FIDIC CONTRACT OF DESIGN, PURCHASE AND CONSTRUCTION

(EPC)交钥匙项目合同条件

7 Plant, Materials and Workmanshi生产设备、材料和工艺

7.1 Manner of Execution实施方法

The Contractor shall carry out the manufacture of Plant, the production and manufacture of Materials, and all other execution of the Works:

(a) in the manner (if any) specified in the Contract,

(b) in a proper workmanlike and careful manner, in accordance with recognized good practice, and

(c) with properly equipped facilities and non-hazardous Materials, except as otherwise specified in the Contract.

承包商应按以下方法进行生产设备的制造、材料的生产加工、以及工程的所有其他实施作业:

按照合同规定的方法(如果有);

按照公认的良好惯例,使用恰当、精巧、仔细的方法;

除合同另有规定外,使用适当配备的设施和无危险的材料.

7.2 Samples样品

The Contractor shall submit samples to the Employer, for review in accordance with the procedures for Contractor’s Documents des cribed in Sub-Clause 5.2 [Contractor’s Documents], as specified in the Contract and at the Contractor’s cost. Each sample shall be labelled as to origin and intended use in the Works.

承包商应根据合同规定,按照第5.2款[承包商文件]中所述的对承包商文件的送审程序,自费向雇主提交样品,供其审核.每件样品应标明其原产地、及其在工程中预期的用处.

7.3 Inspection检验

The Employer’s Personnel shall at all reasonable times:

(a) have full access to all parts of the Site and to all places from which natural Materials are being obtained, and

(b) during production, manufacture and construction (at the Site and, to the extent specified in the Contract, elsewhere), be entitled to examine, inspect, measure and test the materials and workmanship, and to check the progress of manufacture of Plant and production and

manufacture of Materials.

雇主人员应在所有合理的时间内:

有充分机会进入现场的所有部分、以及获得天然材料的所有地点;

有权在加工、生产和施工期间(在现场和其他合同规定的范围),对材料和工艺进行检查、检验、测量和试验,并对生产设备的制造和材料的加工生产进度进行检查.

The Contractor shall give the Employer’s Personnel full opportunity to carry out these activities, including providing access, facilities, permissions and safety equipment. No such activity shall relieve the Contractor from any obligation or responsibility.

承包商应向雇主人员进行上述活动提供一切机会,包括提供进入条件、设施、许可和安全装备.此类活动不应解除承包商的任何义务和职责.

In respect of the work which Employer’s Personnel are entitled to examine, inspect, measure and/or test, the Contractor shall give notice to the Employer whenever any such work is ready and before it is covered up, put out of sight, or packaged for storage or transport. The Employer shall then either carry out the examination, inspection, measurement or testing without unreasonable delay, or promptly give notice to the Contractor that the Employer does not require to do so. If the Contractor fails to give the notice, he shall, if and when required by the Employer, uncover the work and thereafter reinstate and make good, all at the Contractor’s cost.

对于雇主人员有权检查、检验、测量和(或)试验的工作,每当任何此类工作已经准备好,在覆盖、掩蔽、包装以便储存或运输前,承包商应通知雇主.这时,雇主应及时进行检查、检验、测量和试验,不得无故拖延,或者立即通知承包商无需进行这些工作.如果承包商没有发出此类通知,而当雇主提出要求时,承包商应除去物件上的覆盖,并在随后恢复完好,所需费用由承包商承担.

7.4 Testing试验

This Sub-Clause shall apply to all tests specified in the Contract, other than the Tests after Completion (if any).

本款适用于竣工后试验(如果有)以外的合同规定的所有试验.

The Contractor shall provide all apparatus, assistance, documents and other information, electricity, equipment, fuel, consumables, instruments, labor, materials, and suitably qualified and experienced staff, as are necessary to carry out the specified tests efficiently. The Contractor shall agree, with the Employer, the time and place for the specified testing of any Plant, Materials and other parts of the Works.

为有效进行规定的试验,承包商应提供所需的所有仪器、帮助、文件和其他资料、电力、装备、燃料、消耗品、工具、劳力、材料,以及具有适当资质和经验的人员,对任何生产设备、

材料和工程其他部分进行规定的试验,其时间和地点,应由承包商和雇主商定.

The Employer may, under Clause 13 [Variations and Adjustments], vary the location or details of specified tests, or instruct the Contractor to carry out additional tests. If these varied or additional tests show that the tested Plant, Materials or workmanship is not in accordance with the Contract, the cost of carrying out this Variation shall be borne by the Contractor, notwithstanding other provisions of the Contract.

根据第13条[变更和调整]的规定,雇主可以改变进行规定试验的位置或细节,或指示承包商进行附加的试验.如果这些变更或附加的试验表明,经过试验的生产设备、材料、或工艺不符合合同的要求,不管合同有何其他规定,承包商应负担进行本项变更的费用.

The Employer shall give the Contractor not less than 24 hours’ notice of the Employer’s intention to attend the tests. If the Employer does not attend at the time and place agreed, the Contractor may proceed with the tests, unless otherwise instructed by the Employer, and the tests shall then be deemed to have been made in the Employer’s presence.

雇主应至少提前24小时将参加试验的意图通知承包商.如果雇主没有在商定的时间和地点参加试验,除非雇主另有指示,承包商可以自行进行试验,这些试验应被视为是在雇主在场情况下进行的.

If the Contractor suffers delay and/or incurs Cost from complying with these instructions or as a result of a delay for which the Employer is responsible, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:

如果由于服从这些指示,或因雇主应负责的延误的结果,使承包商遭受延误和(或)招致费用,承包商应向雇主发出通知,并有权根据第20.1款[承包商的索赔]的规定提出:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

根据第8.4款[竣工时间的延长]的规定,如果竣工已或将受到延误,对任何此类延误给予延长期;

(b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.

任何上述费用加合理利润应加入合同价格,给予支付.

After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

雇主在收到此通知后,应按照第3.5款[确定]的要求对此类事项进行商定或确定.

The Contractor shall promptly forward to the Employer duly certified reports of the tests. When

the specified test s have been passed, the Employer shall endorse the Contractor’s test certificate, or issue a certificate to him, to that effect. If the Employer has not attended the tests, he shall be deemed to have accepted the readings as accurate.

承包商应立即向雇主提交充分证实的试验报告.当规定的试验通过时,雇主应在承包商的试验证书上签字认可,或向承包商颁发等效的证书.如果雇主未参加试验,他应被视为已经认可试验示数是准确的.

7.5 Rejection拒收

If, as a result of an examination, inspection measurement or testing, any Plant, Materials, design or workmanship is found to be defective or otherwise not in accordance with the Contract, the Employer may reject the Plant, Materials, design or workmanship by giving notice to the Contractor, with reasons. The Contractor shall then promptly make good the defect and ensure that the rejected item complies with the Contract.

如果检查、检验、测量或试验结果,发现任何生产设备、材料、设计或工艺有缺陷,或不符合合同要求,雇主可通过向承包商发出通知,并说明理由,拒收该生产设备、材料、设计或工艺.承包商应立即修复缺陷,并保证上述被拒收的项目符合合同的规定.

If the Employer requires this Plant, Materials, design or workmanship to be retested, the tests shall be repeated under the same terms and conditions. If the rejection and retesting cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these costs to the Employer.

如果雇主要求对上述生产设备、材料、设计或工艺再次进行试验,这些试验应按相同的条款和条件重新进行.如果此项拒收和再次试验使雇主增加了费用,承包商应遵照第2.5款[雇主的索赔]的规定,将该费用付给雇主.

7.6 Remedial Work修补工作

Notwithstanding any previous test or certification, the Employer may instruct the Contractor to:

(a) remove from the Site and replace any Plant or Materials which is not in accordance with the Contract,

(b) remove and re-execute any other work which is not in accordance with the Contract, and

(c) execute any work which is urgently required for the safety of the Works, whether because of an accident, unforeseeable event or otherwise.

尽管已有先前的任何试验或证书,雇主仍可指示承包商进行以下工作:

(i) 将不符合合同要求的任何生产设备或材料移出现场,并进行更换;

(ii)去除不符合合同的任何其他工作,并重新实施;

(iii)实施因意外、不可预见的事件或其他原因引起的、为工程的安全迫切需要的任何工作.

If the Contractor fails to comply with any such instruction, which complies with Sub-Clause 3.4 [Instructions], the Employer shall be entitled to employ and pay other persons to carry out the work. Except to the extent that the Contractor would have been entitled to payment for the work, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay to the Employer all costs arising from this failure

如果承包商未能服从任何此类符合第3.4款[指示]要求的指示,雇主应有权雇用并付款给他人从事该工作.除承包商原有权从该工作所得付款的范围外,承包商应遵照第2.5款[雇主的索赔]的规定,向雇主支付因他未履行指示而使雇主支付的所有费用.

7.7 Ownership of Plant and Materials生产设备和材料的所有权

Each item of Plant and Materials shall, to the extent consistent with the Laws of the Country, become the property of the Employer at whichever is the earlier of the following times, free from liens and other encumbrances:

(a) when it is delivered to the Site;

(b) when the Contractor is entitled to payment of the value of the Plant and Materials under Sub-Clause 8.10 [Payment for Plant and Materials in Event of Suspension].

从下列二者中较早的时间起,在符合工程所在国法律规定范围内,每项生产设备和材料都应无扣押和其他阻碍的成为雇主的财产.

当上述生产设备、材料运至现场时;

当根据第8.10款[暂停时对生产设备和材料的支付]的规定,承包商有权得到按生产设备和材料价值的付款时.

7.8 Royalties土地(矿区)使用费

Unless otherwise stated in the Employer’s Requirements, the Contractor shall pay all royalties, rents and other payments for:

(a) natural Materials obtained from outside the Site, and

(b) the disposal of material from demolitions and excavations and of other surplus material (whether natural or man-made), except to the extent that disposal areas within the Site are specified in the Contract.

除非在雇主要求中另有说明,承包商应为以下事项支付所有的土地(矿区)使用费、租金和其他付款:

从现场以外地区得到的天然材料;

在合同规定的现场范围内的弃置区以外,弃置拆除、开挖的材料和其他剩余材料(不论是天然的或人工的).

8.1 Commencement of Works工程的开工

Unless otherwise stated in the Contract Agreement:

(a) the Employer shall give the Contractor no t less than 7 days’ notice of the Commencement Date; and

(b) the Commencement Date shall be within 42 days after the date on which the Contract comes into full force and effect under Sub-Clause 1.6 [Contract Agreement].

The Contractor shall commence the design and execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay.

除非合同协议书另有说明:

雇主应在不少于7天前向承包商发出开工日期的通知;

开工日期应在第1.6款[合同协议书]规定的合同全面实施和生效日期后42天内.

承包商应在开工日期后,在合理可能情况下尽早开始工程的设计和施工,随后应以正当速度,不拖延地进行工程.

8.2 Time for Completion竣工时间

The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the Works or Section (as the case may be), including:

(a) achieving the passing of the Tests on Completion, and

(b) completing all work which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking-over under Sub-Clause 10.1 [Taking Over of the Works and Sections].

承包商应在工程或分项工程(视情况而定)的竣工时间内,完成整个工程和每个分项工程(如果有),包括:

竣工试验获得通过;完成合同提出的、工程和分项工程按照第10.1款[工程和分项工程的接收]

规定的接收要求竣工所需要的全部工作.

8.3 Programme进度计划

The Contractor shall submit a time programme to the Employer within 28 days after the Commencement Date. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor’s obligations. Unless otherwise stated in the Contract, each programme shall include:

(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works,

(b) the periods for reviews under Sub-Clause 5.2 [Contractor’s Documents],

(c) the sequence and timing of inspections and tests specified in the Contract, and

(d) a supporting report which includes:

(i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the Works, and

(ii) the approximate numb er of each class of Contractor’s Personnel and of each type of Contractor’s Equipment for each major stage.

承包商应在开工日期后28天内,向雇主提交一份进度计划.当原定进度计划与实际进度或承包商的义务不相符时,承包商还应提交一份修订的进度计划.除非合同另有说明,每份进度计划应包括:

承包商计划实施工程的工作顺序,包括工程各主要阶段的预期时间安排;根据第5.2款[承包商文件]规定的审核期限;合同中规定的各项检验和试验的顺序的顺序和时间安排;一份支持报告,内容包括:承包商在工程各主要阶段的实施中拟采用的方法的一般描述;各主要阶段配备的各级承包商人员和各类型承包商设备的大概数量.

Unless the Employer, within 21 days receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Employer’s Personnel shall be entitled to rely upon the programme when planning their activities.

除非雇主在收到进度计划后21天内向承包商发出通知,指出其中不符合合同要求的部分,承包商即按照该进度计划,并遵守合同规定的其它义务,进行工作.雇主人员应有权依照该进度计划安排他们的活动.

The Contractor shall promptly give notice to the Employer of specific probable future events or

circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Employer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor’s stated intentions, the Contractor shall submit a revised programme to the Employer in accordance with this Sub-Clause.

承包商应及时将未来可能对工程施工造成不利影响或延误的事件或情况通知雇主.在此情况下,或在雇主通知承包商指出进度计划(在指出的部分)不符合合同要求,或与实际进度或承包商提出的意向不一致时,承包商应遵照本款要求向雇主提交一份修订进度计划.

8.4 Extension of Time for Completion竣工时间延长

The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’ Claims] to an extensi on of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works and Sections] is or will be delayed by any of the following causes:

(a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]),

(b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions, or

(c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site.

如由于下列任何原因,致使达到按照第10.1款[工程和分项工程的接收]要求的竣工受到或将受到延误的程度,承包商有权按照第20.1款[承包商的索赔]的规定提出延长竣工时间:

变更(除非已根据第13.3款[变更程序]的规定商定调整了竣工时间);

根据本条件某款,有权获得延长期的原因;或

由雇主、雇主人员、或在现场的雇主的其他承包商造成或引起的任何延误、妨碍和阻碍.

If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Employer in accordance with Sub-Clause 20.1 [Contractor’s Claims]. When determining each extension of time under Sub-Clause 20.1, the Employer shall review previous determinations and may increase, but shall not decrease, the total extension of time.

如果承包商认为他有权提出延长竣工时间,应按照第20.1款[承包商的索赔]的规定,向雇主发出通知.雇主每次按照第20.1款确定延长时间时,应对以前所作的确定进行审核,可以增加,但不得减少总的延长时间.

8.5 Delays Caused by Authorities当局造成的延误

If the following conditions apply, namely:

(a) the Contractor has diligently followed the procedures laid down by the relevant legally constituted public authorities in the Country,

(b) these authorities delay or disrupt the Contractor’s work, and

(c) the delay or disruption was not reasonably foreseeable by an experienced contractor by the date for submission of the Tender,

then this delay or disruption will be considered as a cause of delay under sub-paragraph (b) of Sub-Clause 8.4 [Extension of Time for Completion].

如果符合下列条件,即:

承包商已努力遵守了工程所在国依法成立的有关公共当局所制定的程序;

这些当局延误或打乱了承包商的工作;

延误或中废是一个有经验的承包商在递交投标书时无法合理预见的;

则上述延误或中断应被视为根据第8.4款[竣工时间的延长](b)项规定的延误的原因.

8.6 Rate of Progress工程进度

If, at any time:

(a) actual progress is too slow to complete within the Time for Completion, and/or

(b) progress has fallen (or will fall) behind the current programme under Sub-Clause 8.3 [Programme],

如果在任何时候:

实际工程进度对于在竣工时间内完工过于迟缓,和(或)

进度已(或将)落后于根据第8.3款[进度计划]的规定制订的现行进度计划,

other than as a result of a cause listed in Sub-Clause 8.4 [Extension of Time for Completion], then the Employer may instruct the Contractor to submit, under Sub-Clause 8.3 [Programme], a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion.

除由于第8.4款[竣工时间的延长]中列举的某项原因造成的结果外,雇主可指示承包商根据第8.3款[进度计划]的规定提交一份修订的进度计划,以及说明承包商为加快进度在竣工时间内竣工,建议采取的修订方法的补充报告.

Unless the Employer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in t he numbers of Contractor’s Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7 below.

除非雇主另有通知,承包商应采取这些修订方法,对可能需要增加工时、和(或)承包商人员和(或)货物的数量,承包商应自行承担风险和费用.如果这些修订方法使雇主招致附加费用,承包商应根据第2.5款[雇主的索赔]的要求,连同下述第8.7款中提出的误期损害赔偿费(如果有),向雇主支付这些费用.

8.7 Delay Damages误期损害赔偿费

If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum stated in the Particular Conditions, which shall be paid for every day which shall elapse between the relevant Time for Completion and the date stated in the Taking-Over Certificate. However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Particular Conditions.

如果承包商未能遵守第8.2款[竣工时间]的要求,承包商应当为其违约行为,根据第2.5款[雇主的索赔]的要求向雇主支付误期损害赔偿费.此项误期损害赔偿费应按照专用条件中规定的每天应付金额,以接收证书上注明的日期超过相应的竣工时间的天数计算.但按本款计算的赔偿总额,不得超过专用条件中规定的误期损害赔偿费的最高限额(如果有).

These delay damages shall be the only damages due from the Contractor for such default, other than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the Works, These damages shall not relieve the Contractor from his obligation to complete the works,or from any other duties, obligations or responsibilities which he may have under the Contract.

除在工程竣工前根据第15.2款[由雇主终止]的规定终止的情况外,这些误期损害赔偿费应是承包商为此类违约应付的唯一损害赔偿费.这些损害赔偿费不应解除承包商完成工程的义务,或合同规定的其可能承担的其他责任、义务或职责.

8.8 Suspension of Work暂时停工

The Employer may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store and secure such part or the Works against any deterioration, loss or damage.

雇主可以随时指示承包商暂停工程某一部分或全部的施工.在暂停期间,承包商应保护、保管、

并保证该部分或全部工程不致产生任何变质、损失或损害.

The Employer may also notify the cause for the suspension. If and to the extent that the cause is notified and is the responsibility of the Contractor, the following Sub-Clauses 8.9, 8.10 and 8.11 shall not apply.

雇主还可以通知暂停的原因.如果是已通知了原因,而且是由于承包商的职责造成的情况,则下列第8.9、8.10和8.11款应不适用.

8.9 Consequences of Suspension暂停的后果

If t he Contractor suffers delay and/or incurs Cost from complying with the Employer’s instructions under Sub-Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost, which shall be added to the Contract Price.

如果承包商因执行雇主根据第8.8款[暂时停工]的规定发出的指示,和(或)因为复工,而遭受延误和(或)招致增加费用,承包商应向雇主发出通知,并有权依照第20.1款[承包商的索赔]的规定提出:

根据第8.4款[竣工时间的延长]的规定,如竣工已或将受到延误,应对任何此类延误给予延长期;

对任何此类费用应加入合同价格,给予支付.

After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

雇主收到此通知后,应按照第3.5款[确定]的要求,对这些事项进行商定或确定.

The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contr actor’s faulty design, workmanship or materials, or of the Contractor’s failure to protect, store or secure in accordance with Sub-Clause 8.8 [Suspension of Work].

承包商应无权得到为弥补因承包商有缺陷的设计、工艺或材料,或因承包商未能按照第8.8款[暂时停工]的规定保护、保管、或保证安全的后果,带来的延长期和招致费用的支付.

8.10Payment for Plant and Materials in Event of Suspension暂停时对生产设备和材料的付款The Contractor shall be entitled to payment of the value (as at the date of suspension) of Plant

and/or Materials which have not been delivered to Site, if:

(a) the work on Plant or delivery of Plant and/or Materials has been suspended for more than 28 days, and

(b) the Contractor has marked the Plant and/or Materials as the Employer’s property in accordance with the Employer’s instructions.

在下列条件下,承包商有权得到尚未运到现场的生产设备和(或)材料(按暂停开始日期时)的价值的付款:

生产设备的生产、或生产设备和(或)材料的交付被暂停达到28天以上;

承包商已按雇主的指示,标明上述生产设备和(或)材料为雇主的财产.

8.11 Prolonged Suspension 拖长的暂停

If the suspension under Sub-Clause 8.8 [Suspension of Work] has continued for more than 84 days, the Contractor may request th e Employer’s permission to proceed. If the Employer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Employer, treat the suspension as an omission under Clause 13 [Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under Sub-Clause 16.2 [Termination by Contractor].

如果第8.8款[暂时停工]所述的暂停已持续84天以上,承包商可以要求雇主允许继续施工.如在提出这一要求后28天内,雇主没有给出许可,承包商可以通知雇主,将工程受暂停影响的部分视为根据第13条[变更和调整]规定的删减项目.若暂停影响到整个工程,承包商可以根据第16.2款[由承包商终止]的规定发出终止的通知.

8.12 Resumption of Work复工

After the permission or instruction to proceed is given, the Parties shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

在发出继续施工的许可或指示后,双方应共同对受暂停影响的工程、生产设备和材料进行检查.承包商应负责恢复在暂停期间发生的工程或生产设备或材料的任何变质、缺陷或损失.

9Tests on Completion竣工试验

9.1 Contractor’s Obligations承包商的义务

The Contractor shall carry out the Tests on Completion in accordance with this Clause and Sub-Clause 7.4 [Testing], after providing the documents in accordance with Sub-Clause 5.6 [As-Built Documents] and Sub-Clause 5.7 [Operation and Maintenance Manuals].

承包商应按照第5.6款[竣工文件]和第5.7款操作和维修手册]的要求,提供各种文件后,按照本条和第7.4款[试验]的要求进行竣工试验.

The Contractor shall give to the Employer not less than 21 days’ notice of the date after which the Contractor will be ready to carry out each of the Tests on Completion. Unless otherwise agreed, Tests on Completion shall be carried out within 14 days after this date, on such day or days as the Employer shall instruct.

承包商应提前21天将他可以进行每项竣工试验的日期通知雇主.除非另有商定,竣工试验应在此通知日期后的14天内,在雇主指示的某日或某几日内进行.

Unless otherwise stated in the Particular Conditions, the Tests on Completion shall be carried out in the following sequence:

(a) pre-commissioning tests, which shall include the appropriate inspections and (“dry” or “cold”) functional tests to dem onstrate that each item of Plant can safely under-take the next stage, (b);

(b) commissioning tests, which shall include the specified operational texts to demonstrate that the Works or Section can be operated safely and as specified, under all available operating conditions; and

(c) trial operation, which shall demonstrate that the Works or Section perform reliably and in accordance with the Contract.

除非在专用条件中另有说明,竣工试验应按照以下顺序进行:

启动前试验,应包括适当的检验和(“干”或“冷”)性能试验,以证明每项生产设备能够安全地承受下一阶段(b)项试验;

启动试验,应包括规定地操作试验,以证明工程或分项工程能够在所有可利用地操作条件下安全地操作.

试运行,应证明工程或分项工程运行可靠,符合合同要求.

During trial operation, when the Works are operating under stable conditions, the Contractor shall give notice to the Employer that the Works are ready for any other Tests on Completion, including performance tests to demonstrate whether the Works conform with criteria specified in the Employer’s Requirements and with the Performance Guarantees.

在试运行期间,当工程正在稳定条件下运行时,承包商应通知雇主,告知工程已可以做任何其他竣工试验,包括各种性能试验,以证明工程是否符合雇主要求中规定地标准和履约保证.

Trial operation shall not constitute a taking-over under Clause 10 [Employer’s Taking Over]. Unless otherwise stated in the Particular Conditions, any product produced by the Works during trial operation shall be the property of the Employer.

试运行不应构成第10条[雇主的接收]规定的接收.除非专用条件中另有说明,工程在试运行期间生产的任何产品应属于雇主的财产.

In considering the results of the Tests on Completion, appropriate allowances shall be made for the effect of any use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the Works, or a Section, have passed each of the Tests on Completion described in sub-paragraph (a), (b) or (c), the Contractor shall submit a certified report of the results of these Tests to the Employer.

在考虑竣工试验结果时,雇主应适当考虑到因雇主对工程的任何使用,对工程的性能或其他特性产生的影响.一旦工程或某分项工程通过了本款(a)、(b)或(c)项中的每项竣工试验,承包商应向雇主提供一份经证实的这些试验结果的报告.

9.2 Delayed Tests延误的试验

If the Tests on Completion are being unduly delayed by the Employer, Sub-Clause 7.4 [Testing] (fifth paragraph) and/or Sub-Clause 10.3 [Interference with Tests on Completion] shall be applicable.

If the Tests on Completion are being unduly delayed by the Contractor, the Employer may by notice require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Employer.

如果雇主不当地延误竣工试验,雇主可通知承包商,要求在接到通知后21天内进行竣工试验.承包商应在上述期限内的某日或某几日内进行竣工试验,并将该日期通知雇主.

If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer’s Personnel may proceed with the Tests at the risk and cost of the Contractor. These Tests on Completion shall then be deemed to have been carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate.

如果承包商未在规定的21天内进行竣工试验,雇主人员可自行进行这些试验.试验的风险和费用应由承包商承担.这些竣工试验应被视为是承包商在场时进行的,试验结果应认为准确,予以认可.

9.3 Retesting重新试验

If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 7.5 [Rejection] shall apply, and the Employer or the Contractor may require the failed Tests, and Tests on Completion on any related work, to be repeated under the same terms and conditions.

如果工程或分项工程未能通过竣工试验,应适用第7.5款[拒收]的规定,雇主或承包商可要求按相同的条款和条件,重新进行此项未通过的试验和相关工程的竣工试验.

9.4 Failure to Pass Tests on Completion未能通过竣工试验

If the Works, or a Section, fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting], the Employer shall be entitled to:

(a) order further repetition of Tests on Completion under Sub-Clause 9.3;

(b) if the failure deprives the Employer of substantially the whole benefit of the Works or Section, reject the Works or Section (as the case may be), in which event the Employer shall have the same remedies as are provided in sub-paragraph (c) of Sub-Clause 11.4 [Failure to Remedy Defects]; or

(c) issue a Taking-Over Certificate.

如果工程或某分项工程未能通过根据第9.3款[重新试验]的规定重新进行的竣工试验,雇主应有权:

下令根据第9.3款再次重复竣工试验;

如果此项试验未通过,使雇主实质上丧失了工程或分项工程的整个利益时,拒收工程或分项工程(视情况而定),在此情况下,雇主应采取与第11.4款[未能修补缺陷](c)项规定的相同不久措施;或颁发接受证书.

In the event of sub-paragraph (c), the Contractor shall proceed in accordance with all other obligations under the Contract, and the Contract Price shall be reduced by such amount as shall be appropriate to cover the reduced value to the Employer as a result of this failure. Unless the relevant reduction for this failure is stated (or its method of calculation is defined) in the Contract, the Employer may require the reduction to be (ⅰ) agreed by both Parties (in full satisfaction of this failure only) and paid before this Taking-Over Certificate is issued, or (ⅱ) determined and paid under Sub-Clause 2.5 [Employer’s Claims] and Sub-Clause 3.5 [Determinations].

在采用( c )项办法的情况下,承包商应继续履行合同规定的所有其他义务.但合同价格应予降低,减少的金额应足以弥补此项试验未通过的后果给雇主带来的价值损失.除非对此项试验未通过相应减少的合同价格在合同中另有说明(或规定了计算方法),雇主可以要求该减少额(ⅰ)经双方商定(仅限于满足此项试验未通过的要求),并在此项接收证书颁发前支付,或(ⅱ)根据第2.5款[雇主的索赔]和第3.5款[确定]的规定,确定并支付.

10Employer’s Taking Over雇主的接收

10.1 Taking Over of the Works and Sections工程和分项工程的接收

Except as stated in Sub-Clause 9.4 [Failure to Pass Tests on Completion], the Works shall be taken

over by the Employer when (ⅰ) the Works have been completed in accordance with the Contract, including the matters described in Sub-Clause 8.2 [Time for Completion] and except as allowed in sub-paragraph (a) below, and (ⅱ) a Taking-Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub-Clause.

除第9.4款[未能通过竣工试验]中所述情况外,当(ⅰ)除下面(a)项允许的情况以外,工程已按合同规定包括第8.2款[竣工时间]中提出的事项竣工,(ⅱ)已按照本款规定颁发工程接收证书,或认为已经颁发时,雇主应接收工程.

The Contractor may apply by notice to the Employer for a Taking-Over Certificate not earlier than 14 days before the Works will, in the Contractor’s opinion, be complete and ready for taking over. If the Works are divided into Sections, the Contractor may similarly apply for a Taking-Over Certificate for each Section.

承包商可在他认为工程将竣工并做好接收准备的日期前不少于14天,向雇主发出申请接收证书的通知.若工程分成若干个分项工程,承包商可类似地为每个分项工程申请接收证书.

The Employer shall, within 28 days after receiving the Contractor’s application:

(a) issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or section were completed in accordance with the Contract, except for any minor outstanding work and defects which will not substantially affect the use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied); or

(b) reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work before issuing a further notice under this Sub-Clause.

雇主在收到承包商申请通知后28天内,应:

向承包商颁发接受证书,注明工程或分项工程按照合同要求竣工的日期, 任何对工程或分项工程预期使用目的没有实质影响的少量收尾工作和缺陷(直到或当收尾工作和缺陷修补完成时)除外;或

拒绝申请,说明理由,并指出在能颁发接收证书前承包商需做工作.承包商应在再次根据本款发出申请通知前,完成此项工作.

If the Employer fails either to issue the Taking-Over Certificate or to reject the Contractor’s application within the period of 28 days, and if the Works or Section (as the case may be) are substantially in accordance with the Contract, the Taking-Over Certificate shall be deemed to have been issued on the last day of that period.

如果雇主在28天期限内既未颁发接收证书,又未拒绝承包商的申请,而工程或分项工程(视具体情况而定)实质上符合合同规定,接收证书应视为已在上述规定期限的最后一日颁发.

10.2 Taking Over of Parts of the Works部分工程的接收

Parts of the Works (other than Sections) shall not be taken over or used by the Employer, except as may be stated in the Contract or as may be agreed by both Parties.

除合同中可能说明或可能经双方同意以外,任何部分工程(分项工程以外),雇主均不得接收或使用.

10.3 Interference with Tests on Completion对竣工试验的干扰

If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Contractor shall carry out the Tests on Completion as soon as practicable.

如果由雇主应负责的原因妨碍承包商进行竣工试验达14天以上,承包商应尽快地进行竣工试验.

If the Contractor suffers delay and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.

如果由于进行竣工试验的此项拖延,使承包商遭受延误和(或)招致增加费用,承包商应向雇主发出通知,有权根据第20.1款[承包商的索赔]的规定提出:

根据第8.4款[竣工时间的延长]的规定,如果竣工已或将受到延误,对任何此类延误给予延长期;

对任何此类费用,加合理的利润,应加入合同价格,给予支付.

After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

雇主受到此通知后,应按照第3.5款[确定]的规定,对这些事项进行商定或确定.

FIDIC合同(银皮书中文版)

目录 1 一般规定 (1) 1.1定义 (1) 1.2解释 (4) 1.3通信交流 (5) 1.4法律和语言 (5) 1.5文件优先次序 (5) 1.6合同协议书 (5) 1.7权益转让 (6) 1.8文件的照管和提供 (6) 1.9保密性 (6) 1.10雇主使用承包商文件 (6) 1.11承包商使用雇主文件 (7) 1.12保密事项 (7) 1.13遵守法律 (7) 1.14共同的和各自的责任 (7) 2雇主. (8) 2.1现场进入权 (8) 2.2许可、执照或批准 (8) 2.3雇主人员 (9) 2.4雇主的资金安排 (9) 2.5雇主的索赔 (9) 3雇主的管理 (9) 3.1雇主代表 (9) 3.2其他雇主人员 (10) 3.3受托人员 (10) 3.4指示 (10) 3.5确定 (11) 4承包商 (11) 4.1承包商的一般义务 (11) 4.2履约担保 (11) 4.3承包商代表 (12) 4.4分包商 (13) 4.5指定的分包商 (13) 4.6合作 (13) 4.7放线 (14) 4.8安全程序 (14) 4.9质量保证 (14) 4.10现场数据 (14) 4.11合同价格 (15)

4.13道路通行权于设施 (15) 4.14避免干扰 (15) 4.15进场通路 (15) 4.16货物运输 (16) 4.17承包商设备 (16) 4.18环境保护 (16) 4.19电、水和燃气 (16) 4.20雇主设备和免费供应的材料 (17) 4.21进度报告 (17) 4.22现场保安 (18) 4.23承包商的现场作业 (18) 4.24化石 (19) 5设计 (19) 5.1设计义务一般要求 (19) 5.2承包商文件 (20) 5.3承包商的承诺 (20) 5.4技术标准和法规 (21) 5.5培训 (21) 5.6竣工文件 (21) 5.7操作和维修手册 (21) 5.8设计错误 (22) 6员工 (22) 6.1员工的雇用 (22) 6.2工资标准和劳动条件 (22) 6.3为雇主服务的人员 (22) 6.4劳动法 (22) 6.5工作时间 (22) 6.6为员工提供设施 (23) 6.7健康和安全 (23) 6.8承包商的监督 (23) 6.9承包商人员 (23) 6.10承包商人员和设备的记录 (24) 6.11无序行为 (24) 7生产设备、材料和工艺 (24) 7.1实施方法 (24) 7.2样品 (24) 7.3检验 (24) 7.4试验 (25) 7.5拒收 (26) 7.6修补工作 (26) 7.7生产设备和材料的所有权 (26)

fidic合同条件体系及应用讲解学习

FIDIC合同条件体系及应用 FIDIC合同条件体系及应用 一、FIDIC合同主要文件构成 FIDIC专业委员会编制了一系列规范性合同条件,构成了FIDIC合同条件体系,包括: (红皮书) FIDIC土木工程施工合同条件 Conditions of Contract for Work Of Civil Engineering Construction (新红皮书) FIDIC程施工合同条件(1999年新增) Condition of Contract for Construction 注:《施工合同条件》(新红皮书)的全称是:由业主设计的房屋和工程施工合同条件(Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer); (黄皮书) FIDIC电气与机械工程合同条件 Conditions of Contract for Electrical and Mechanical Works (新黄皮书) FIDIC永久设备和设计—建造合同条件(1999年新增) Conditions of Contract for Plant and Design—Build

注:《设备与设计-建造合同》(新黄皮书)的全称是:由承包商设计的电气和机械设备安装与民用和工程合同条件(Conditions of Contract for Plant and Designed-Build for Electrlcal and Mechanical Plant and Building and Engineering Works Designed by the Contractor)。 (橘皮书)FIDIC设计-建造与交钥匙工程合同条件 Conditions of Contract for Design— Build and Turnkey (银皮书)FIDIC设计采购施工(EPC)/交钥匙工程合同条件 Conditions of Contract for EPC Turnkey Projects (白皮书)FIDIC业主咨询工程师标准服务协议书条件(1998年第三版)Conditions of Contract for EPC/Turnkey Projects (绿皮书)合同的简短格式 Short Form of Contract 二、FIDIC主要合同文件的适用性 国际承包工程涉及到的FIDIC合同主要有四种: 常见的是土木工程施工方面的,正式名称为《土木工程施工合同条件》(Conditions of Contract for Works of Civil Engineering Construction),由于封皮是红色的,海外通常叫做“红皮书”; 还有黄色封皮的,是机电工程方面的,正式名称为《机电工程合同条件》(Conditions of Contract for Electrical and Mechanical Works),常叫“黄皮书”;

FIDIC设计采购施工EPC合同条件银皮书中文版

. 目录 1 一般规定 (1) 1 ....................................................................... 1.1定义 3 ....................................................................... 1.2解释 3 ................................................................... 1.3通信交流 4 ................................................................. 1.4法律和语言 4 ............................................................... 1.5文件优先次序 4 ................................................................. 1.6合同协议书 4 ................................................................... 1.7权益转让 4 ........................................................... 1.8文件的照管和提供 4 ..................................................................... 1.9保密性 4........................................................ 雇主使用承包商文件1.10 5........................................................ 1.11承包商使用雇主文件5.................................................................. 1.12保密事项5.................................................................. 1.13遵守法律5........................................................ 1.14共同的和各自的责任 2雇主. (5) 5................................................................. 现场进入权 2.1 6........................................................... 许可、执照或批准 2.2 6................................................................... 雇主人员 2.3 6............................................................. 雇主的资金安排 2.4 6................................................................. 雇主的索赔 2.53雇主的管理 .. (7) 7 ................................................................... 3.1雇主代表 7 ............................................................... 3.2其他雇主人员 7 ................................................................... 3.3受托人员 7 ....................................................................... 3.4指示 8....................................................................... 确定3.5 4承包商 ............................................................ 8 8........................................................... 4.1承包商的一般义务 8................................................................... 履约担保 4.2 9................................................................. 承包商代表 4.3 9..................................................................... 分包商 4.4 9 ............................................................... 4.5指定的分包商 9 ....................................................................... 4.6合作 10...................................................................... 放线4.7 10.................................................................. 4.8安全程序

FIDIC合同条款-设计采购施工(EPC)交钥匙工程合同条件(银皮书)

FIDIC设计-建造与交钥匙工程合同条件 (银皮书) 目录 设计-建造与交钥匙工程合同条件(第一部分通用条件)(1-3) (2) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(4) (10) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(5-7) (18) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(8-11) (25) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(12-13) (33) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(14-17) (42) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(18-20) (50) 第二部分附注 (59)

设计-建造与交钥匙工程合同条件(第一部分通用条件)(1-3) 1.合同 定义 1.1在合同(如下文所定义的)中,下文定义的措词和用语,除上下文另有 要求外,应具有本款赋予的含义: 1.1.1文件 1.1.1.1“合同”指本合同条件(第一与第二部分)、雇主的要求、 投标书、承包商的建议书、资料表、中标函、合同协议书(如已签订)以及其他明确列入中标函或合同协议书(如已签订)中的此类进一步的文件。 1.1.1.2“雇主的要求”指合同中包括的对工作范围、标准、设计 准则(如有时)和进度计划的说明,以及根据合同对其所作的任何变更和修正。 1.1.1.3“标书”指承包商为了工程间雇主提出并为中标函接受的 报价书。 1.1.1.4“投标书附录”指包括在投标书中已填写完的附录。 1.1.1.5“承包商的建议书”指包含在合同中、随投标书一同递交 的初步设计。 1.1.1.6“资料表”指包含在合同中、与投标书一同递交的信息与 数据。 1.1.1.7“支付计划表”指第1.4款中所指的计划表(如有时)。 1.1.1.8“中标函”指雇主对投标书的正式接受函。 1.1.1.9“合同协议书”指第 1.5款中所述的合同协议书(如有 时)。 1.1.2人员 1.1. 2.1“雇主”指投标书附录中指定的当事人以及取得此当事人 资格的合法继承人,但不指(除非承包商同意)此当事人的任何受让人。 1.1. 2.2“承包商”指其投标书已为雇主接受的当事人以及取得此 当事人资格的合法继承人,但不指(除非雇主同意)此当事人的任何受让人。

FIDIC--设计采购施工(EPC)合同条件--银皮书(中文版,1999第一版)

目录 1一般规定 (6) 1.1定义 (6) 1.1.4款项与付款 (9) 1.1.5工程和货物 (9) 1.1.6其他定义 (10) 1.2解释 (11) 1.3通信交流 (11) 1.4法律和语言 (11) 1.5文件优先次序 (12) 1.6合同协议书 (12) 1.7权益转让 (12) 1.8文件的照管和提供 (12) 1.9保密性 (13) 1.10雇主使用承包商文件 (13) 1.11承包商使用雇主文件 (14) 1.12保密事项 (14) 1.13遵守法律 (14) 1.14共同的和各自的责任 (15) 2雇主 (16) 2.1现场进入权 (16) 2.2许可、执照或批准 (16) 2.3雇主人员 (17) 2.4雇主的资金安排 (17) 2.5雇主的索赔 (17) 3雇主的管理 (19) 3.1雇主代表 (19) 3.2其他雇主人员 (19) 3.3受托人员 (19) 3.4指示 (20) 3.5确定 (20) 4承包商 (21) 4.1承包商的一般义务 (21) 4.2履约担保 (21) 4.3承包商代表 (22) 4.4分包商 (23) 4.5指定的分包商 (23) 4.6合作 (24) 4.7放线 (24) 4.8安全程序 (25) 4.9质量保证 (25) 4.10现场数据 (25) 4.11合同价格 (26)

4.16货物运输 (27) 4.17承包商设备 (28) 4.18环境保护 (28) 4.19电、水和燃气 (28) 4.20雇主设备和免费供应的材料 (29) 4.21进度报告 (29) 4.22现场保安 (30) 4.23承包商的现场作业 (31) 4.24化石 (31) 5设计 (33) 5.1设计义务一般要求 (33) 5.2承包商文件 (33) 5.3承包商的承诺 (34) 5.4技术标准和法规 (35) 5.5培训 (35) 5.6竣工文件 (35) 5.7操作和维修手册 (36) 5.8设计错误 (36) 6员工 (37) 6.1员工的雇用 (37) 6.2工资标准和劳动条件 (37) 6.3为雇主服务的人员 (37) 6.4劳动法 (37) 6.5工作时间 (37) 6.6为员工提供设施 (38) 6.7健康和安全 (38) 6.8承包商的监督 (38) 6.9承包商人员 (39) 6.10承包商人员和设备的记录 (39) 6.11无序行为 (39) 7生产设备、材料和工艺 (41) 7.1实施方法 (41) 7.2样品 (41) 7.3检验 (41) 7.4试验 (42) 7.5拒收 (43) 7.6修补工作 (43) 7.7生产设备和材料的所有权 (44) 7.8土地(矿区)使用费 (44) 8开工、延误和暂停 (45) 8.1工程的开工 (45) 8.2竣工时间 (45) 8.3进度计划 (45) 8.4竣工时间延长 (46) 8.5当局造成的延误 (47)

银皮书中文版FIDIC设计采购施工EC合同条

目录 1 一般规定 (6) 1.1定义 (6) 1.2解释 (11) 1.3通信交流 (12) 1.4法律和语言 (12) 1.5文件优先次序 (12) 1.6合同协议书 (13) 1.7权益转让 (13) 1.8文件的照管和提供 (14) 1.9保密性 (14) 1.10雇主使用承包商文件 (14) 1.11承包商使用雇主文件 (15) 1.12保密事项 (16) 1.13遵守法律 (16) 1.14共同的和各自的责任 (16) 2雇主. (16) 2.1现场进入权 (16) 2.2许可、执照或批准 (18) 2.3雇主人员 (18) 2.4雇主的资金安排 (18) 2.5雇主的索赔 (18) 3雇主的管理 (20) 3.1雇主代表 (20) 3.2其他雇主人员 (20) 3.3受托人员 (20) 3.4指示 (20) 3.5确定 (22) 4承包商 (22) 4.1承包商的一般义务 (22) 4.2履约担保 (22) 4.3承包商代表 (24) 4.4分包商 (24) 4.5指定的分包商 (24) 4.6合作 (25) 4.7放线 (26) 4.8安全程序 (26) 4.9质量保证 (26) 4.10现场数据 (27) 4.11合同价格 (28) 4.12不可预见的困难 (28)

4.13道路通行权于设施 (28) 4.14避免干扰 (28) 4.15进场通路 (28) 4.16货物运输 (30) 4.17承包商设备 (30) 4.18环境保护 (30) 4.19电、水和燃气 (30) 4.20雇主设备和免费供应的材料 (31) 4.21进度报告 (32) 4.22现场保安 (33) 4.23承包商的现场作业 (34) 4.24化石 (34) 5设计 (34) 5.1设计义务一般要求 (34) 5.2承包商文件 (36) 5.3承包商的承诺 (36) 5.4技术标准和法规 (37) 5.5培训 (38) 5.6竣工文件 (38) 5.7操作和维修手册 (38) 5.8设计错误 (38) 6员工 (39) 6.1员工的雇用 (39) 6.2工资标准和劳动条件 (40) 6.3为雇主服务的人员 (40) 6.4劳动法 (40) 6.5工作时间 (40) 6.6为员工提供设施 (40) 6.7健康和安全 (40) 6.8承包商的监督 (42) 6.9承包商人员 (42) 6.10承包商人员和设备的记录 (42) 6.11无序行为 (42) 7生产设备、材料和工艺 (42) 7.1实施方法 (42) 7.2样品 (44) 7.3检验 (44) 7.4试验 (44) 7.5拒收 (46) 7.6修补工作 (46) 7.7生产设备和材料的所有权 (46) 7.8土地(矿区)使用费 (46)

新版《菲迪克(FIDIC)合同条件和指南》及其权威解释

新版《菲迪克(FIDIC)合同条件和指南》及其权威解释 素有工程合同“圣经”之称的菲迪克条款,继2002年在机械工业出版社出版了4本最新版《菲迪克(FIDIC)合同条件》中英文对照本后,众望已久的新版《菲迪克(FIDIC)合同指南》中英文对照本也于今年6月正式出版。至此菲迪克整套新版合同范本和应用指南中译本已全部出齐。这是我国投资建设领域人们关心的一件大事。它将推动我国工程项目管理迈向国际标准,走上新的台阶。 新版《菲迪克(FIDIC)合同条件》具有以下突出特点: 一、继承几十年经验,全面改进。 菲迪克作为国际工程咨询业权威性组织,其制订的《土木工程施工合同条件》(红皮书)和《电气与机械工程合同条件》(黄皮书)等在国际通行已半个世纪。这次新版认真吸取了过去的经验,加入新的理念,做了彻底改写。更好地适应可持续发展和协调保护业主,承包商及社会公众各方利益的需要。菲迪克认为,这次改版,不是原来几本合同条件的修订版,而是全新版本,所以称为1999年第一版。 二、几种合同范本体现不同的工程承包和项目管理模式。 改变过去以工程类型冠名,按适用的工程类型划分合同条件的旧模式。采用按不同的工程承包和项目管理模式划分合同条件。如: 1、《施工合同条件》(新红皮书),适用于业主提供设计;承包商负责设备材料采购和施工,咨询工程师监理,按图纸估价,按实结算,不可预见条件和物价变动允许调价。是一种业主参与和控制较多,承担风险也较多的合同格式。 2、《生产设备和设计-施工合同条件》(新黄皮书),适用于承包商负责设备采购、设计和施工,咨询工程师监理,总额价格承包,但不可预见条件和物价变动可以调价,是一种业主控制较多的总承包合同格式。

FIDIC合同文本介绍及合同条件适用

FIDIC合同文本介绍及合同条件适用 为了保证交易的顺利进行,多数国家或地区政府、社会团体和国际组织都制定了有标准的招招标程序、合同文件、工程量计算规则和仲载方式告示。使用这些标准的招投标程序、合同文件,便于投标人熟悉合同条款,减少编制投标文件时所考虑的潜在风险,以降低报价。发生争议的时候,可以执行合同文件所附带的争议解决条款来处理纠纷。标准的合同条件能够合理公平的在合同双方之间分配风险和责任,明确规定了双方的权利、义务,很大程度上避免了因不认真履行合同造成的额外费用支出和相关争议。 FIDIC作为国际上权威的咨询工程师机构,多年来所编写的标准合同条件是国际工程界几十年来实践经验的总结,公正的规定了合同各方的职责、权利和义务,程序严谨,可操作性强。如今已在工程建设、机械和电气设备的提供等方面被广泛使用。现简要介绍FIDIC 合同条件的发展过程和新版(99版)合同条件的适用范围等情况。 一、FIDIC合同文件的发展 1957年,FIDIC与国际房屋建筑和公共工程联合会[现在的欧洲国际建筑联合会(FIEC)]在英国咨询工程师联合会(ACE)颁布的《土木工程合同文件格式》的基础上出版了《土木工程施工合同条件(国际)》(第1版)(俗称“红皮书”),常称为FIDIC条件。该条件分为两部分,第一部分是通用合同条件,第二部分为专用合同条件。 1963年,首次出版了适用于业主和承包商的机械与设备供应和安装的《电气与机械工程标准合同条件格式》即黄皮书。 1969年,红皮书出版了第二版。这版增加了第三部分,疏浚和填筑工程专用条件。 1977年,FIDIC和欧洲国际建筑联合会(FIEC)联合编写 Federation Internationale Europeenne de la Construction(巴黎),这是红皮书和第三版。 1980年,黄皮书出了第二版。 1987年9月红皮书出版了第四版。将第二部分(专用合同条件)扩大了,单独成册出版,但其条款编号与第一部分一一对应,使两部分合在一起共同构成确定合同双方权利和义务的合同条件。第二部分必须根据合同的具体情况起草。为了方便第二部分的编写,其编有解释性说明以及条款的例子,为合同双方提供了必要且可供选择了条文。(1988年,做了若干编辑方面的修改之后,红皮书再次重印。这些修改不影响有关条款的涵义,只是澄

FIDIC合同文本介绍

FIDIC合同文本介绍 为了保证交易的顺利进行,多数国家或地区政府、社会团体和国际组织都制定了有标准的招标程序、合同文件、工程量计算规则和仲载方式。使用这些标准的招投标程序、合同文件,便于投标人熟悉合同条款,减少编制投标文件时所考虑的潜在风险,以降低报价。发生争议的时候,可以执行合同文件所附带的争议解决条款来处理纠纷。标准的合同条件能够合理公平的在合同双方之间分配风险和责任,明确规定了双方的权利、义务,很大程度上避免了因不认真履行合同造成的额外费用支出和相关争议。 FIDIC作为国际上权威的咨询工程师机构,多年来所编写的标准合同条件是国际工程界几十年来实践经验的总结,公正的规定了合同各方的职责、权利和义务,程序严谨,可操作性强。如今已在工程建设、机械和电气设备的提供等方面被广泛使用。现简要介绍FIDIC合同 条件的发展过程和新版(99版)合同条件的适用范围等情况。 一、FIDIC合同文件的发展 1957年,FIDIC与国际房屋建筑和公共工程联合会[现在的欧洲国际建筑联合会(FIEC)]在英国咨询工程师联合会(ACE)颁布的〈〈土木工程合同文件格式》的基础上出版了〈〈土木工程施工合同条件(国际)》(第1版)(俗称“红皮书”),常称为FIDIC条件。该条件分为两部分,第一部分

是通用合同条件,第二部分为专用合同条件。1963 年,首次出版了适用于业主和承包商的机械与设备供应和安装的〈〈电气与机械工程标准合同条件格式》即黄皮书。 1969年,红皮书出版了第二版。这版增加了第三部分,疏浚和填筑工程专用条件。 1977 年,FIDIC 和欧洲国际建筑联合会(FIEC )联合编写Federation Internationale Europeenne de la Construction(巴黎),这是红皮书和第三版。 1980年,黄皮书出了第二版。 1987年9月红皮书出版了第四版。将第二部分(专用合同条件)扩大了,单独成册出版,但其条款编号与第一部分一一对应,使两部分合在一起共同构成确定合同双方权利和义务的合同条件。第二部分必 须根据合同的具体情况起草。为了方便第二部分的编写,其编有解释性说明以及条款的例子,为合同双方提供了必要且可供选择了条文。 (1988年,做了若干编辑方面的修改之后,红皮书再次重印。这些修改不影响有关条款的涵义,只是澄清了其真正意图。)

FIDIC--设计采购施工(EPC)合同条件--银皮书(中文版,1999第一版)

目录1 一般规定 6 1.1 定义 6 1.1.4 款项与付款 8 1.1.5 工程和货物 8 1.1.6 其他定义 9 1.2 解释 9 1.3 通信交流 10 1.4 法律和语言 10 1.5 文件优先次序 10 1.6 合同协议书 11 1.7 权益转让 11 1.8 文件的照管和提供 11 1.9 保密性 11 1.10 雇主使用承包商文件 11 1.11 承包商使用雇主文件 12 1.12 保密事项 12

1.13 遵守法律 12 1.14 共同的和各自的责任 12 2 雇主 14 2.1 现场进入权 14 2.2 许可、执照或批准 14 2.3 雇主人员 15 2.4 雇主的资金安排 15 2.5 雇主的索赔 15 3 雇主的管理 16 3.1 雇主代表 16 3.2 其他雇主人员 16 3.3 受托人员 16 3.4 指示 17 3.5 确定 17 4 承包商 18 4.1 承包商的一般义务 18 4.2 履约担保 18

4.3 承包商代表 19 4.4 分包商 19 4.5 指定的分包商 20 4.6 合作 20 4.7 放线 20 4.8 安全程序 21 4.9 质量保证 21 4.10 现场数据 21 4.11 合同价格 21 4.12 不可预见的困难 22 4.13 道路通行权于设施 22 4.14 避免干扰 22 4.15 进场通路 22 4.16 货物运输 23 4.17 承包商设备 23 4.18 环境保护 23 4.19 电、水和燃气 23

4.20 雇主设备和免费供应的材料 24 4.21 进度报告 24 4.22 现场保安 25 4.23 承包商的现场作业 25 4.24 化石 26 5 设计 27 5.1 设计义务一般要求 27 5.2 承包商文件 27 5.3 承包商的承诺 28 5.4 技术标准和法规 28 5.5 培训 29 5.6 竣工文件 29 5.7 操作和维修手册 29 5.8 设计错误 29 6 员工 30 6.1 员工的雇用 30 6.2 工资标准和劳动条件 30

FIDIC设计采购施工(EPC)合同条件(银皮书英文版)

CONTENTS 1 GENERAL PROVISIONS (1) 1.1D EFINITIONS (1) 1.2I NTERPRETATION (6) 1.3C OMMUNICATIONS (6) 1.4L AW AND L ANGUAGE (7) 1.5P RIORITY OF D OCUMENTS (7) 1.6C ONTRACT A GREEMENT (8) 1.7A SSIGNMENT (8) 1.8C ARE AND S UPPLY OF D OCUMENTS (8) 1.9C ONFIDENTIALITY (8) 1.10E MPLOYER’S U SE OF C ONTRACTOR’S D OCUMENTS (9) 1.11C ONTRACTOR’S U SE OF E MPLOYER’S D OCUMENTS (9) 1.12C ONFIDENTIAL D ETAILS (10) 1.13C OMPLIANCE WITH L AWS (10) 1.14J OINT AND S EVERAL L IABILITY (10) 2 THE EMPLOYER (11) 2.1R IGHT OF A CCESS TO THE S ITE (11) 2.2P ERMITS,L ICENCES OR A PPROVES (11) 2.3E MPLOYER’S PERSONNEL (12) 2.4E MPLOYER’S F INANCIAL A RRANGEMENTS (12) 2.5E MPLOYER’S C LAIMS (12) 3 THE EMPLOYER’S ADMINISTRATION (13) 3.1T HE E MPLOYER’S R EPRESENTATIVE (13) 3.2T HE E MPLOYER’S PERSONNEL (14) 3.3D ELEGATED P ERSONS (14) 3.4I NSTRUCTIONS (15) 3.5D ETERMINATIONS (15) 4 THE CONTRACTOR (15) 4.1T HE C ONTRACTOR’S G ENERAL O BLIGATIONS (15) 4.2P ERFORMANCE SECURITY (16)

FIDIC 设计采购施工合同条件(银皮书 第1-4.5条中英文)

FIDIC 设计采购施工合同条件(银皮书第7-10条中英文) FIDIC CONTRACT OF DESIGN, PURCHASE AND CONSTRUCTION (EPC)交钥匙项目合同条件 7 Plant, Materials and Workmanshi生产设备、材料和工艺 7.1 Manner of Execution实施方法 The Contractor shall carry out the manufacture of Plant, the production and manufacture of Materials, and all other execution of the Works: (a) in the manner (if any) specified in the Contract, (b) in a proper workmanlike and careful manner, in accordance with recognized good practice, and (c) with properly equipped facilities and non-hazardous Materials, except as otherwise specified in the Contract. 承包商应按以下方法进行生产设备的制造、材料的生产加工、以及工程的所有其他实施作业: 按照合同规定的方法(如果有); 按照公认的良好惯例,使用恰当、精巧、仔细的方法; 除合同另有规定外,使用适当配备的设施和无危险的材料. 7.2 Samples样品 The Contractor shall submit samples to the Employer, for review in accordance with the procedures for Contractor’s Documents des cribed in Sub-Clause 5.2 [Contractor’s Documents], as specified in the Contract and at the Contractor’s cost. Each sample shall be labelled as to origin and intended use in the Works. 承包商应根据合同规定,按照第5.2款[承包商文件]中所述的对承包商文件的送审程序,自费向雇主提交样品,供其审核.每件样品应标明其原产地、及其在工程中预期的用处. 7.3 Inspection检验 The Employer’s Personnel shall at all reasonable times: (a) have full access to all parts of the Site and to all places from which natural Materials are being obtained, and (b) during production, manufacture and construction (at the Site and, to the extent specified in the Contract, elsewhere), be entitled to examine, inspect, measure and test the materials and workmanship, and to check the progress of manufacture of Plant and production and

监理工程师:FIDIC合同文本介绍(三)

监理工程师:FIDIC合同文本介绍(三) 3.《EPC/交钥匙项目合同条件》(银皮书) 适用范围:《EPC/交钥匙项目合同条件》是一种现代新型的建设履行方式。该合同范本适用于建设项目规模大、复杂程度高、承包商提供设计、承包商承担绝大部分风险的情况。与其它三个合同范本的区别在于,在《EPC/交钥匙项目合同条件》下业主只承担工程项目的很小风险,而将绝大部分风险转移给承包商。这是由于作为这些项目(特别是私人投资的商业项目)投资方的业主在投资前关心的是工程的最终价格和最终工期,以便他们能够准确的预测在该项目上投资的经济可行性。所以,他们希望少承担项目实施过程中的风险,以避免追加费用和延长工期。因此,当业主希望: (1)承包商承担全部设计责任,合同价格的高度确定性,以及时间不允许逾期; (2)不卷入每天的项目工作中去; (3)多支付承包商建造费用,但作为条件承包商须承担额外的工程总价及工期的风险; (4)项目的管理严格采纳双方当事人的方式,如无工程师的介入,那么,《EPC/交钥匙项目合同范本》(银皮书)正是所需。另外,使用EPC合同的项目的招标阶段给予承包商充分的时间和资料使其全面了解业主的要求并进行前期规划、风险评估的估价;业主也不得过度干预承包商的工作;业主的付款方式应按照合同支付,而无须象新红皮书和新黄皮书里规定的工程师核查工程量并签认支付证书后才付款。考试大监理工程师 《EPC/交钥匙项目合同条件》特别适宜于下列项目类型: (1)民间主动融资PFI(Private Finance Initiate),或公共/民间伙伴PPP (Public/Private Partnership),或BOT(Built Operate Transfer)及其它特许经营合同的项目; (2)发电厂或工厂且业主期望以固定价格的交钥匙方式来履行项目; (3)基础设计项目(如公路、铁路、桥、水或污水处理石、水坝等)或类似项目,业主提供资金并希望以固定价格的交钥匙方式来履行项目; (4)民用项目且业主希望采纳固定价格的交钥匙方式来履行项目,通常项目的完成包括所有家具、调试和设备。

fidic合同银皮书

fidic合同银皮书 篇一:FIDIC设计采购施工(EPC)合同条件(银皮书中文版) 目录 1 一般规定 ................................................ ................................................... . (1) 定义 ................................................ ................................................... (1) 解释 ................................................ ................................................... (4) 通信交流 ................................................ ................................................... . (5) 法律和语言 ................................................

................................................... (5) 文件优先次序 ................................................ ................................................... .. (5) 合同协议书 ................................................ ................................................... (5) 权益转让 ................................................ ................................................... . (6) 文件的照管和提供 ................................................ ................................................... (6) 保密性 ................................................ ................................................... .. (6)

FIDIC设计采购施工(EPC)合同条件(银皮书英文版)

contents 1 General Provisions 1 1.1 Definitions 1 1.2 Interpretation 6 1.3 Communications 6 1.4 Law and Language 7 1.5 Priority of Documents 7 1.6 Contract Agreement 8 1.7 Assignment 8 1.8 Care and Supply of Documents 8 1.9 Confidentiality 8 1.10 Employer’s Use of Contractor’s Documents 9 1.11 Contractor’s Use of Employer’s Documents 9 1.12 Confidential Details 10 1.13 Compliance with Laws 10 1.14 Joint and Several Liability 10 2 The Employer 11

2.1 Right of Access to the Site 11 2.2 Permits, Licences or Approves 11 2.3 Employer’s personnel 12 2.4 Employer’s Financial Arrangements 12 2.5 Employer’s Claims 12 3 The Employer’s Administration 13 3.1 The Employer’s Represent ative 13 3.2 The Employer’s personnel 14 3.3 Delegated Persons 14 3.4 Instructions 15 3.5 Determinations 15 4 The Contractor 15 4.1 The Contractor’s General Obligations 15 4.2 Performance security 16 4.3 Contractor’s Represe ntative 17 4.4subContractors 18 4.5 Nominated Subcontractors 18