of different bending adjusted value,

the deduction is deducted from each half of the length of two adjacent;

Semi steel hooks end zone, the length of lines increased ppb (d bar

diameter);

Crossed from the steel work are advised to start on both sides of the

center line;

Asymmetric both sides of the steel reinforced side from the beginning

can be delimited If it is the other side that is different, we need to

re-crossed.

2.2钢筋安装

The installation of steel

2.2.1工艺流程:准备工作→钢筋绑扎接头→梁板钢筋绑扎.

Process: Ready to work →Steel joints→Beam steel joints

2.2.2准备工作

Ready to work

核对成品钢筋的钢号、直径、形状、尺寸和数量等是否与料单牌相符。如人错漏,应纠

正增补。

准备绑扎用的铁丝、绑扎工具(如钢筋钩、带扳口的小撬棍)绑扎架等。

钢筋绑扎用的铁丝,采用20~22号铁丝,其中22号铁丝只用于绑扎直径12㎜以下

的钢筋。

准备挖制混凝土保护层用的水泥砂浆垫块或塑料卡。水泥垫块的厚度,应等于保护层厚度。垫块的平面尺寸;当保护层层叠叠厚度等于或小于20㎜时为30×30㎜,大于20

㎜时50㎜×50㎜。

划出钢筋位置线。平板和墙板的钢筋,在模板上划线;钢筋接头的位置应根据来料规格、接头位置、数量的规定,使其错开,在模板上划线。

绑扎形式复杂的结构部位时,应先研究逐根钢筋穿插就位的顺序,并与模板工联系讨论支模和绑扎钢筋的先后次序,以减少绑扎困难。

Check reinforced steel products, diameter, shape, size and quantity of materials with single line card.

If human errors should be corrected added.

Prepared lashing the wire, lashing tools (such as steel hooks and wrenched mouth with a small crowbar) lashing parking.

Assembling the steel wire, using 20-22 gauge wire, 22 gauge wire used only for a steel pipe diameter of 12 mm.

Prepared to dig protective layer of cement mortar system concrete pad or plastic cards.

Cement pad thickness, thickness should be equal protection. Pad size of the plane; When the thickness of multi-layered protection equal to or less than 20 mm at 30 × 30 mm, 20 mm greater than 7.50 mm × 50 mm.

Line drawn steel. The steel wall plate and in the template lines; According to the exceptional standard specification of the location should be reinforced joints, joint location, quantity, it staggered the template lines.

Lashing complex forms part of the structure, each reinforced schedule should first study the order in place, and discussions associated with templates for assembling steel formwork and the priorities to reduce the difficulties lashing

2.2.3钢筋绑扎接头

Steel joints

钢筋绑扎接头宜设置在受力较少处.同一纵向受力钢筋不宜设置两个或两个以上接头.接头末端至钢筋弯起点的距离不应小于钢筋直径的10倍.

同一构件中相邻纵向受力钢筋的绑扎搭接接头宜相互措开.同一连接区域内,纵向受拉钢筋绑扎搭接接头面积百分率及箍筋配置要求应符合规范规定的要求.

绑扎搭接接头中钢筋的横向间距不应小于钢筋直径,且不应小于25㎜.

当纵向受力筋的绑扎搭接接头面积不百分率不大于25%时,其最小搭接长度应符合要求.

Steel pipe joints are advised to set up the force less Department. The same longitudinal reinforcement is not advisable to install two or more joints. Bend steel joints start to the end of the bar diameter and the distance of not less than 10 times.

Adjacent vertical component reinforced by the same forces of banding lap joints are advised to open each other measures. Connecting the same region, an area of longitudinal reinforcement lashing percentage lap joints and stirrups conforming to the requirements of the distribution requirement. Lashing lap joints in the horizontal spacing of not less than steel bar diameter, and not less than 25 mm. When assembling the vertical lap joint force tendon percentage size of not more than 25%, the minimum length of lap should meet the requirements.

2.2.4梁板钢筋的绑扎

Beam steel joints

纵向受力钢筋采用双层排列时,两排钢筋之间应垫以直径≥25㎜的短钢筋,以保持其设计距离.

箍筋的接头(弯钩叠合处)应交错布置在两根架立钢筋上.

板的钢筋网绑扎与基础相同,但应注意板上部的负筋,要防止被踩下.

Longitudinal topology by using double-strength steel, two rows of steel should pad diameter ≥ 25 mm with a short iron bars, designed to keep their distance.

Stirrup joints (congruence) should be staggered in the last two of erect steel. The steel plate and pipe network infrastructure, but they should pay attention to the Ministry of negative reinforcement plate to prevent fall into.

2.3混凝土施工

Concrete Construction

2.3.1混凝土浇筑

Concrete pouring

在浇筑工序中,应控制混凝土的均匀性和密实性.混凝土拌合物运输至浇筑地点后,应立即浇筑入模.在浇筑过程中,如发现混凝土拌合物的均匀性和稠度发生较大的变化,应及时处理.

浇筑混凝土时,应注意防止混凝土的分层离析.混凝土由料斗、漏斗内卸出进行浇筑时,其自由倾落高度一般不宜超过2M,在竖向结构中浇筑混凝土的高度不得超过3M,否则应采用串筒、斜槽、溜管等下料。

浇筑竖向结构混凝土前,底部应先填50~100㎜厚与混凝土成分相同的水泥砂浆。

浇筑混凝土时,应经常观察模板、支撑、钢筋、预埋件和预留孔洞的情况,当发现有变形、移位时,应立即停止浇筑,并应在已浇筑的混凝土凝结前修整完好。

混凝土在浇筑及静置过程中,应采取措施防止产生裂缝。混凝土因沉降及干缩产生的非结构性的表面裂缝,应在混凝土终凝前予以修整。在浇筑与柱和墙连成整体的梁和板时,应在柱和墙浇筑完毕后停1-1.5H,使混凝土获得初步沉实后,再继续浇筑,以防止接缝处出现裂缝.

梁和板应同时浇筑混凝土.较大尺寸的梁,可单独施工.

In the pouring process, we should control the uniformity and density of concrete. Transport place after pouring fresh concrete to be poured into the mode immediately. In the pouring process, found fresh concrete there is a greater consistency and uniformity of the changes should be dealt with in a timely manner. Poured concrete, concrete should be taken to prevent segregation. Concrete from the hopper, the hopper catch unloaded when its free dumping highly charged 2M generally should not exceed the height of the vertical structure of concrete poured over 3M, otherwise string should be used cartridges, Chute, slipped under management and other materials. Concrete pouring vertical structure, the bottom should be filling in the same 50-mm thick cement mortar and concrete components. Pouring concrete should always observe the template, support, reinforcement, correcting the hole and reserved, and when there

deformation and displacement, it should immediately stop pouring and pouring the concrete that should have been repaired before intact. Concrete pouring and put it aside for at least the process should take measures to prevent cracks. Settlement due to the shrinkage of concrete and the surface of non-structural cracks in concrete should be repaired before the end condensate. Even in the pouring walls and columns and beams and plates as a whole, the columns and walls should be stopped after pouring 1-1.5H, preliminary pragmatic and concrete, pouring continue to prevent seams, cracks have emerged. Should be pouring concrete beams and plates. Bigger size beam construction alone.

2.3.2混凝土养护

Concrete Maintenance

采用覆盖浇水养护,利用平均气温高于+5℃的自然条件,用适当的材料对混凝土表面加以覆盖并浇水,使混凝土在一定的时间内保持水泥水化作用所需要的适当温度和湿度条件.

Cover water conservation use, average temperatures above +5 ° C using natural conditions, the use of appropriate materials on the concrete surface to be covered and watered, in the concrete cement hydration within a certain period of time required to maintain the proper temperature and humidity conditions.

覆盖浇水养护应符合下列规定:

Cover water conservation should meet the following requirements :

(1)覆盖浇水养护应在混凝土浇筑完毕后的12H内进行.

Covered in concrete pouring water conservation should be carried out after the 12H.

(2)混凝土的浇水养护时间,对采用硅酸盐水泥、普通硅酸盐

水泥或矿渣硅酸盐水泥拌制的混凝土,不得少于7D,对掺用缓凝型外加剂、矿物掺合料或有抗渗性要求的混凝土,不得少于14D。

当采用其他品种水泥时,混凝土的养护应根据所采用水泥的技术性能确定。

The concrete water conservation, the use of portland cement and ordinary portland .

Portland cement or slag cement mixing concrete, no less than the 7D, the type doped using retarding additives, or mineral admixture impermeability of concrete demands no less than the 14D.

When the other varieties of cement, concrete curing of cement used in the technical specifications should be defined.

(3)浇水次数应根据能保持混凝土处于湿润的状态来决定。

Watering frequency can be maintained under moist concrete in the state to decide.

(4)混凝土的养护用水宜与拌制水相同。

Concrete mixing water and the conservation of water are advised the same. (5)当日平均气温低于5℃时,不得浇水。

The average day temperature below 5 ° C, no water.

各种施工工艺标准

各种施工工艺标准 2011-07-13 04:42:09| 分类:施工工艺及规|字号订阅 序言 本企业标准的编写是依据国家标准、行业标准和地方性标准等为基础而进行的。本着”国家标准是最低限度的标准,企业标准应严于国家标准,方才有意义”这样的指导思想,否则,企业就不能得到持续进步和长足发展;坚持贯彻“精心施工、精雕细琢;质量第一、用户第一”的企业精神;同时,也结合本公司实际管理水平和质量水平来进行编写。本标准在质量实测方面稍微严于国家标准,今要求各项目经理部在施工过程认真贯彻执行本标准。 为了提高本企业标准质量,请各在建工程项目经理部在执行本标准过程中,注意积累资料、总结经验,如发现有更好的管理理念、施工技术或新工艺、新方法、新技术、新材料等都要及时反馈给公司,只要有利于公司管理水平的提升;有利于工程质量的提高;有利于降低成本提高经济效率等意见和建议,公司都会予与重视并吸收采纳,以供今后修订时加入新的容,从而促使本公司的整体素质得到全面的提升,并能增强公司在建筑市场的竟争力,使本公司越办越好越红火,在不久的将来晋升为特级资质等级的企业,成为中国建筑业的龙头企业,希望这一天指日可待。 ×建筑工程编写 目录 1、XDQB2002-001土方开挖与回填施工工艺标准--------------------------6 2、XDQB2002-002模板安装与拆除施工工艺标准---------------------------9 3、XDQB2002-003钢筋加工与安装施工工艺标准-------------------------11 4、XDQB2002-004现浇混凝土施工工艺标准-- ----------------------------14 5、XDQB2002-005砖墙砌筑施工工艺标准----------------------------------16 6、XDQB2002-006一般抹灰施工工艺标准----------------------------------18 7、XDQB2002-007装饰抹灰施工工艺标准----------------------------------20

英文版excel中英文对照表

英文版Excel 中英文对照表 激活(activate) 数组(array) 数组公式(array formula) 相关联的数据透视表(associated PivotTable report )自动套用格式(autoformat) 坐标轴(asix) 基础地址(base address) “合并计算”表(consolidation table) 比较条件(comparison criteria) 比较运算符(comparison operator) 常量(constant) 单元格引用(cell reference) 当前区域(current region) 分类轴(category asix) 分类字段(category field) 复制区域(copy area) 计算列(calculated column) 计算项(calculated item) 计算字段(数据库)(calculated field) 计算字段(数据透视表)(calculated field) 列标题(column heading) 列字段(column field) 条件(criteria) 条件窗格((criteria pane) 条件格式(conditional format) 图表工作表(chart sheet) 图表区(chart area) 修订记录(change history) 约束条件(constraints) 证书验证机构(certifying authority) 自定义计算(custom calculation) 垂直线(drop lines) 从属单元格(dependents) 明细数据(detail data) 默认工作表模板(default worksheet template) 默认工作簿模板(default workbook template) 默认启动工作簿(default startup workbook ) 目标区域(destination area) 数据标签 (data label) 数据标志(data marker) 数据表(data table) 数据表单(data form) 数据窗格(data pane)

装修施工工艺大全

地面工程施工工艺流程 木工工程施工工艺流程 墙面装饰施工工艺流程 油漆涂料施工工艺流程 吊顶工程装饰工艺流程 电路灯具施工工艺流程 卫浴洁具安装工艺流程 管路改造工程工艺流程 厨房设备施工工艺流程 铝合金门窗的工艺流程 地面工程施工工艺流程 石材地面施工工艺流程 瓷地面砖铺贴工艺流程 木地板铺贴工艺流程 塑料地板铺贴工艺流程 地毯铺设工艺流程 水泥砂浆抹灰的施工 石材地面的施工工艺流程 石材地面指天然花岗石、石及人造花岗石、石等地面。 一、石材地面装饰构造: 室地面所用石材一般为磨光的板材,板厚20毫米左右,目前也有薄板,厚度在10毫米左右,适于家庭装饰用。每块大小在300毫米×300毫米~500毫米×500毫米。可使用薄板和1:2水泥砂浆掺107胶铺贴。 石材地面装饰基本工艺流程: 清扫整理基层地面→水泥砂浆找平→定标高、弹线→选料→板材浸水湿润→安装标准块→摊铺水泥砂浆→铺贴石材→灌缝→清洁→养护交工。 三、施工要点: 基层处理要干净,高低不平处要先凿平和修补, 基层应清洁,不能有砂浆、尤其是白灰砂浆灰、油渍等,并用水湿润地面。 铺装石材、瓷质砖时必须安放标准块,标准块应安放在十字线交点,对角安装。 铺装操作时要每行依次挂线,石材必须浸水湿润,阴干后擦净背面。

石材、瓷质砖地面铺装后的养护十分重要,安装24小时后必须洒水养护, 铺巾完后覆盖锯末养护。 四、注意事项。 (1)铺贴前将板材进行试拼,对花、对色、编号,以入铺设出的地面花色一致。 (2)石材必须浸水阴干。以免影响其凝结硬化,发生空鼓、起壳等问题。 (3)铺贴完成后,2~3天不得上人。 铺贴瓷地面砖基本工艺流程 1、铺贴彩色釉面砖类: 处理基层→弹线→瓷砖浸水湿润→摊铺水泥砂浆→安装标准块→铺贴地面砖→勾缝→清洁→养护。 2、铺贴瓷锦砖(马赛克)类: 处理基层→弹线、标筋→摊铺水泥砂浆→铺贴→拍实→洒水、揭纸→拨缝、灌缝→清洁→养护。 铺贴瓷地砖的施工要点 1、混凝土地面应将基层凿毛,凿毛深度5~10毫米,凿毛痕的间距为30毫米左右。之后,清净浮灰,砂浆、油渍,产散水刷少将地面。 2、铺贴前应弹好线,在地面弹出与门道口成直角的基准线,弹线应从门口开始,以保证进口处为整砖,非整砖置于阴角或家具下面,弹线应弹出纵横定位控制线。 3、铺贴瓷地面砖前,应先将瓷地面砖浸泡阴干。 4、铺贴时,水泥砂浆应饱满地抹在瓷地面砖背面,铺贴后用橡皮棰敲实。同时,用水平尺检查校正,擦净表面水泥砂浆。 5、铺贴完2~3小时后,用白水泥擦缝,用水泥、砂子=1:1(体积比)的水泥砂浆,缝要填充密实,平整光滑。再用棉丝将表面擦净。 6、注意事项。 (1)基层必须处理合格,不得有浮土、浮灰。 (2)瓷地面砖必须浸泡后阴干。经免影响其凝结硬化,发生空鼓、起壳等问题。 (3)铺贴完成后,2~3小时不得上人。瓷锦砖应养护4~5天才可上人。 木地板施工工艺流程 一、木地板装饰的做法 粘贴式木地板: 在混凝土结构层上用15毫米厚1:3水泥砂浆找平,现在大多采用不着高分子粘结剂,将木地板直接粘贴在地面上。 实铺式木地板: 实铺式木地板基层采用梯形截面木搁栅(俗称木楞),木搁栅的间距一般为400毫米,中间可填一些轻质材料,以减低人行走时的空鼓声、并改善保温隔热效果。为增强整体性,木搁栅之上铺钉毛地板,最后在毛地板能上能下打接或粘接木地板。 在木地板一墙的交接处,要用踢脚板压盖。为散发潮气,可在踢脚板上开孔通风。 架空式木地板: 架空式木地板是在地面先砌地垄墙,然后安装木搁栅、毛地板、面层地板。因家庭居室高度较低,这种架空式木地板很少在家庭装饰中使用。 二、木地板装饰的基本工艺流程 粘贴法施工工艺为:

最新菜单中英文对照大全

菜单中英文对照大全随着我国加入WTO及对外交往活动的日益增多,餐饮业也面临着走向世界这个问题。因此,我们作为餐饮业的从业人员,或多或少地懂一点有关餐饮方面的专业英语,是非常必要的。 餐饮专业英语主要包括日常会话用语、烹饪技术用语和中餐英文菜单等等,而这其中尤以中餐英文菜单用得最为普遍。 要将中餐菜单翻译成英文,就先得了解中餐菜名的构成及命名方法。中餐菜名通常由原料名称,烹制方法、菜肴的色香味形器、菜肴的创始人或发源地等构成。这种反映菜肴内容和特色的命名方法叫做写实性命名法,此外还有反映菜肴深刻含义的写意性命名法。 由于汉语和英语的差异很大,我们在把中餐菜名由中文译成英文的时候,应该采用写实性命名法,尽量将菜肴的原料、烹制方法、菜肴的味型等翻译出来,以便让客人一目了然。为了让大家更好地掌握将中餐菜名译成英文的技巧,笔者特将自己在翻译中总结出来的几点“公式”(中英文对照)介绍如下,以供大家参考。 一、以主料开头的翻译方法 1 公式:主料(形状)+(with)辅料 例:杏仁鸡丁chicken cubes with almond 牛肉豆腐beef with beancurd 西红柿炒蛋Scrambled egg with to tomato 2 公式:主料(形状)+(with,in)味汁 例:芥末鸭掌duck webs with mustard sauce 葱油鸡chicken in Scallion oil 米酒鱼卷fish rolls with rice wine 二、以烹制方法开头的翻译方法 1 公式:烹法+主料(形状)

例:软炸里脊soft-fried pork fillet 烤乳猪roast suckling pig 炒鳝片Stir-fried eel slices 2 公式:烹法+主料(形状)+(with)辅料 仔姜烧鸡条braised chicken fillet with tender ginger 3 公式:烹法+主料(形状)+(with,in)味汁 例:红烧牛肉braised beef with brown sauce 鱼香肉丝fried shredded pork with Sweet and sour sauce 清炖猪蹄stewed pig hoof in clean soup 三、以形状或口感开头的翻译方法 1(口感)和主料、辅料 公式:形状(口感)+主料+(with)辅料 例:芝麻酥鸡crisp chicken with sesame 陈皮兔丁diced rabbit with orange peel 时蔬鸡片Sliced chicken with seasonal vegetables 2烹法和主料 公式:口感+烹法+主料 例:香酥排骨crisp fried spareribs 水煮嫩鱼tender stewed fish 香煎鸡块fragrant fried chicken

花语大全

1 红玫瑰——我爱你 2 玫瑰——热情 3 玫瑰——美丽纯洁的爱情 4 橙红玫瑰——初恋的心情 5 白玫瑰——纯洁与高贵 6 粉玫瑰——初恋,特别的关怀 7 黄玫瑰——歉意 8 红玫瑰——热恋,真心实意 玫瑰(白)——我尊敬你 9 10 玫瑰(红)——热恋 11 玫瑰(红白混合)——和解 12 玫瑰(黄)——嫉妒、分手、友谊之情 13 白玫瑰——我足以与你相配 14 紫玫瑰——珍惜的爱 黄玫瑰——腿色的爱 15 16 香槟玫瑰——我只钟情你一个&爱上你是我今生最大的幸福;想你是我最甜蜜的痛苦; 17 和你在一起是我的骄傲 红色素菊,玫瑰——我爱你 18 19 蓝色玫瑰——无法得到的东西 20 香槟玫瑰——梦幻的感觉 白玫瑰——我足以与你相配 21 22 康乃馨——母爱

23 米红康乃馨——伤感 24 郁金香——魅惑、爱之寓言 25 黄郁金香——绝望之爱 26 波斯菊——纯情、永远快活 27 水仙花——尊敬 28 红郁金香——爱的誓言 29 文竹——永恒 30 秋牡丹——失恋 白山茶——真爱、真情 31 32 红山茶——天生丽质 33 剑兰——性格坚强、用心 34 毋忘我——永恒的爱 35 鸡冠花——多色的爱 36 雏菊——清白、纯真、纤细 蝴蝶兰——初恋、幸福渐进、纯洁美丽 37 38 麒麟草——警戒 39 紫丁香——初恋、羞怯 梅花——高洁 40 41 风铃草——温柔的爱 42 飞燕草——轻薄 桔梗——气质高雅、不变的爱 43 44 金缕梅——灵感

45 金雀儿——谦逊 46 桃花——疑惑、好运将至、爱慕47 石竹——谦逊、多愁善感、莽撞48 百日草——思考 49 白茶——无瑕 50 玛格烈菊——预言 51 橙花——贞洁 52 矢车菊——雅致、优美 千日草——不朽 53 54 杏花——疑惑 55 大岩桐——欲望 56 杜鹃花——节制、移情别恋 57 栀枝——清雅 58 罂粟花——安慰、多谢 凤仙花——惹人爱、拒绝爱情 59 60 大丁香——神秘 61 李花——纯洁 樱花——淡泊、欢乐 62 63 芍药——恐惧、惜别、害羞 64 大丽花——华丽、吉祥 附子——敬意 65 66 金盏花——悲哀、离别、迷恋

各种加固方法施工工艺标准

各种加固方法施工工艺 一. 粘钢施工工艺: 流程:粘贴面处理T加压固定及卸荷系统准备(根据实际情况和设计要求,卸荷步骤有时省去)T胶粘剂 配制f涂胶和粘贴f固化、卸加压固定系统f检验f维护 1. 粘贴面处理 1.1. 混凝土面应凿除粉饰层,油垢、污物,然后用角磨机打磨除去1-2mm厚表层,较大凹陷处用找平胶修 补平整,打磨完毕用压缩空气吹净浮尘,最后用棉布沾丙酮拭净表面,待粘贴面完全干燥后备用。 12钢板粘贴面应用角磨机进行粗糙、除锈处理,直至打磨岀现光泽,使用前若洁净仅用干布擦拭即可。否则可用棉布沾丙酮拭净表面,待完全干燥后备用。 1.3. 该工序所用主要物资:护目镜、防尘口罩、冲击电锤及扁铲、手锤、角磨机、金刚石磨片、砂轮片、空压机、棉布、丙酮。 2. 加压固定及卸荷系统准备(根据实际情况和设计要求,卸荷步骤有时省去) 2.1. 加固构件所承受的活荷载如人员、办公机具宜暂时移去,并尽量减小施工临时荷载。 22加压固定宜采用千斤顶、垫板、顶杆所组成的系统,该系统不仅能产生较大压力,而且加压固定的同时卸去了部分加固构件承担的荷载,能更好的使后粘钢板与原构件协同受力,加固效果最好,施工效率较高。 2.3. 加压固定也可采用膨胀螺栓、角钢、垫板所组成的系统,该系统需要在加固构件上合适位置钻孔固定膨胀螺栓,仅能产生较小压力,不能产生卸荷效果,适合侧面钢板的粘贴。 3. 胶粘剂配制 3.1. 建筑结构胶为A、B两组份,取洁净容器(塑料或金属盆,不得有油污、水、杂质)和称重衡器按说明 书配合比混合,并用搅拌器搅拌约5-10分钟至色泽均匀为止。搅拌时最好沿同一方向搅拌,尽量避免混入空气形成气泡,配置场所宜通风良好。 3.2. 该工序所用主要物资:搅拌器、容器、衡器、腻刀、手套。 4. 涂胶和粘贴 4.1. 胶粘剂配制好后,用腻刀涂抹在已处理好钢板面上(或混凝土表面),胶断面宜成三角形,中间厚3毫米左右,边缘厚1毫米左右,然后将钢板粘贴在混凝土表面,用准备好的固定加压系统固定,适当加压, 以胶液刚从钢板边缝挤岀为度。 4.2. 该工序所用主要物资:加压固定及卸荷系统,腻刀、手套。 5. 固化、卸加压固定系统 5.1.5.2. 该工序所用主要物资:扳手、手套、时钟、温度计。 6. 检验 6.1. JGN-G 型结构胶操作性能极好,正常操作可达到100%勺饱满度。检验时可用小锤轻击粘贴钢板,从音 响判断粘贴效果,也可采用超生仪检测。若锚固区有效粘结面积少于90%非锚固区有效粘结面积少于70%应剥离钢板,重新粘贴。 6.2. 对重要构件也可采用载荷检验,一般采用分级加载至正常荷载的标准值,检测结果较直观、可靠,但 费用较高,耗时也较长。需要千斤顶或配重(常用沙袋、砖块)、百分表、裂缝显微镜、衡器。 7. 维护

各类花的花语大全

各类花的花语大全 花语是指人们用花来表达人的语言,不同的花、不同的枝数代表不同的含义,不同的花送的对象也不一样。你知道多少花卉的话语呢?爱汇网小编精心为大家搜集整理了各类花的花语,大家一起来看看吧。 非洲堇:关怀我吧 三色堇:思念,思虑,沉思 黄色三色堇:忧喜参半 紫色三色堇:沉默不语 鸢尾(爱丽斯):好消息、使者、想念你、信仰者的幸福 德国鸢尾:神圣 小鸢尾:协力抵挡、同心 清新脱俗的百合有如婀娜多姿的美丽佳人,不问尘事,只可远观而不可亵玩。 百合:顺利、心想事成、祝福、高贵、百年好合 百合(香水):纯洁、婚礼的祝福、高贵、圣洁的友谊 百合(白):纯洁、庄严、心心相印 百合(葵):胜利、荣誉、富贵 百合(姬):财富、荣誉、清纯、高雅

火百合(红):奔放的热情 狐尾百合:尊贵、欣欣向荣、杰出 玉米百合:执著的爱、勇敢 编笠百合:才能、威严、杰出 圣诞百合:喜洋洋、庆祝、真情 水仙百合:喜悦、期待相逢 女神维纳斯最喜欢收集风信子花瓣上的露水,使肌肤更漂亮光滑。 风信子的花期过后,若要再开花,需要剪掉之前奄奄一息的花朵。所以风信子也代表着重生的爱——忘记过去的悲伤,开始崭新的爱。 风信子(别名西洋水仙):永远的怀念。只要点燃生命之火,便可同享丰富人生风信子;胜利竞技得意 紫色风信子:悲伤、忧郁的爱。道歉、后悔。(得到我的爱,你一定会幸福快乐) 淡紫色风信子:轻柔的气质、浪漫的情怀。悲伤。 白色风信子:暗恋。纯洁清淡或不敢表露的爱 红色风信子:感谢你,让人感动的爱(你的爱充满我心中) 桃红色风信子:代表热情。 粉色风信子:倾慕、浪漫。

黄色风信子:有你我就很幸福。 蓝色风信子:高贵浓郁,恒心、贞操、彷佛见到你一样高兴。深蓝色风信子:因爱而有些忧郁 淡绿风信子:如果你想没有秘密,必先拥有善良的心。 康乃馨是所有女性的神圣之花,美好典雅的典范。 康乃馨:母亲我爱您、热情、真情 康乃馨(红):相信你的爱 康乃馨(粉红):热爱、亮丽 康乃馨(白):吾爱永在、真情、纯洁 康乃馨(黄):轻蔑 蔷薇:坚强 红蔷薇:热恋 粉蔷薇:爱的誓言,执子之手,与子偕老 白蔷薇:纯洁的爱情 黄蔷薇:永恒的微笑 深红蔷薇:只想与你在一起

施工工艺大全(最新版)PDF可编辑

施工工艺大全

目 录 第一章、装饰工程 (3) 第一节、地面装饰类 (3) 地面铺石材 (3) 复合地板地面 (5) 地面铺瓷砖 (6) 地面铺地毯 (10) 不锈钢踢脚安装 (11) PVC地板施工方案 (12) 地面铺地毯(块毯) (13) 地面铺塑胶 (14) 第二节、墙面工程 (16) 大理石湿贴施工 (16) 墙面干挂石材 (19) 马赛克饰面 (22) 墙面柱面贴瓷砖 (24) 木装饰墙身饰面 (28) 木材表面清油油漆涂饰 (30) 混凝土及抹灰面刷乳胶漆 (33) 玻璃墙面 (36) 铝塑板墙面 (37) 裱糊壁纸 (37) 大理石窗台板、暖气罩安装 (41) 墙面软包 (43) 木制吸音板墙面安装工艺 (46) 第三节、顶棚工程 (48) 轻钢龙骨石膏板吊顶 (48) 金属板吊顶 (49) 悬吊式顶棚装饰工艺 (51) 轻钢龙骨铝扣板吊顶 (52) 轻钢龙骨矿棉板吊顶 (53) 木质吸音板吊顶施工方案 (55)

轻钢龙骨木饰面吊顶 (57) 木格栅吊顶 (59) 第四节、细部工程 (61) 轻钢龙骨石膏板隔墙 (61) 玻璃隔墙安装 (64) 木门安装 (64) 铝合金门窗的安装 (68) 玻璃门安装 (70) 窗帘盒、窗帘杆、窗帘轨安装 (73) 聚氨脂防水工程 (75) 卫生间洗手盆柜安装 (76) 卫生间镜子安装 (78) 不锈钢楼梯栏杆、扶手施工工艺 (79) 金箔镶贴工艺 (80) 固定家具制作安装 (81) 木龙骨隔断墙的施工工艺流程 (84) 玻璃砖分隔墙施工工艺流程 (84) 镜面玻璃墙面施工工艺流程 (84) 第五节、机电工程 (85) 电气安装工程 (85) 配电箱安装工艺 (88) 卫生洁具安装 (91) 给水管道: (93) 排水管道安装: (93) 第二章、空调工程 (126) 风管工程施工方案 (126) 第三章、消防工程 (128) 消防系统安装 (128) 第四章、设备工程 (133) 厨房设备安装 (133) 室内煤气管道的安装原则 (134) 锅炉的搬运与就位 (135)

各种施工工艺大全

一、石材地面装饰构造 : 室内地面所用石材一般为磨光的板材,板厚 20 毫米左右,目前也有 薄板,厚度在10毫米左右,适于家庭装饰用。每块大小在 300毫米X 300毫米~500 毫 米X 500毫米。可使用薄板和1: 2水泥砂浆掺107胶铺贴。 石材地面装饰基本工艺流程: 清扫整理基层地面f 水泥砂浆找平f 定标高、弹线f 选料f 板材浸水 湿润f 安装标准块f 摊铺水泥砂浆f 铺贴石材f 灌缝f 清洁f 养护交工。 三、施工要点 : 基层处理要干净 ,高低不平处要先凿平和修补 , 基层应清洁,不能有砂 浆、 尤其是白灰砂浆灰、油渍等,并用水湿润地面。 铺装石材、瓷质砖时必须安放标准块 ,标准块应安放在十字线交点 ,对角 安装。 铺装操作时要每行依次挂线 ,石材必须浸水湿润 ,阴干后擦净背面。 石材、 瓷质砖地面铺装后的养护十分重要 ,安装 24 小时后必须洒水养 护, 铺巾完后覆盖锯末养护。 四、注意事项。 (1) 面花色一致。 (2) 问题。 (3) 铺贴 陶瓷地面砖基本工艺流程 1 、铺贴彩色釉面砖类: 处理基层-弹线-瓷砖浸水湿润-摊铺水泥砂浆-安装标准块-铺贴 地面砖T 勾缝 —清洁—养护。 2、铺贴陶瓷锦砖(马赛克)类: 处理基层f 弹线、标筋f 摊铺水泥砂浆f 铺贴f 拍实f 洒水、揭纸f 拨 缝、灌缝f 清洁f 养护。 铺贴陶瓷地砖的施工要点 1、 混凝土地面应将基层凿毛,凿毛深度 5~ 1 0毫米,凿毛痕的间距为 30 毫米左右。之后,清净浮灰,砂浆、油渍,产散水刷少将地面。 2、 铺贴前应弹好线,在地面弹出与门道口成直角的基准线 ,弹线应从 门口 开始 ,以保证进口处为整砖 ,非整砖置于阴角或家具下面 ,弹线应弹出纵横定位控 制线。 3、铺贴陶瓷地面砖前,应先将陶瓷地面砖浸泡阴干。 4、铺贴时,水泥砂浆应饱满地抹在陶瓷地面砖背面,铺贴后用橡皮 棰敲实。同时,用水平尺检查校正,擦净表面水泥砂浆。 5、铺贴完 2~3 小时后,用白水泥擦缝,用水泥、砂子 =1:1(体积比 ) 的水泥砂浆 ,缝要填充密实 ,平整光滑。再用棉丝将表面擦净。 铺贴前将板材进行试拼,对花、对色、编号,以入铺设出的地 石材必须浸水阴干。以免影响其凝结硬化,发生空鼓、起壳等 铺贴完成后, 2~3 天内不得上人。

英文名字中英文对照大全

男性英文名: Aaron艾伦巍然的高山受神启示的 Abbott艾布特父性的伟大的精神 Abel亚伯-生命呼吸 Abner艾伯纳睿智有智慧 Abraham亚伯拉罕崇高的父亲众人之父 Adair亚岱尔犹如像树般坚强 Adam亚当天下第一个男人 Adolph阿道夫高贵的狼 Adonis亚度尼斯美男子 Alan艾伦英俊的好看的和睦和平高兴的 Albert艾伯特高贵的聪明人类的守护者 Aldrich奥德里奇英明的统治者 Alexander亚历山大人类的保护者国王的名字 Alfred亚尔弗列得条顿睿智的顾问聪明帮手 Alger阿杰尔光荣高贵护卫 Allen艾伦英俊的好看的 Alston奥斯顿出身高贵的人 Alva阿尔瓦白种人的金发碧眼的 Alvin阿尔文被大家所喜爱的每个人的朋友 Alvis亚尔维斯短小精悍的人 Amos亚摩斯任重道远的人 Andre安得烈勇敢的骁勇的 Andrew安德鲁勇敢的骁勇的 Andy安迪勇敢的骁勇的 Angelo安其罗上帝的使者 Augus安格斯一个唯一无二的 Ansel安西尔出身极高贵的人教养极高贵的人 Antony安东尼值得赞美备受尊崇的 Antonio安东尼奥值得赞美备受尊崇的 Archer阿奇尔拉开千钧之弓的大力士 Archibald阿奇柏德高贵的勇敢的 Aries亚力士公羊牡羊座 Arlen亚尔林誓约 Armand亚尔曼军人 Armstrong阿姆斯壮臂力强健的人我的一小步是人类的一大步Arno阿诺鹰Arthur亚瑟高尚的贵族的 Arvin艾文以平等之心待人者 Asa亚撒上帝的赐予治愈者 Atwood亚特伍德住在森林森林中的人 Aubrey奥布里有钱有势的国王 August奥格斯格神圣的尊崇的身份高尚的人八月 Augustine奥古斯汀指八月出生的人 Avery艾富里淘气爱恶作剧的人

玫瑰花花语_玫瑰花的花语_玫瑰花语大全(最全面)

玫瑰花花语_玫瑰花的花语_玫瑰花语大全(最全面) 玫瑰代表爱情,但不同颜色的玫瑰花的花语是什么?不同朵数的玫瑰花又代表什么意思?玫瑰花有哪些送法?以下是小编总结的玫瑰花语知识,欢迎参阅。 玫瑰花语:爱情、爱与美、容光焕发 玫瑰花是“爱情之花”。特别是2月14日,西方情人节,农历正月十五日、七月七日,东方情人节,在爱情之河畅游的年轻人,都用此花献给自己的心上人来表达自己的感情。在古希腊神话中,玫瑰花集爱与美于一身,既是美神的化身,又溶进了爱神的血液。可以说,在世界范围内,玫瑰是用来表达爱情的通用语言,形成了永不凋零的玫瑰花花语文化。 玫瑰花不同数量的花语 1朵:你是我的唯一 2朵:世界上只有你和我 3朵:I LOVE YOU 4朵:誓言、承诺 5朵:无悔 6朵:顺心如意、顺利、永结同心、愿你一切顺利 7朵:喜相逢、偷偷爱着你 8朵:贵弥补、歉意、弥补、深深歉意、请原谅我 9朵:长相守、坚定 10朵:十全十美

11朵:爱你一生一世 12朵:全部的爱比翼双飞、圆满组合、心心相印、每日思念对方13朵:暗恋 14朵:骄傲 15朵:守住你的人 16朵:一帆风顺 17朵:伴你一生 18朵:青春美丽 19朵:爱的最高点 20朵:两情相爱 21朵:最爱 22朵:双双对对、两情相悦,你浓我浓、两情相悦、双双对对24朵:思念、纯洁的爱 30朵:请接受我的爱 33朵:三生三世 36朵:我的爱只留给你 40朵:誓死不渝的爱情 44朵:至死不渝、山盟海誓、恒古不变的誓言 48朵:挚爱 50朵:无悔的爱 51朵:我心中只有你 57:吾爱吾妻、 56朵:吾爱、

66朵:顺利、事事顺利、情场顺利、六六大顺、细水长流我的爱永远不变77朵:喜相逢、求婚、情人相逢、相逢自是有缘 88朵:弥补歉意、用心弥补一切的错 99朵:天长地久 100朵:白头偕老 101朵:直到永远的爱 108朵:求婚 111朵:一生一世只爱你一个 123朵:爱情自由、自由之恋 144朵:爱你生生世世、12×12爱你日日月月生生世世 365朵:天天爱你 999朵:无尽的爱天长地久,爱无止休长相厮守、至死不渝 1000朵:忠诚的爱,至死不渝 1001朵:直到永远 玫瑰花数量的其它含义 1朵玫瑰代表——我的心中只有你! 2朵玫瑰代表——这世界只有我俩! 3朵玫瑰代表——我爱你! 4朵玫瑰代表——至死不渝! 5朵玫瑰代表——由衷欣赏! 6朵玫瑰代表——互敬,互爱,互谅! 7朵玫瑰代表——我偷偷地爱著你! 8朵玫瑰代表——感谢你的关怀扶持及鼓励!

吸音板施工工艺大全

施工工艺大全——木制吸音板墙面安装工艺 一、材料说明: 木质吸音板,采用国内外先进技术、运用最新声学理论,声学效果明显,安装简单便捷,符合环保要求,在国内新型建筑装饰工程中得到了广泛的应用。 1、龙骨 (1)吸音板覆盖的墙面必须按设计图或施工图的要求安装龙骨,并对龙骨进行调平处理。龙骨表面应平整、光滑、无锈蚀、无变形。 (2)结构墙体要按照建筑规范进行施工前处理,龙骨的排布尺寸一定要和吸音板的排布相适应。木龙骨间距应小于300mm,轻钢龙骨间距不大于400mm。龙骨的安装应与吸音板长度方向相垂直。 (3)木龙骨表面到基层的距离按照具体要求,一般为50mm。木龙骨边面平整度及垂直度误差应不大于0.5mm。 (4)龙骨间隙内需要填充物的,应按设计要求先行安装、处理,并保证不影响吸音板的安装。 二、安装: 1、测量墙面尺寸,确认安装位置,确定水平线和垂直线,确定电线插口、管子等物体的切空预留尺寸。 2、按施工现场的实际尺寸计算并裁开部分吸音板(对立面上有对

称要求的,尤其要注意裁开部分吸音板的尺寸,保证两边的对称)和线条(收边线条、外角线条、连接线条),并为电线插口、管子等物体切空预留。 3、安装吸音板: (1)吸音板的安装顺序,遵循从左到右、从下到上的原则。(2)吸音板横向安装时,凹口朝上;竖直安装时,凹口在右侧。(3)部分实木吸音板有对花纹要求的,每一立面应按照吸音板上事先编制好的编号依次从小到大进行安装。(吸音板的编号遵循从左到右、从下到上、数字依次从小到大) 4、吸音板在龙骨上的固定: (1)木龙骨:用射钉安装 沿企口及板槽处用射钉将吸音板固定在龙骨上,射钉必须有2/3 以上嵌入木龙骨,射钉要均匀排布,并要求有一定的密度,每块吸音板与每条龙骨上联结射钉数量不少于10 个。 (2)轻钢龙骨:采用专用安装配件 吸音板横向安装,凹口朝上并用安装配件安装,每块吸音板依次相接。吸音板竖直安装,凹口在右侧,则从左开始用同样的方法安装。二块吸音板端要留出不小于3mm 的缝隙。 5、对吸音板有收边要求时,可采用编号为580 收边线条对其进行收边,收边处用螺钉固定。对右侧、上侧的收边线条安装时为横向膨胀预留1.5mm,并可采用硅胶密封。 6、墙角处吸音板安装有二种方法,密拼或用588 线条固定。

建筑工程施工工艺流程大全

施工技术合理化建议 1、建议本工程的设计师到场,以确保现场出现的施工技术问题时能够按照业主的合理要求,以最合理的方案,最快的速度、最有效的措施进行协调解决,保证施工顺利进行,从而提高效率,降低成本。 2、建议业主召开施工前的进度计划会议。工程不能按业主要求如期交付使用,是当前工程施工中存在的比较普遍的问题,虽然因素诸多,但施工组织管理不力是主要原因。因此应细化各施工队的进度计划,制定一个合理的符合实际的总进度表并认真监督执行,以确保各施工队以最低的消耗、最快的效率、最短的工期完成本工程。 3、建议业主进行开工前的技术会审,尽量做到施工时无变更,过程中少签证,减少施工过程中不必要的浪费,使本工程既能保证按期完工,又能较好地体现出原装饰设计方案的效果,这就需要各施工方对图纸的研究、理解细之又细,严之又严。以避免施工中出现疏漏给业主造成不必要的浪费。 4、建议业主成立现场施工领导小组,由业主负责、监理挂帅、各参建单位参加 (1)每天一个碰头会,汇总当天进度、摆出问题及解决办法、安排第二天的工作,可采取现场讲评。 (2)成立技术领导小组,由监理和总包方技术负责人挂帅,经常性就工地各类技术问题进行会审,解决问题不过夜,以确保工程顺利进行。 (3)成立安全文明检查小组,由各施工队出人轮流值班检查工地安全文明施工情况,要求当值人员做好值班记录,以备业主和监理可随时检查。 (4)实行奖惩制度,对不按进度施工的、不安全文明施工的施工队要进行罚款。罚金用于奖励表现好的施工队。 (5)监督举报制度,所有人员都可对不安全不文明现象进行举报,一经查实罚款的50%奖励举报人。这是强化工地管理的有效方法。

各种花语大全

各种花语大全 郁金香——爱的表白、荣誉、祝福、永恒 郁金香(紫) ——无尽的爱、最爱郁金香(白)——纯情、纯洁郁金香(粉) ——美人、热爱、幸福郁金香(红) ——爱的告白、喜悦郁金香(黄) ——高贵、珍重、财富 百合——顺利、心想事成、祝福香水百合——纯洁、富贵、婚礼的祝福 百合(白) ——纯洁、庄严、心心相印葵百合——胜利、荣誉、富贵 姬百合——财富、高雅 蔷薇——追忆 康乃馨——母亲我爱您、热情、真情 康乃馨(红)——相信您的爱康乃馨(粉) ——热爱、美丽 康乃馨(白)——纯结的友谊 菊花——清静、高雅、真爱菊花——清静、高洁、真爱、我爱非洲菊——神秘、兴奋、 有毅力 波斯菊——永远快乐 玫瑰——爱情 红玫瑰——热恋 粉玫瑰——永远的爱 白玫瑰——纯纯的爱 黄玫瑰——失恋、褪去的爱 火鹤花——新婚、祝福、幸运、快乐风信子——喜悦、爱意、浓情蜜意小苍兰——纯洁、幸福、清新舒畅 海芋——希望、雄壮之美 彩色海芋——爱情、富贵、真情剑兰——用心、长寿、福禄、康宁向日葵——爱慕、光辉、忠诚 各种花语大全

2017-05-11 10:42 | #2楼 郁金香——爱的表白、荣誉、祝福、永恒郁金香(紫) ——无尽的爱、最爱 郁金香(白)——纯情、纯洁 郁金香(粉) ——美人、热爱、幸福 郁金香(红) ——爱的告白、喜悦 郁金香(黄) ——高贵、珍重、财富 百合——顺利、心想事成、祝福 香水百合——纯洁、富贵、婚礼的祝福百合(白) ——纯洁、庄严、心心相印 葵百合——胜利、荣誉、富贵 姬百合——财富、高雅 蔷薇——追忆 康乃馨——母亲我爱您、热情、真情 康乃馨(红)——相信您的爱 康乃馨(粉) ——热爱、美丽 康乃馨(白)——纯结的友谊

各种施工工艺标准

基础工程施工操作要点(管桩) 一、施工准备 1、对现场管理人员和施工班组进行专项技术交底; 2、场地平整:要求高差控制在0.5%以下,周边做好排水沟,以便桩机顺利行走; 3、在打桩区域,对地下及地上的障碍物及时清除; 4、为保证桩的精度,控制点测设后,须经复核,合格后才能移交施工队正式施工; 二、施工流程 测量放线定桩位桩机就位插桩校正桩身垂直度沉桩吊下一节桩焊接接桩焊接点检查验收送桩至设计标高移至下一桩位 三、操作要点 1、桩机的基础必须稳固,安装必须周正、水平,压桩时,导向压桩架、送桩器和桩身应在同一条中心线上; 2、采用双向经纬仪校正桩身垂直,经纬仪应放在距桩机20米处,成90度方向设置。如发现垂直度超标(0.5%),应及时调整、重新压桩; 3、压桩过程中必须使管桩轴心受压,若有偏移及时调整,确保垂直度偏差不大于0.5%。焊接桩前要校正好上下桩管的垂直度,上下节桩中心线偏差小于2mm; 4、桩顶最后的标高应采用水准仪控制。根据区块的自然地面标高的不同并标记于桩位编号图上;送桩器以红漆明显标记不同的送桩深度位置,送桩时严格控制,务使桩顶标高允许偏差控制在-50~0mm之间; 四、质量标准 1、管桩堆放高度不得超过4层,并在底部垂直于桩长度方向设置2道垫木,垫木分别设置于距桩端0.2倍桩长处; 2、下节桩的桩头易设导向箍,上下两节桩的桩端偏差不宜大于2mm; 3、接桩宜采用E43焊条或气保焊,焊接前采用钢丝刷将上下端板表面清理干净;焊接时应分层焊接,确保焊缝饱满、连续,分层次数不少于3层; 4、接好的桩头应待自然冷却后方可继续送桩,自然冷却时间不宜小于8分钟,严禁水冷或接好后就施工;

英文名字中英文对照大全

男性英文名: Aaron 艾伦巍然的高山受神启示的 Abbott 艾布特父性的伟大的精神 Abel 亚伯 - 生命呼吸 Abner 艾伯纳睿智有智慧 Abraham 亚伯拉罕崇高的父亲众人之父 Adair 亚岱尔犹如像树般坚强 Adam 亚当天下第一个男人 Adolph 阿道夫高贵的狼 Adonis 亚度尼斯美男子 Alan 艾伦英俊的好看的和睦和平高兴的 Albert 艾伯特高贵的聪明人类的守护者 Aldrich 奥德里奇英明的统治者 Alexander 亚历山大人类的保护者国王的名字 Alfred 亚尔弗列得条顿睿智的顾问聪明帮手 Alger 阿杰尔光荣高贵护卫 Allen 艾伦英俊的好看的 Alston 奥斯顿出身高贵的人 Alva 阿尔瓦白种人的金发碧眼的 Alvin 阿尔文被大家所喜爱的每个人的朋友 Alvis 亚尔维斯短小精悍的人 Amos 亚摩斯任重道远的人 Andre 安得烈勇敢的骁勇的 Andrew 安德鲁勇敢的骁勇的 Andy 安迪勇敢的骁勇的 Angelo 安其罗上帝的使者 Augus 安格斯一个唯一无二的 Ansel 安西尔出身极高贵的人教养极高贵的人 Antony 安东尼值得赞美备受尊崇的 Antonio 安东尼奥值得赞美备受尊崇的 Archer 阿奇尔拉开千钧之弓的大力士 Archibald 阿奇柏德高贵的勇敢的 Aries 亚力士公羊牡羊座 Arlen 亚尔林誓约 Armand 亚尔曼军人 Armstrong 阿姆斯壮臂力强健的人我的一小步是人类的一大步 Arno 阿诺鹰Arthur 亚瑟高尚的贵族的 Arvin 艾文以平等之心待人者 Asa 亚撒上帝的赐予治愈者 Atwood 亚特伍德住在森林森林中的人 Aubrey 奥布里有钱有势的国王 August 奥格斯格神圣的尊崇的身份高尚的人八月 Augustine 奥古斯汀指八月出生的人 Avery 艾富里淘气爱恶作剧的人

各种花语大全

花语大全-各种花的花语 郁金香——爱的表白、荣誉、祝福、永恒郁金香(紫) ——无尽的爱、最爱 郁金香(白)——纯情、纯洁 郁金香(粉) ——美人、热爱、幸福 郁金香(红) ——爱的告白、喜悦 郁金香(黄) ——高贵、珍重、财富 百合——顺利、心想事成、祝福 香水百合——纯洁、富贵、婚礼的祝福

百合(白) ——纯洁、庄严、心心相印葵百合——胜利、荣誉、富贵 姬百合——财富、高雅 蔷薇——追忆 康乃馨——母亲我爱您、热情、真情康乃馨(红)——相信您的爱 康乃馨(粉) ——热爱、美丽 康乃馨(白)——纯结的友谊

菊花——清静、高雅、真爱 菊花——清静、高洁、真爱、我爱非洲菊——神秘、兴奋、有毅力波斯菊——永远快乐 玫瑰——爱情 红玫瑰——热恋 粉玫瑰——永远的爱 白玫瑰——纯纯的爱 黄玫瑰——失恋、褪去的爱

火鹤花——新婚、祝福、幸运、快乐风信子——喜悦、爱意、浓情蜜意小苍兰——纯洁、幸福、清新舒畅海芋——希望、雄壮之美 彩色海芋——爱情、富贵、真情剑兰——用心、长寿、福禄、康宁向日葵——爱慕、光辉、忠诚 牡丹——富贵 金鱼草——爱出风头 大理花——华丽、优雅 满天星——真心喜欢 圣诞红——祝福

星辰花——永不变心 桔梗——真诚的爱 玛格丽特——暗恋 迷失香——留住回忆 桃花——我是你的俘虏 薰衣草——等待爱情 三色堇——沉思、请想念我 芙蓉——纤细之美花箴言:世上没有爱情悲剧,只有因爱 而生的悲剧。 非洲堇——关怀我吧 四叶草——爱和幸运 铃兰——把握幸福 蒲公英——再次重逢前的分离 龙胆花——喜欢看忧伤时的你 莲花——信仰

月份中英文对照表

月份中英文对照表 月份中英文对照表 一月:January 简写 Jan. 二月:February 简写 Feb. 三月:March 简写 Mar. 四月:April 简写 Apr. 五月:May 简写 May. 六月:June 简写 Jun. 七月:July 简写 Jul. 八月:August 简写 Aug. 九月:September 简写 Sep. / Sept. 十月:October 简写 Oct. 十一月:November 简写 Nov. 十二月:December 简写 Dec 中英文颜色,月份,星期天对照表 中英文颜色,月份,星期天对照表 粉红 pink 杏色 skin 黄色 yellow 橙色 orange 紫色的、蓝色的 violet 蓝色 bluc 绿色 green 桃红 peachblow 炭灰 anthrazit 紫红色 mauve 克色 black 银色 silver 灰色 grey 军绿 armanigreen 银色的 silver 深红 rubycarmine 棕色 brown 枣红 aubergine 沙色 sand 浅湖蓝 ltturo

海蓝 electricblue 红色 red 灰绿 greygreen 湖蓝 ruro 枣红、酒红 burgundy 百色 white 卡其 khaki 花灰 greymarl 桔色 orange 宝蓝、深蓝 navy 米白米色 ivore 印花 printing 紫色 lilac 文字 letter 丝绸、丝带 silk 紫色的 purpic 绿叶 greenery 淡色 lavender 尼龙 nylon 浅绿色 aqua 灰色灰白 gray 墨水 ink 暗红 red 乳白色 milk 橙红的、浅红的 salmon 咖啡色 coffee 蛇 snake 彩蓝 turo 桔黄、金黄 saffron 浅绿 turquoise 玫红 rose 格子 grid 米白 geram 梅红、深红 strawberry 美国 Ameri 杏色米色 beige 星 star 深紫 purple 灰色的 dusty 日本 Japan 软的、温和的 soit 菱形 rhombus 黑色 black 淡黄色 primrose 工? ? ? 厂 factory 一月 January 二月 February 三月 March 四月 April 五月 May 七月 July 八月 August 九月 September 十月 October 六月 June 香港制造 Made in Hongkong 玫瑰红 rose 十一月 November 十二月 December 中国制造 Made in China 公司 company 车间 workshop 星期一星期二星期三星期四星期五星期六星期日 Monday Tuesday Wednesday Thursday Friday Saturday Sunday 1啰=12打=144码=132米 1码=36英寸=米 1米=码

各种花的花语及英文名称

中国水仙 new year lily 自尊/单恋石榴pomegranate 相思/永生 月桂 victor\'s laurel 胜利/不诚实报春花polyanthus 初恋/自作多情 木棉 cotton tree 热 情紫丁香 lilac 青春的回忆 吊钟 lady\'s eardrops 尝试/热心紫荆chinese redbud 故情/手足情 百合 lily 纯净/神 圣紫罗兰 wall flower 信任/爱的羁绊 桃花 peach 被你俘 虏紫藤 wistaria 沉迷的爱 杜鹃 azalea 爱的快乐/节制铃兰lily-of-the-valley 纤细/希望/纯洁 牡丹 tree paeony 富贵/羞怯银杏ginkgo 长寿 芍药 paeony 害 羞蝴蝶兰moth orchid 幸福/纯洁/吉祥

辛夷 violet magnolia 友情/爱自然蟹爪仙人掌christmas cactus 锦上添花 玫瑰 rose 爱情/爱与 美郁金香 tulip 名誉/慈善/美丽 茶花 common camelia 美德/谦逊千日红common globe-amaranth 永恒的爱/不朽 非洲堇 african vioet 永恒的美天人菊indian blanket 团结/协力 栀子花 cape jasmine 喜悦/纯洁木槿 rose of sharon 劝告/短暂的美 风信子 hyacinyh 悲哀/永远怀念百子莲african lily 爱的来临 牵牛花 morning glory 爱情/依赖君子兰kafir lily 宝贵/高贵 荷包花 lady\'s pocketbook 聚集财富含笑花 banana shrub 矜持/含蓄 非洲菊 african daisy 神秘/兴奋含羞草esnsitive plant 敏感 茉莉 arabian jasmine 你属于我/亲切猪笼草 pitcher plant 财源广进

相关主题