一、工程概况

1、工程名称:简蒲高速公路K214+250-K249+173景观绿化工程

2、监理内容:施工质量控制、进度控制、协助业主进行投资控制及安全文明施工管理

二、监理依据

1、监理委托合同及工程承包合同

2、施工图设计、变更设计图纸

3、《公路工程监理规范》(JTG G10-2006)

4、《行道树栽植技术规程》(DBJ08-54-96)

5、《大树移植技术规程》(DBJ08-53-96)

6、《草坪建植和草坪养护管理的技术规程》(DBJ08-67-97)

7、《建筑工程施工质量验收统一标准》(GB50300-2001)

8、《公路工程质量检验评定标准》(JTG F80/1-2004)

三、监理工作流程

监理工作程序

施工准备阶段监理工作程序

质量控制工作程序

隐蔽工程验收流程

施工测量放线监理查验程序 质保资料完整合格 隐蔽工程验收自检合

施工承包方

施工承包方填报 报验申请表 监理在报验申请表上

签认同意意见

施工承包方进行

下道工序施工

包 否 可

监理对隐蔽工程

及分项工程质量

进度控制工作程序

安全施工监管工作程序

签订承发包合同 编制施工总进度计

审查施工总进度计

编制年、季、月度实施

审查实施计划

组织实施进度计

检查计划实施情况

修改实施进度计实际值与计划值

同意

不同

同意

不同

有偏差

根据总进度控制计划,编制下期实施性进根据形象计划编写月

否交工监理工作程序

工程付款监理工作程序

申报否

报告

四、监理的职责和权限

1、监理职责

(1)督促施工单位编制施工组织设计和单位、分部、分项开工报告,并对其进行审核,提出审核意见后上报建设单位。

(2)对施工单位用于工程的各种原材料、成品、半成品进行质量认可,不符合规范要求的拒绝认可。

(3)督促施工单位按照设计文件、操作规程、已批准的施工组织设计和技术规范进行施工,跟踪检查施工质量,按验收标准逐项工序验收签证,并按要求进行监理抽检,控制质量,达到既定目标。

(4)根据业主下达的节点计划,协助业主审查督促施工单位上报的计划,运用动态管理的方法控制进度目标的实现。

(5)督促施工单位健全质量保证和管理体系,健全安全生产、文明施工制度,并经常检查、督促和落实。

(6)检查和督促施工单位及时、齐全、准确地完成内部资料编制和按规定做的各项试验。

(7)负责现场计量,核实工程数量,及时对工程完成数量进行审核,报甲方审批,签证竣工工程量。

(8)及时完成监理资料及抽检工作,做到真实、规范、正确。定期向业主提供监理月报,报告规程进度、质量和安全生产、文明施工的情况,以使业主制定有效的措施和决定。

(9)参与调查安全事故,督促施工单位及时写出安全事故调查报告。

(10)工程竣工后,及时提出工程质量评估报告,参加工程验收。

2、监理的权限

(1)有权要求施工单位在开工前提供单位、分部、分项开工报告和施工组织设计及相应的质量保证措施和进行质量控制所必要的其他资料,测量试验设备和施工机械设备。(2)有权检查施工单位的各项管理制度,并督促健全、完善质保体系,对施工单位技术资质和施工活动进行连续不断的审查和评价,发现不合格人员,有权要求承建单位及时换人。

(3)有权对用于工程的原材料和设备(仪器)进行监控,验收和复验不合格合格的原材料,未经检验的设备(仪器)等,监理有权终止其使用。

(4)工程不具备开工条件或上道工序未经自检和监理检验认可的,驻地监理工程师有权拒发开工通知(开工令)和发暂停其施工的指令。

(5)在下述情况下,驻地监理工程师有权下达暂停工令,并报请指挥部研究决策。

①施工出现异常情况,经提出后施工单位仍不采取措施或采取的改进措施不力,致使质量状况未见好转者。

②对发出质量事故未经处理或未提出有效补救措施而继续作业者。

③擅自变更设计图纸进行施工者。

④使用不合格材料或擅自变更、替换工程材料者。

⑤严重违反操作规程,经指出不及时纠正者。

⑥施工中存在重大质量、安全问题或有重大质量和安全隐患时。

(6)对验收不合格的工序,监理工程师有权拒绝验收,直至整改完成,监理工程师有权对不合格工作量拒绝签认。

五、监理程序

按以下三个阶段具体实施:

1、施工准备阶段

(1)审查施工单位提交的施工组织设计,对施工方案,质保措施,进度计划、安全、文明施工等提出意见,报指挥部批准,监理从项目整体角度进行协调和控制。

(2)审查承包单位提出的重要材料、成品、半成品、施工机械等计划及工程试验计划,提出具体要求,核实材料供方质保措施,对进场的原材料、成品、半成品进行质保检查。

(3)检查现场的测量标志,督促承包人对设计交付的水准点进行全面复测,并做好水准点加密工作。监理亦全频率进行复测。

(4)督促承包单位健全,完善管理网络质保体系等各项管理制度。

(5)向承包单位进行监理细则交底,以便互相了解情况,配合工作。

(6)审核开工报告,上报甲方批准。

2、施工实施阶段

(1)监理全过程跟踪检查,全面掌握、了解工序施工进度,方法和质量及安全、文明施工等情况。

(2)对进场材料、成品、半成品的试验和机具设备的使用进行检查。

(3)严格工序间交接检查,坚持上道工序未经检查验收,验收不合格或未采取纠正措施的,不允许转入下道工序施工。监理要对已完工程,按相应的质量评定标准进行检查验收。

(4)及时对合格工程量进行签认,作为工程计量支付的依据由监理工程师汇总整理后签发。若工程质量或内业资料不符合要求,此签证将不予认可。

(5)检查承包单位的试验频率是否正常进行。

(6)对承包单位的施工进度、计划的执行情况,及时提出建议反馈给指挥部和承包单位。

3、施工竣工阶段

(1)按规定的质量评定标准对完成的工程进行检查验收,并协助指挥部对部位工程和单位工程进行检查验收,质量评定。

(2)审核施工单位提供的质量检验报告和其他竣工资料,按有关规定进行归档。

六、绿化工程的质量监理

(一)土壤和水

.1、种植或播种前应对该地区的土壤理化性质进行化验分析,采取相应的消毒、施肥和客土等措施。

2、种植地的土壤含有其他有害成分,以及强酸性土、强碱土、盐土、盐碱土、重粘土、砂土等,均应根据设计规定,采用客土或采取改良土壤的技术措施。

3、种植或养护植物用水应无油、酸、碱、盐或其他对植物生长有害的物质,并应符合相关要求。

(二)铺设表土

承包人在表土施工前通知监理工程师,承包人做出取得表土的所有安排,提供有关良好表土的证明,并附一份挖取表土和恢复该地区的安排。覆盖表土范围的地表面通过挖松、加填或挖除以保持平整均匀。表土覆盖到要求深度后,其完成工程符合所要求的线形、坡度边坡和横断面。

准备工作经监理工程师同意后,应即铺设表土(一般松厚加5%预加沉降值),使之在沉降后,达到合同规定的或图上所示的大致厚度。当表土过分潮湿或处在对工作有害的条件时不应铺设。除另有规定外,表土完成标高应比路缘石、集水井、人行道、车行道或其它类似结构低25㎜,应用耙、犁或其它合适机具,将土块打碎使之形成均匀组织

土。不能打碎的土块,大于设计要求的石块、树根、树桩和其它垃圾应清除,并运往监理工程师同意的地点废弃。

(三)撒播草种

1、准备好地表面:

在播种前承包人应耕作到设计深度内消除硬土,绿地应按设计要求构筑地形;土地平整,排水坡度恰当,无积水。

2、播种方法:

承包人应事先将采用机具和播种方法报监理工程师审核,播种应在合同中规定的正常播种、施肥和覆盖的适宜时间或不规定日期时,应在当地生长季节进行播种、施肥和覆盖。

3、植物覆盖法:

植物覆盖包括撒布切碎的稻草、木屑或其它允许的材料,可以干撒也可以湿撒,可以与播种同时进行,也可以分别操作。植物覆盖应使覆盖物不移动。

(四)种植乔木、灌木和草皮:

1、基本要求

(1)灌木应根系发达,生长茁壮,无病害,规格及形态应符合设计要求。

(2)种植穴、槽的定点放线应符合设计要求。

(3)种植的植物材料的整形修剪应符合设计要求。

(4)苗木挖掘、包装应符合要求。

(5)裸根苗木宜当天种植。

2、种植季节:

应在各类植物的最适当季节及日期进行种植;草坪种植的适宜季节和草种类型选择应符合下列规定:

①冷季型草播种宜在秋季进行,也可在春、夏季进行。

②茎枝栽植暖季型草播种宜在夏季和多雨季节进行。

③植生带、铺砌草块或草卷,四季均可。

落叶类(幼芽出现前)应在早春种植,常青类比之晚一个月;土壤条件不适合种植时也不应种植。

3、提供植物、检查及运送:

承包人应在种植工作前,向监理工程师提供有关种植物供应来源的全部资料。草坪、地被植物的种子应注明品种、品系、产地、生产单位、采收年份、纯净度及发芽率,不得有病虫害。自外地引进种子应有检疫合格证。

运输前应有相当仔细和具有熟练技术的良好园艺人员负责将植物挖出,包扎打捆,任何时候,根系应保持潮湿、防冻、防过热。落叶树在裸根情况下运输时,必须将根部包涂粘土浆,使根的全部带有泥土,然后包装在稻草袋内。所有常青树及灌木的根部,均应形成土球并用草袋包装。种植前,这些土球应是坚实的,草色应完好,树冠应仔细捆扎以防止枝叉折断。

草皮、多年生植物以及其它植物应在合适的盆或容器内运输。

植物以单株或成捆、大包或容器装有一株或多株植物运到工地时,均应分别带有标明清楚的标签,应标明正规的园艺的名称、尺寸、年龄或其它详细资料。

4、储存和保护:

运到工地一天内种不完的植物,应防止过热或过冷,并存放在阴凉处以防日晒风吹。裸树根应将包打开,放在沟内,根部暂盖壅土,并保持湿润。带有土球及草袋包装的植物应用土、稻草或其它适当材料加以保护,并保持土、稻草等潮湿和湿润,以防根系干燥。

5、种植准备:

承包人应标出种植地段及种植位置的轮廓放样,并得到监理工程师的批准。种植地段应修整到图示的线形和坡度,并具有舒顺的外形。种植中所有不适宜回填的材料,均应由承包人自工地移走。

6、种植:

应由有经验的工人,按照公认的正常做法进行种植和回填土,各植物应近乎垂直地栽好,在种植后一定时间内应每天对乔木或灌木进行浇水。

在铺植地表的准备工作完成以后,即可铺植草皮,除平铺外,在边坡较陡之处也可由坡脚处向上钉铺,用小尖木桩或竹签钉固于边坡上,铺后即可喷灌浇水。

1

2

3

4、在施工过程中检查和监督计划的实施。当工程未能按计划进行时,应要求承包人调整或修改计划,并通知承包人采取必要的措施加快施工进度,以符合施工合同的要求。

5、定期向建设单位报告工程进度情况,当施工进度可能导致合同工期严重延误时,有责任提出中止执行施工合同的详细报告,供建设单位采取措施或做出相应的决定。

八、工程计量控制

1、认真审核施工图及合格工程的计量记录,以此作为计量的依据。

2、每月按时审查验工工作量,防止错报,审核后报甲方审批。

3、对工程变更先报驻地办,驻地监理提出审核意见后,报甲方批准,并以此作为计量和支付的依据。

九、安全、文明施工监理

1、协助做好临时设施的搭建工作,临时设施必须符合文明工地要求。

2、检查督促落实各施工单位安全、文明施工制度,帮助健全安全、文明施工网络,并督促施工单位按市有关安全、文明施工文件要求执行。

3、坚持“安全第一、预防为主、综合治理”的原则,督促施工单位做好安全交底工作。

4、协调施工单位对进入现场设备、机具进行安全检查,检查特殊工种操作证,杜绝违章操作现象。

5、做好安全用电督促工作,要求规范用电,杜绝乱拉线,乱接线的情况发生。

6、巡视现场时,发现隐患,督促有关人员限期解决,对违章指挥、违章作业,立即制止。

7、针对本工程施工特点,督促施工方做好护栏、警示牌架设及各项安全防护措施,确保交通安全。

8、施工现场必须做到挂牌施工和管理人员佩卡上岗,工地现场施工材料必须堆放整齐,工地生活设施必须清洁文明。

9、协助甲方和施工单位开展安全、文明施工检查,做好竞赛评比活动。争创文明工地。

十、旁站监理的重要部位、工序清单

1、旁站监理的职责

(1)检查施工企业现场质检人员到岗,特殊工种人员持证上岗以及施工机械、建筑材料准备情况。

(2)在现场监督关键部位、关键工序的施工方案执行和工程建设强制性标准执行情况。(3)检查现场建筑材料、建筑构配件、设备和商品混凝土的质量检验报告等,并可在现场监督施工企业进行检验或者委托具有资格的第三方进行复验。

(4)做好旁站记录和监理日记,保存旁站监理原始资料。

2、旁站监理的范围

(1)涉及结构安全和使用功能的重要施工部位和隐蔽工程

(2)见证取样和专项检测

(3)测量复核和检验过程

(4)安装试验

(5)新工艺、新技术、新材料、新设备的试验,首次试验段重要施工过程

(6)施工过程中出现的严重质量问题及质量事故处理过程

(7)影响工程质量的关键工序

3、旁站监理的内容和清单

重要部位旁站要求

土方地形1、原地形标高测量(标高、面积)

2、土方回填(标高、土方量、土方质量)

植物种植1、植物规格、形态、病虫害

2、树穴开挖(长度、宽度、病虫害)

3、植物修剪

隐蔽工程全过程跟踪

营养土使用全过程跟踪

建筑材料、种植材料进场见证和取样跟踪、栽植土的检验、树木草

皮栽植苗木进场检验

新技术、新工艺、新材料、新设

全过程跟踪

定位放线、沉降观测参与施工单位共同测量观测

十一、分部分项工程检测的内容和要求

分项工程名称检测内容与要求

栽植土1、栽植土必须符合栽植植物的生长要求

2、检查土壤分析报告

3、土地平整不低于规程,检查频率3000㎡1点,每点500

㎡,但不少于3点

4、石砾等杂物含量不高于规程,检查频率3000㎡1点,每点

500㎡,但不少于3点

5、栽植土深度和地下水位深度符合规程要求,检查频率3000

㎡1点,每点500㎡,但不少于3点

6、栽植土块地径符合规程,检查频率3000㎡1点,每点500

㎡,但不少于3点

7、石砾、瓦砾、杂物块茎符合规程,检查频率3000㎡1点,

每点500㎡,但不少于3点

8、地形标高符合规程,检查频率3000㎡1点,每点500㎡,

但不少于6点

植物材料1、植物材料品种符合设计要求

2、严禁带有重要病虫草害,检测“植物检疫证”和“苗木出

圃单”

3、姿态和生长势、检测频率按乔灌木数量10%,每株为1点

4、土球和裸根树木根系

5、乔木胸径、高度和蓬径

6、灌木高度、蓬径、地径

7、球类蓬径和高度

树木栽植1、放样定位符合设计要求,偏差不得超过5%-10%

2、树坑按规程

3、定向及排列按规程

4、栽植深度按规程

5、土球包装物、培土、浇水按规程

6、垂直度、支撑、绕杆、修剪按规程

绿化工程监理实施细则(完整资料).doc

【最新整理,下载后即可编辑】 白莲泾整合整治工程 绿化工程监理实施细则 总监理工程师: 专业监理工程师: 上海新光工程咨询有限公司 白莲泾综合整治工程项目监理部 年月日 白莲泾整合整治工程绿化工程监理实施细则

1 工程概况 1.1工程名称:白莲泾综合整治工程绿化工程 1.2 业主:浦东新区海塘管理署、浦东新区河道管理署、浦东新 区河闸管理署 1.3设计单位:上海市城市建设设计研究院、华东师范大学、华东理工大学 1.4监理单位:上海新光工程咨询有限公司 1.5承包商:上海浦东新区东宝市政实业有限公司、上海东外滩园林市政有限公司、华东师范大学、华东理工大学 1.6工程地址:白莲泾浦东南路桥至老白莲泾套闸段 1.7工程规模: 本绿化工程(浦东南路——白莲泾套闸)包括三个部分:防汛墙美化工程、浮岛绿化和套闸之间防汛墙的美化。 白莲泾段防汛墙美化工程:防汛墙的迎水面布置涂迷彩涂料、垂直绿化组合模块、防汛墙顶部绿化带及爬山虎挂蓝等。整治防汛墙美化39324m。 浮岛绿化工程:结合防汛墙美化工程,依据白莲泾河道外貌,将水面廊道设计成模块化浮动型,从内至外,依次布置种植高,中,低的水生植物的生态浮岛,远处眺望,与河岸绿化相连,视觉上更富有层次感,构筑一条城市水脉的绿色堤防。浮岛绿化种植4452m 2。 白莲泾套闸闸区绿化改造工程:闸区北部绿化现状良好,基本保

持原状;南部现状基本为草地,在靠近围墙处有一排水杉,在绿化改造中增加花灌木和矮灌木。 2 编制依据 (1)国家、地方政府和相关部门的相关法律、法规、规程和规范。 (2)《工程建设标准强制性条文》(水利工程部分)。 (3)《上海市水利工程施工质量检验评定标准(试行)》(DBJ08-90-2000) (4)《水利水电工程组织设计规范》SDJ338-89。 (5)《水利水电工程施工测量规范》(SL52-93)。 (6)《疏浚工程技术规范》(JTJ319-99)。 (7)本工程施工图纸及施工承包合同。 (8)《建设工程安全生产管理条例》(国务院令第393号)。 (9)《上海市建设工程文明施工管理暂行条例》 2.7本工程项目审批文件、施工图纸、设计文件(包括设计交底、图 纸会审记录、设计变更及设计通知单等)、技术资料。 2.8本工程建设监理合同、施工承包合同。 2.9经批准的《施工组织设计(方案)》及其他文件。 3 监理工作流程

城市道路工程监理实施细则

城市道路工程监理实施细 则 The Standardization Office was revised on the afternoon of December 13, 2020

城市道路工程监理实施细则 渭南市建设工程监理中心富平监理部二〇一五年九月十八日

目录 一、工程概况: 二、监理依据及执行标准、法规: 三、监理内容: (一)专业特点 (二)监理流程 (三)监理工作的控制要点及标准值(四)监理工作的方法及措施

一、工程概况: 二、监理依据及执行标准、法规: 1、监理依据:已批准的监理规划。与专业工程相关的标准,设计文件和技术资料。施工组织设计 2、执行标准和法规: 工程建设规范《城市道路工程质量验收规范》等标准。中华人民共和国建筑法、国家建设工程质量管理条例及建设部监理文件和建设的政策、法规。 国家现行的有关技术规范、规程、标准和强制性条文。工程监理规范,省市主管部门颁发的有关质量监督文件。 三、监理内容: (一)专业工程特点: (二)监理工作流程(附表) (三)监理工作的控制要点及目标值

(四)监理工作方法及措施: 1、施工准备阶段监理工作: ⑴督促承建单位建立工程项目质量保证体系,承建单位是工程具体实施者,在项目开工前要求承建单位根据工程特点和质量目标要求,建立质量保证体系,明确质量管理目标和质量管理职责,以及完善的质量管理程序和办法。 ⑵为了掌握工程情况,取得良好的监理工作效果,监理人员要充分熟悉图纸,并对施工图进行审核,同时,参加设计技术交底与图纸会审,发现问题及时向设计单位提出。 ⑶审查施工单位的施工组织设计,并要求施工单位对主要施工方法或工程关键部位,分别编制施工技术方案。 ⑷施工前应会同勘测设计部门到现场交接中线控制桩和设计指定的水准点,并应对控制桩加以保护。临时水准点的设置距离不大于

公路工程改造监理实施细则

第一章总则 1.1 工程概况 ######东起江苏省丰县,西至菏泽市东明县,是省际交通的重要通道。大田集至定陶段是丰东线菏泽境内的一部分,现为二级公路,该路段修建时间较早,路面窄且病害严重,已无法满足快速增长的交通运输需求,成为制约丰东线菏泽境内通行的交通瓶颈。因此,该项目改建势在必行,通过加宽路面,改善通行条件,将更好地促进社会经济和交通运输事业的发展,是适应交通量快速增长,完善公路交通网络布局的一项重要工程。 本项目采用二级公路标准,设计速度80km/h,第二驻地办承担第三、四、六合同段的监理任务。其中第三合同段包含K111+850.9~K132+372.5段内的临时工程、路面工程、绿化工程,一般路段路基宽度采用15.0m,路面宽度采用13.5m,定陶县黄店段及德商高速分离立交处路基宽度采用23.5m,路面宽度采用22m,定陶县东王店路基宽度采用16.5m,路面宽度采用15m,定陶城区段路基宽度采用19.5m,路面宽度采用18m;第四合同段包含K144+937.2~K150+668.4段内的临时工程、路面工程,路基宽度采用23.5m,路面宽度采用22.0m;第六合同段为全线交通工程,包含标志、标线、轮廓标、道口标柱和示警桩。 三合同段路面结构层类型为:加宽及新建路面表面层采用细粒式改性沥青混凝土(AC-10),下面层采用中粒式沥青混凝土(AC-16),基层采用水泥稳定碎石,底基层采用二灰土;补强路段基层采用水泥稳定碎石;罩面路段面层采用细粒式改性沥青混凝土(AC-10)。 四合同段路面结构层类型为:加宽及新建路面面层采用中粒式改性沥青混凝土(AC-16),基层采用大粒径透水性沥青混合料(LSPM-25)和水泥稳定碎石,底基层采用二灰土;补强部分面层采用采用中粒式改性沥青混凝土(AC-16

(完整版)园林绿化工程监理实施细则

1.工程概况及专业工程特点: 1.1 工程概况 本工程位于莱西市沙岭河公园(北京路-济南路)段。该路段长450米,宽50米绿化面积2.25万平方米。 1.2 专业工程特点和监控要点 园林绿化工程的特点是综合性、艺术性和独特性。园林绿化工程内容多样化、复杂化,工程规模日趋大型化,园林绿化工程与土木、建筑、市政、灯光及其它工程协同作业日趋增多,园林绿化工程还涉及美学、艺术、文学等相关领域,其艺术文化内涵逐步提高,此外还具有施工方法不一,质量要求不一,季节性强,受自然条件影响大等特点,因而施工项目的质量比一般工程项目的质量更难以控制。 1.2.1园林绿化种植工程 1.2.1.1本绿化工程植物材料的选择和配置有以下特点: ⑴植物类别丰富,品种充实。植物类系包括了常绿乔木、落叶乔木、常绿灌木、落叶灌木、常绿草本地被、水生植物、草本花卉等八大类。 ⑵景观效果明显,工程竣工后可以形成乔、灌、草(地被)结合;花、果、叶相配;高、中、低错落,层次和季相丰富;以春景为主,四季有花,四季常青,呈现生物多样性并具有湿地生态景观的人工植物群落。 1.2.1.2本绿化工程植物材料的监理工作重点: ⑴对投入材料和设备的订货、采购、检查、验收、取样、试验

均应进行全面控制,从组织货源到使用认证,要做到层层把关。严控进场的种植土质量,苗木质量和规格,各种管线、铺装材料、灯光亮化设施、控制设备等材料和设备的质量。 ⑵要求施工单位编制切实可行和详尽的施工方案,并注意方案的整体性。方案应包括绿化工程中的种植前土壤处理、苗木运输和假植、种植穴或槽、树木种植、大树移植及土建工程中的叠山、塑山、小品工程和园林景观照明工程等方面的施工方法、施工顺序和质量控制点等内容。 ⑶严格监控样板区段的施工质量,确定样板段的质量标准,以样板段为标准进行推广施工。 ⑷督促施工单位加强园林绿化工程的后期养护管理。 2、编制依据 2.1 设计文件 2.1.1本工程设计文件、设计补充文件及说明、设计变更等设计文件,与设计有关的标准图集及说明。 2.1.2 设计交底和图纸会审会议纪要。 2.2 监理文件 2.2.1本工程的监理规划。 2.2.2工程委托监理合同。 2.3总包、分包施工单位的施工合同 2.4 园林绿化工程标准、施工质量验收规范和技术规程等 2.4.1《建设工程监理规范》(GB50319-2013)

市政道路工程监理实施细则DOC

一、工程概况: 本次工程是对重庆市江北区四条路城市对外连接道路进行路面及其附属设施改造,四条路分别为大川水岸、重庆市救助站对外连接道、鸿恩雅苑对外连接道、长新路。 二、编制依据: 1.《市政道路工程质量检验评定标准》CJJ1-90; 2.《水泥混凝土路面施工及验收规范》GBJ97-87; 3.《公路路面基层施工技术规范》JTJ034-2000; 4.《公路沥青路面施工技术规范》JTJ032-94; 5.《公路工程质量检验评定标准》JTJ071-98; 6.《建设工程监理规范》GB50319-2000; 7.本工程《建设监理规划》; 8.本工程《施工组织设计》; 9.本工程设计图纸及有关技术文件等。 三、主要监理内容 1.道路工程:原混凝土路面、基层拆除,原人行道砖、路缘石、路边石的拆除,土石方挖运、土石方回填、回填碾压、余方弃置、安砌预制混凝土路缘石及路边石、水泥稳定级配碎石基层、混凝土基层、改性沥青混凝土面层、人行道透水砖及盲道砖铺设、交通标示线。 2.挡护工程:土石方开挖,土石方回填,重力式挡墙。 3.管道工程:挖沟槽土石方,土方回填,聚乙烯(HDPE)双壁波纹雨、污水管,混凝土检查井,d300国标II级钢筋混凝土管满包,雨水口。 4.电气工程:强电管沟,强电检查井,电力电缆,路灯,路灯手孔井,接地装置,配电箱等。

五、监理控制要点 1. 准备工作控制要点 熟悉合同文件、设计文件及有关技术资料,组织或协助业主组织图纸会审和设计技术交底; 2. 审查承包人的施工组织设计,提出审查意见,审核、检查进度计划及质量目标控制计划,签返《施工组织设计(方案)报审表》; 3. 审查承包人现场项目管理机构的质量管理体系、技术管理体系和质量保证体系,审核其组织机构、管理制度、人员的资格证和上岗证是否能确保工程项目的施工质量; 4. 检查施工机具进场情况,审查施工机具性能和数量是否满足施工要求,签返《进场设备报验单》; 5. 审查承包人报送的《分包单位资格报审表》和分包单位有关资质资料,符合有关规定后,签返《分包单位资格报审表》; 6. 复核承包人报送的测量放线控制成果,检查控制桩的保护措施,审查专职测量人员的资格及设备检定情况,符合要求后签返《施工测量放线报验单》; 7. 核查承包人各类材料的进场数量、质量(含质保书)及检测报告,签返《工程材料/构配件/设备报审表》; 8. 检查承包人施工准备情况,批复《工程开工报审表》。 六、控制目标 1. 路基工程 1.1 土石方工程: (一)基本要求: 1)清除地表腐植土0.3米并压实,当松土厚度超过0.3米时,应翻挖土后再回

公路涵洞工程监理实施细则范本

为使本建设项目监理工作制度化、标准化、规范化、程序化,进一步提高工程监管水平,提高投资效益,依据项目施工、监理合同及有关规范、规定特制定本细则,与其它管理办法互为补充,望各参建单位遵照执行。 一、工程概况 二、编制依据 1、监理规划 2、部颁《公路路基施工技术规范》(JTG F10—2006) 3、部颁《公路路面基层施工技术细则》(JTG/T F20—2015) 4、部颁《公路水泥混凝土路面施工技术细则》(JTG/T F30-2014) 5、部颁《公路沥青路面施工技术规范》(JTG F40-2004) 6、部颁《公路工程质量检验评定标准》(JTJ F80/1—2004) 三、路基施工监理控制要点 (一)、路基施工准备阶段的监理 1、测量工作监理要点: (1)、监理工程师向承包人书面提供原始基准点、基准线和基准高程的方位及数据。 (2)、施工单位必须根据设计资料认真搞好导线复测工作,复测采用全站仪或其它满足测量精度的仪器,复测导线时必须和相邻施工段的导线闭合,测量精度应满足规范要求. (3)、原有导线点不能满足施工要求时,应进行加密,保证在道路施工中,相邻导线点间能相互通视。对有碍施工的导线点,施工前应加以固定,固定方法可采用交点法或其它方法. (4)、路基开工前应全面恢复中线并固定路线主要控制桩,如交点、转点、圆曲线及缓和曲线的起讫点等。所有中线桩及主要控制桩必须采用坐标法恢复。 (5)、纵断高程测量要求至少每20米测一点,数据必须闭合,记录清楚完整,无涂改。应整理绘制复测后的纵断面图,并计算填挖高度. (6)、横断面测量要求至少每20米测一横断面,地形变化特殊地段应加测断面,地貌特征做好记录和说明,驻地办抽检频率不少于设计断面的30%同时根据需要增加频率.

公路工程监理使用表格word版本

公路工程监理使用表格

目录 1、总体施工组织设计报审表················································A-10 2、分项(分部、单位)工程开工申请批复单··································A-11 3、施工放样报验单························································A-12 4、原材料报验单··························································A-13 5、分项工程施工主要人员报验单············································A-14 6、进场设备报验单························································A-15 7、施工方案及主要工艺报审表··············································A-16 8、专项安全、文明(环保)施工方案报批单··································A-17 9、检验申请批复单························································A-18 10、工序检查报验单·······················································A-19 11、下承层检验申请批复单·················································A-20 12、混凝土浇筑申请报告单·················································A-21 13、施工单位月工作计划报告单·············································A-22 14、施工单位每周工作计划·················································A-23 15、监理巡视记录························································A-24 16、监理旁站记录·························································A-25 17、监理日志·····························································A-26 18、监理日巡视、旁站、抽捡安排表·········································A-27 19、工地会议记要·························································A-28 20、监理指令·····························································A-29 21、工程暂时停工指令·····················································A-30 22、复工申请·····························································A-31 23、复工指令·····························································A-32 24、施工日志·····························································A-33 25、工程质量(安全)事故处理报告单·······································A-34 26、中间交工证书·························································A-35 27、公路工程(施工段)交工验收证书··································A-36 28、工程缺陷责任期终止证书···············································A-37

园林绿化工程安全监理实施详尽细则

园林绿化工程安全监理实施详尽细则

咸嘉生态文化城镇带 (南外环、太乙大道及规划七路)绿化工程 施工安全 监 理 细 则 编制 批准 编制时间: 咸嘉生态文化城镇带(南外环、太乙大道及规划七路) 绿化工程项目监理部

目录 一、工程项目概况 (3) 二、安全监理实施细则的编制依据 (4) 三、监理范围 (4) 四、监理工作流程 (4) 〈一〉监理工作依据 (5) 〈二〉施工监理工作程序 (5) 五、监理工作控制要点及目标值 (8) 〈一〉本工程监理预控措施 (8) 〈二〉本工程施工安全监理控制要点及目标值 (9) 六、监理工作方法及措施 (10) 〈一〉主要工程安全检查要点 (10) 〈二〉监理工作内容 (11) 〈三〉安全施工监理手段 (14) 〈四〉安全施工监理措施 (15)

咸嘉生态文化城镇带 (南外环、太乙大道及规划七路)绿化工程 安全监理实施细则 安全生产始终贯穿于整个建设工程的全过程,安全监理工作的主要任务是贯彻落实国家的安全生产方针、政策、法律、法规,督促施工单位按照国家有关安全生产的现行法律、法规和标准进行生产施工,消除施工中的冒险性、盲目性、随意性及违反各种操作规程的现象。 市政工程的安全监理工作不仅要监督检查各部位安全文明生产的安全防护措施的贯彻落实情况,还应该监督检查施工中各项安全措施的落实,以达到预防安全事故、控制和减少各类伤亡事故的发生,确保安全生产。 为了更好的贯彻落实《建筑法》、《安全生产法》、《建设工程安全生产管理条例》等法律法规,更充分的发挥监理单位所起的监督、帮助、促进、协调、服务的作用,落实安全监理责任,结合本工程实际情况,特制定本工程安全监理实施细则,以指导安全监理工作有效开展。 一、工程概况 工程名称:咸嘉生态文化城镇带(南外环、太乙大道及规划七路)绿化工程工程地点:南外环、太乙大道及规划七路沿线两侧 建设单位:咸宁市政府投资项目建设管理局 监理单位: 设计单位:湖北淦川园林景观设计有限公司 施工单位:湖北碧云园林绿化有限责任公司 工程规模: 总规模:181872.6㎡。 规划七路,红线范围:128339.1㎡。道路总长为2500m。绿化面积为57657.7㎡。草沟面积为6634.2㎡.湿沟为3860m。 太乙大道,道路总长为2880m。景观面积为68144.7㎡。绿化面积为64841.7㎡。海绵体面积为9677.7㎡。

道路工程监理实施细则范文

市长寿区2014年农村公路路面改造工程 监理实施细则 (道路工程) 容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期:

道路工程监理实施细则 1. 本细则编写依椐 1.1本项目工程已批准的监理规划。 1.2路达工程勘察设计咨询的一阶段施工设计图纸 1.3规、规程: 1.3.1《建设工程监理规》GB50319--2000 1.3.2《建筑工程施工质量验收统一标准》 1.3.3工程建设标准强制性条文 1.3.4各分部工程质量验收规如:(根据工程项目具体情况增加删减) 《工程建设强制性标准条文》房屋建设部分 《建筑地基基础工程施工质量验收规》GB50202-2002 《混凝土结构工程施工质量验收规》GB50204-2002 《建筑工程施工质量验收统一标准》GB50300-2001 《建筑工程质量检验评定标准》GB50301-2002 《公路路基设计规》JTG D30—2004 1.4 ******工程施工组织设计 ******工程委托监理合同 ******工程建筑工程施工合同 ******工程招投标文件 2. 专业工程特点

2.1 ******工程,位于****省******市****,总面积约****平方米,地上**层,地下**层,主要由*****组成。地下是***,地上主要是***,建筑高度是米,结构形式为**,基础形式为****。耐火等级是***,抗震设防烈度是****。 2.2 该工程建设单位是***,施工单位是***,设计单位是***(简单描述) 3.监理工作的流程如下: 4. 监理目标值

绿化景观监理细则

绿城理想之城中央公园工程 监理实施细则(绿化景观部分) 内容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期:

目录 一、专业工程的特点 二、监理依据 三、监理工作范围 四、园林小品质量控制要点: (1)园路 (2)钢构廊架、钢构特色景观桥 (3)木栈道、木平台 (4)砼景观桥 (5)铁艺雕塑 (6)水系湖体 五、园林植物种植前准备阶段控制要点 六、园林植物施工阶段控制要点: (一)园林植物质量控制要点 (二)园林植物质量的检验方法及措施 七、种植土质量控制要点: (一)种植土质量控制要点 (二)种植土检验方法 八、园林植物种植工程质量控制要点: (一)放样定点 (二)乔木土球挖掘规格 (三)灌木土球挖掘规格 (四)竹类土台挖掘规格 (五)树木种植穴(塘)规格 (六)树木土球的包扎 (七)树木挖掘 (八)树木运输前的修剪 (九)树木的装运 (十)树木种植前的修剪 (十一)树木的种植 九、大树、特大树种植工程质量控制要点 (一)大树、特大树修剪强度 (二)移植时期 (三)大树、特大树土球和包扎 (四)大树、特大树木吊运、根、枝处理 (五)大树、特大树种植穴(塘)技术处理 十、草坪、草本地被植物种植工程控制要点:(一)草坪种植 (二)花卉、地被植物种植 (三)花卉、地被植物的配置和选择质量要求 十一、养护管理阶段的监理

一、专业工程的特点 本工程工作量大,任务繁重,工期紧。 本项绿化工程植物材料的选择和配置有以下特点: 1、植物类别丰富,品种充实。植物类系包括了常绿乔木、落叶乔木、常绿灌木、 落叶灌木、常绿草本地被、水生植物、草本花卉等八大类。 2、景观效果明显,工程竣工后可以形成乔、灌、草(地被)结合;花、果、叶相配;高、中、低错落,层次和季相丰富;以春景为主,四季有花,四季常青,呈现生物多样性并具有湿地生态景观的人工植物群落。 3、根据工程时间的安排,宜采取先落叶树,后常绿树,冬秋落叶树,春天常绿树的程序去种植,以提高种植成活率和保存率。 4、针对本工程所使用的植物材料,待收到种植设计图纸后,将对每个品种的适生条件和种植、养护要点呈报建设单位。并作为监理对其控制的要求。 二、监理依据 该绿化景观工程监理是受工程项目建设单位的委托,依据国家有关工程建设的法律、法规,经有关部门批准的工程项目建设文件,建设工程委托监理合同及建设工程合同,对工程建设实施的专业化监督管理。在实施工程建设中和实施监理依据是: 1、中华人民共和国国务院《城市绿化条例》; 2、中华人民共和国行业标准《城市绿化工程施工及验收规范》(1999年); 3、《砌体工程施工质量验收规范》(GB 50203-2002); 4、本工程合同文件、施工组织设计 三、监理工作范围 绿城理想之城中央公园与商业中心景观工程全部施工内容施工阶段和养护阶段的监理。控制工程质量、造价和工期“三控制”;对合同的履行、安全生产和信息处理“三管理”;协调建设单位与工程建设有关各方的工作关系“一协调”。 四、园林小品监理控制要点 (一)园路 1、园路路基挖槽宽、深必须符合设计要求,监理验槽并签发隐蔽工程报验单后,施工企业方可进行下道工序; 2、路基的垫层道渣、碎石厚度必须符合设计要求; 3、路基的强度、密实度必须符合设计要求; 4、砂浆比必须符合设计要求,使用商品砼必须出具有关商品砼的材料,同时要做好砂浆(强

市政道路工程安全监理实施细则

庞公路延伸段(庞公祠路--向阳路) 道路排水工程 安全文明施工监理细则 编制: 审核: 北京中协成建设监理有限责任公司 2017年 1 月 25日

安全监理工作细则 一、项目工程特点 1、庞公路延伸段为庞公片区南北向主干道,本次设计起点为现状庞公路终点(庞公祠路),途中与主干道(庞鱼路、江华路、内环路、向阳路)、规划次干路、支路等13条路相交,由南止于向阳路。 2、庞公路沿线路口交叉均为平交,由于交叉口通行能力小于路段,并且相交道路较多,为满足交通需求,提高交叉口通行能力,针对不同等级道路采用不同平交方式,主干路相交采用十字交叉,对路口进行扩宽渠化,次干路采取普通平交,不展宽渠化。 3、沿线有许多居民住宅区和菜地,对文明施工的要求高。 4、线路区分布少量水塘及灌溉蓄水池,含少量地表水。 5、据现场考察,道路沿线地势平坦、交通便利、水、电充足,能满足工程需要。 二、安全监理工作流程 监理部成员熟悉图纸┈以总监为组织者,各专业监理工程师分工编制安全监理细则┈监理部审核施工单位的施工组织设计、专项施工方案、安全应急救援预案┈监理部,核查施工单位的安全生产许可证,检查施工单

位的安全生产管理体系是否健全,并检查施工单位的安全规章制度、特殊工种上岗证、安全技术交底┈各专业监理工程师检查施工单位的施工机具的合格证及保养情况┈各专业监理工程师检查施工操作人员的安全教育培训资料┈监理部检查施工现场的机具布置等是否与总平面图相符┈监理部巡视检查现场施工安全工作,检查施工用电是否规范,并针对情况发出联系单、通知单等及时督促施工单位整改,督促施工单位安全管理体系有效运转┈施工单位拒绝按照监理要求进行整改或停止施工的,监理部及时向当地主管部门进行报告┈整理安全资料,进行归档。 三、监理工作控制要点及目标 3.1安全管理方针 “安全第一,预防为主”。安全生产应以人的管理核心,即消除人的不安全行为,严格控制违章作业行为,施工过程中一切作业必须服从安全。 安全管理重点内容:检查施工单位安全管理体系是否健全,专职安全员配置是否符合要求,审查施工单位安全管理资料是否及时、齐全、真实,施工组织设计、施工方案中安全技术措施是否可靠、可行;对施工组织设计、施工方案、施工安全技术措施、安全防护用品的使用情况进行检查,对施工中存在的安全隐患应严格按《安全生产管理条例》第十四条规定行使监理的安全职责,并应及时与施工方沟通,动之以情,晓之以理,督促施工单位整改、消除安全隐患,充分体现监理工作的预控性和协调性。 基础施工阶段施工安全控制要点:挖土机械作业安全;边坡防护安全;

园林绿化工程监理实施细则59560

园林绿化工程监理实施细则一、工程概况 工程名称:XX绿化升级改造工程 工程地 点: x>市<x>区<乂棉 建设单 位: XXf理委员会 监理单 位: XX建设监理有限公司 设计单 位: X XX林建筑规划设计院 工程规 模: 园建绿化造价206.50 万元 施工单 位: XX园艺绿化工程有限公司 一、专业工程的特点景观工程园林绿化工程的特点是工作量大,任务繁重,工期紧。绿化工程植物材料的选择和配置有以下特点: 1、植物类别丰富,品种充实。植物类系包括了常绿乔木、落叶乔木、常绿灌木、落叶灌木、常绿草本地被、水生植物、草本花卉等八大类。 2、景观效果明显,工程竣工后可以形成乔、灌、草(地被)结合;花、果、叶相配;高、中、低错落,层次和季相丰富;以春景为主,四季有花,四季常青,呈现生物多样性并具有湿地生态景观的人工植物群落。 3、根据工程时间的安排,宜采取先落叶树,后常绿树,冬秋落叶树,春天常绿树的程序去种植,以提高种植成活率和保存率。 4、本工程属大型以上且专业性较强的项目,针对工程所使用的百种植物材料,待收到种植设计图纸后,将对每个品种的适生条件和种植、养护要点呈报建设单位。并作为监理对其控制的要求。 二、监理细则编制依据

1、景观工程监理规划; 2、从事该工程施工安装单位报送的施工组织设计; 3、中华人民共和国国务院令第100号《城市绿化条例》; 4、CJJ/T 82-1999《城市绿化工程施工及验收规范》; 5、DB11T 212-2003《城市园林绿化工程施工及验收规范》; 6、本工程设计文件。 三、监理工作范围 景观工程施工阶段和养护、保修阶段的监理。控制工程质量、投资和 进度“三控制”;对合同的履行、安全生产和信息处理“三管理”;协 调建设单位与工程建设有关各方的工作关系 二、质量控制 1、各类苗木土球挖掘规格:乔木:土球直径(cm)按胸高直径的8倍, 土球厚度按胸高直径7—8倍;灌木:土球直径(cm)按冠径的80 %, 土球厚度按冠径60 %; 2、竹类必须选择2年生的边缘竹子为竹母;土台挖掘需保留来鞭 40-50CM,去鞭80CM;近距离移植必须多带宿土,来去鞭可适当放 小,但必须带有隐芽的地下鞭,保护好螺丝钉,否则就不发笋,延误竹林的满园; 3、裸根树木挖掘一定要用用锐利铁锹,直径 3 cm以上的根要用锯锯断;细根可用剪枝剪剪断,不得强拉或劈断,尽量保护毛细根;带 土球树木,保证不使土球松散,在整修土球时必须先扎腰箍; 4、树木土球的包扎常用草绳,采用橘子辫、五角形、铜钱形皆可;但必须

市政道路工程监理实施细则

B13 成阿工业园区元丰路工程 监理实施细则 (道路) 内容提要: 专业工程特点 监理工作流程 监理工作控制目标及控制要点 监理工作方法及措施 项目监理机构(章): 专业监理工程师: 总监理工程师: 日期:

目录 目录----------------------------------------------------1 一、总则-------------------------------------------------2 二、工程特点---------------------------------------------2 三、监理工作流程-----------------------------------------3 四、监理工作目标-----------------------------------------6 五、控制要点和方法---------------------------------------6 1、管线分部------------------------------------------7 2、路基分部------------------------------------------7 3、路面分部-----------------------------------------11 Ⅰ、路面基层-----------------------------------------11Ⅱ、路面面层-----------------------------------------12 4、其它部位-----------------------------------------13 5、工程进度-----------------------------------------13 6、工程造价-----------------------------------------14

市政道路及配套工程监理实施细则监理大纲范本

XXXXXX工程 监理实施细则 编制: 审批: 有限公司 XX年X月

目录 一、工程概况-----------------------------------------------------2 二、编制依据-----------------------------------------------------2 三、监理工作目标值-----------------------------------------------3 四、道路工程质量监理工作流程-------------------------------------3 五、道路工程测量放样质量监理-------------------------------------5 六、路基工程质量监理---------------------------------------------7 七、道路基层质量监理---------------------------------------------16 八、道路面层质量监理---------------------------------------------17 九、人行道工程质量监理-------------------------------------------23 十、附属构筑物质量监理-------------------------------------------23

一、工程概况 本项目位于。两条路均为城市支路,设计速度为30km/h。 主要参建单位: 建设单位: 设计单位: 监理单位: 施工单位: 本工程主要包括: 含道路标线、导向箭头、地面文字标记、标志杆基础。 二、编制依据 1、工程施工合同文件、设计图纸及招标文件等资料。 2、《城市道路工程设计规范》(CJJ37-2012); 3、《城市道路交叉口规划规范》(GB 50647-2011); 4、《城市道路交叉口设计规程》(CJJ 152-2010); 5、《城市道路路线设计规范》(CJJ 193-2012); 6、《无障碍设计规范》(GB 50763-2012)。 7、《城市道路路基设计规范》(CJJ 194-2013); 8、《建筑地基处理技术规范》(JGJ 79-2012); 9、《城镇道路路面设计规范》(CJJ169-2012); 10、《公路沥青路面设计规范》(JTG D50-2006); 11、《城镇道路工程施工与质量验收规范》( CJJ 1-2008); 12、《公路水泥混凝土路面设计规范》(JTG D40-2011)。 13、其它有关的国家及地方强制性规范和标准 14、经批准的监理规划 15、《建筑工程施工技术资料编制指南》; 16、《省建筑工程竣工验收技术资料统一用表》; 17《建筑施工安全管理资料统一用表》 18、行业主管部门现行有关建设工程管理的文件规定;

绿化工程监理规划

A.0.4 广靖高速下、新洲路南、人民路东 绿化景观工程项目 监理规划 2017年3月1 日至2017年6 月1 日 内容提要: 工程概况 监理目标、依据 监理组织机构、人员配备、岗位职责 监理工作方法和措施 监理工作重难点监控 监理单位(章):江苏华夏工程项目管理有限公司总监理工程师:李祥生 日期:2017年2月18日 江苏省建设厅监制

广靖高速下、新洲路南、人民路东 绿化景观工程项目 监理规划 一、工程项目概况 工程名称:广靖高速下、新洲路南、人民路东绿化景观工程项目 工程地点:泰州靖江市 建设单位:靖江市水利局 监理单位:江苏华夏工程项目管理有限公司 设计单位:南京市园林规划设计院有限责任公司 施工单位:江苏新经纬景观营造有限公司 工程总造价:约525万 二、监理目标 (一)监理工作目标 工期目标:90个工作日 质量目标:合格 安全与文明施工监理目标: 1.伤亡事故控制:伤亡事故为零。 2.安全监理目标:按《建筑施工安全检查标准》(JGJ59-99)达到合格等级。 3.文明施工目标:达到《建筑施工安全检查标准》(JGJ59-99) (二)监理工作内容 施工阶段的监理工作,包括: 1、施工阶段全过程的质量控制、进度控制、投资控制、合同管理、组织协调;

2、严格执行中华人民共和国国家标准《建设工程监理规范》(GB50319-2000),履行造价人才网监理合同中的义务和责任; 3、文明施工及安全生产的监理; 三、监理工作依据 1.国家《城市绿化工程施工及验收规范CJJ/T82—99》; 2.《工程建设监理规范》(GB50319-2000); 3.本工程委托监理合同; 4.本工程施工承包合同; 5.本工程的设计施工图、设计说明书和设计变更; 6.国家和莆田市有关法律、法规、技术标准。 四、监理机构的组织形式及人员配置情况 本工程规模较小,根据工程特点,施工阶段不同,监理机构设置,现场共配备一位监理员直接由总监理工程师管理,总监理工程师负责整个项目监理工作的规划、组织和领导,同时负责整个项目范围内各方面工作的协调和合同管理的具体工作。 五、岗位职责 (一)总监理工程师的职责 (1)确定项目监理机构人员的分工和岗位职责。 (2)主持编写项目监理规划、审批项目监理实施细则,并负责管理项目监理机构的日常工作。 (3)审查分包单位的资质,并提出审查意见。 (4)检查和监督监理人员的工作,根据工程项目的进度情况可进行 人员调配,对不称职的人员应调换其工作。 (5)主持监理工作会议,签发项目监理机构的文件和指令。 (6)审定承包单位提交的开工报告、施工组织设计、技术方案、进度计划。 (7)审核签署承包单位的申请、支付证书和竣工结算。

道路工程监理实施细则

道路工程监理实施 细则

城口县国道G211(省道S202线)鸡鸣场镇 过境公路改线工程 质量监理细则 编制(专业监理工程师): 审核(总监理工程师): 重庆建新建设工程监理咨询有限公司 二O一七年六月

质量监理实施细则 1、工程概况: 本项目位于城口县S202线鸡鸣乡,为S202箱穿越场镇段改线工程。起点位于S202线K125+203,终点位于S202线K125+203,控制高程分别为559.03m和564.42m,路线中间控制点为先行修建的双孔石拱桥(车行道净宽12m),控制高程为559.95m。项目为新建工程全长 1.162518km。 1)、本工程路幅布置如下: 路幅宽22m=5.0m(人行道、绿化带)+12.0m(车行道)+5.0m (人行道、绿化带)。 道路横坡:车行道向外1.5%,人行道向内2.0%。 车行道边采用平侧石筑边,人行道边平侧石采用花岗岩石材。 2)、排水设置 (1)污水管道:顺道路通长设置于人行道下管径为 DN400~d600,污水井结构为M10水泥砂浆浆砌C30砼砌块,井盖为:轻型高分子复合材料井盖井座DN800。污水就近接入下游截污干管。 (2)雨水管道: 根据就近入河原则,收集路面及地块雨水,就近排入下游河道。顺道路通长设置于人行道下。管径为DN300~DN800,雨水井结构为M10水泥砂浆浆砌C30砼砌块,井盖为:轻型高分子复合材料井盖井座DN800,根据实际情况沿途预留雨水支管。 3)、桥涵布置

K0+080处设置2*1.5钢筋砼盖板涵,对先行修建的双孔石拱桥桥面进行改造(属路面工程)。 4)、路面结构 车行道采用沥青砼路面,按城市主干道标准设计,沥青混凝土路面设计使用年限为。路面结构设计按住房和城乡建设部《城镇道路路面设计规范》CJJ169- 执行。机动车道路面设计弯沉值为0.23mm。 机动车道路面结构(总厚58cm): 5cm AC-13C 细粒式沥青砼(SBS改性,掺抗剥落剂) 7cm AC-20C 中粒式沥青砼 22cm 5.5%水稳碎石基层 24cm 4%水稳碎石基层 沥青砼之间涂刷粘层油,若上、下两层连续摊铺可取消。 5)、人行道路面结构(总厚18cm): 20x10x6cm 砼预制透水砖 2cm 水泥砂浆 10cm 水泥砼 6)、交通情况 本项目为新建项目可全封闭施工。 7)、路基 本项目工程主要以填方为主。 8)、路基防护 路基防护采用衡重式挡墙和路肩墙,均为C20片石砼浇筑。

1、公路工程监理使用表格

施工组织 1.公路工程监理使用表格 第1页共4页 业总高级驻地办 表号表格名称监 主高级驻地驻地办 办 A-1施工放样报验单○○●A-2工程分项开工申请批复单○○●A-2-1施工单位进场主要负责人统计表○○●A-2-2施工单位进场人员统计表○○●A-3承包人每周工作计划○○●A-4监理日报●○ A-5检验申请批复单○○●A-6工作指令○○A-7工程变更令○○A-8索赔申请单○○●A-9索赔时间 /金额审批表○ A-10工地会议纪要●○A-11中间交工证书○○填写人:主送:●承设 填写 包代填送时间备注 份数 人处 工程放样后4 开工前7天4 开工前7天4 开工前7天4 每周五4 每月底3 验收后4 ●随时4 ●变更审批后4 索赔前 21 天4 ●审批后3 ○随时4 ●验收后4 抄送:○

1.公路工程监理使用表格 第2页共4页 业总高级驻地办 表号表格名称监 主高级驻地驻地办 办 A-13工程暂时停工指令○( ) A-14复工指令○○ A-15工程质量事故处理报告单○○●A-15-1不合格工程工序质量检验单○○●A-15-2工程质量处理检验反馈单● A-16工程交工证书○○A-17工程缺陷责任期终止证书○○○ ○○ A-18通用函件○○ ○○●A-19施工技术方案报审表○○●A-20施工材料报验单○○●A-21进场设备报验单○○●填写人:主送:●承设 填写 包代填送时间备注 份数 人处 ●随时3 ●整改后4 事故后 2天4 事故后 2天4 事故后 2天2 ●4 ●5 ● 4 随时4 4 4 4 4 抄送:○

1.公路工程监理使用表格 第3页共4页 业总高级驻地办承设 填写 表号表格名称监包代填送时间备注 主高级驻地驻地办份数 办人处 A-22事故报告单○○●及时4 A-23监理工程师通知(通用)○○●随时4 A-24额外或紧急工程通知○○●随时4 A-25计日工作通知○○●随时4 A-26设计变更通知○○●○5 A-27监理试验月报表●○每月底3 A-28工程监理月报表●○每月底3 A-30工程变更审查表○●○4 A-31工程变更申报表○○●4 A-32工程变更现场签认单○○●4 A-33工程变更审查汇签表○○●4 A-34工程变更通知○●2 A-35延期、索赔人员统计表○○●及时4填写人:主送:●抄送:○

园林景观与绿化工程监理细则

目录 1.工程概况 2.监理工作依据和工程质量验收规定 3.监理工作流程 4.监理工作控制要点及目标值 5.监理工作方法和措施 6.旁站监理工作 7.安全生产的监理措施

园林景观与绿化工程监理实施细则 1.工程概况 本工程地上10层,地下设有四层地下室,总建筑面积78419.5m2,总造价约30793万元。建筑总高度为51.5m。 工程范围:包括土建(含深基坑)、装修、钢结构、室内水电设备安装、室外管网等,具体情况详见施工图。 建筑总面积78419.5m2,建筑总高度为51.5m,建筑层数:地上11层,地下4层。1层至4层为商业裙房,5层至10层南北塔楼为酒店客房,地下室负一层为商业及停车场,负二至四层为停车库。 建筑结构的设计使用年限为50年,耐火等级为一级,防火等级为二级。抗震设防类别为乙类,抗震设防烈度为7度。防水等级为一级。 本项目西南面为4层20.9m高的商业裙房,5到11层为南北塔楼;商业裙房距西面规划道路边线21m,酒店距北面规划道路边线65m。人防区建筑面积为5869m2。 2.监理工作依据 2.1工程建设监理合同和经批准的监理规划; 2.2业主与承建商签订的施工承包合同及其附件; 2.3设计施工图及其说明以及施工单位的深化图; 3.4现行国家和地方的规范和标准: 《建筑工程施工质量验收统一标准》GB50300-2001; 《园林景观与绿化工程监理规程》(试行); 《建设工程监理规范》(GB50319-2007); 2.5国家和地方现行的建筑工程质量验收标准及验收规范; 2.6有关的标准图集及说明。

3.监理工作流程 4.1施工监理工作一般程序:

相关主题