临时用电专项施工方案(参考范本)

临时用电专项施工方案(参考范本)
临时用电专项施工方案(参考范本)

目录

一、工程概况............................................................................. - 2 -

二、编制依据............................................................................. - 2 -

三、电气设备及总体线路布置.............................................. - 3 -

四、电器设备的选择 ............................................................... - 4 -

五、负荷计算............................................................................. - 4 -

六、分配箱电缆选择 ............................................................... - 9 -七.安全用电组织措施......................................................... - 10 -八、安全用电技术措施......................................................... - 11 -

(一)配电室的建造....................................................... - 11 -(二)配电箱与开关箱 .................................................. - 12 -(三)电器设备的安装 .................................................. - 13 -(四)施工现场的电缆线路 ......................................... - 15 -(五)接零保护、重复接地与防雷接地 ................... - 17 -(六)现场照明................................................................ - 19 -(七)自备发电机 ........................................................... - 19 -(八)漏电保护器 ........................................................... - 20 -八.用电防火措施.................................................................. - 20 -九、消防预案........................................................................... - 23 -

附图:

附图一:施工现场临用电平面布置图

附图二:配电系统图

施工现场临时用电专项施工方案

一、工程概况

工程名称:

建设地点:

建设单位:

设计单位:

监理单位:

勘探单位:

施工单位:

说明项目所处位置、建筑面积、结构类型、建筑层数、建筑物高度、层高、抗震等级、防火等级、使用年限、±0.000相当于黄海高程标高等基本情况。

现场用电电源:电源从业主指定的接线点将线路引至工地配电室,再从配电室相继引入各施工用电点,整个现场用电设配电箱。施工用电采用TN-S系统,严格按JGJ46-2005《施工现场临时用电安全技术规范》强制性条文执行,做好用电机械与电动工具的接地、接零保护,保证其安全运行。

根据现场勘测及总体平面布置,全场设××型号塔吊××台、施工升降机××台,现场设另钢筋制作车间、木工棚各××座;现场设办公室、宿舍、食堂等(详见施工用电总平面图)。

二、编制依据

1、《建设工程施工现场供用电安全规范》GB50194-2014

2、《施工现场临时用电安全技术规范》JGJ46-2005

3、《低压配电设计规范》GB50054-2011

4、《供配电系统设计规范》GB50052-2013

5、《通用用电设备配电设计规范》GB50055-2011

6、《建筑施工安全检查标准》JGJ59-2011

7、本工程施工组织设计

8、本工程施工图纸

9、公司标准

三、电气设备及总体线路布置

本工程施工用电电源位于×××部位。甲方提供××台变压器容量为400KVA。根据规范规定本工程临时用电实施三级配电,采用TN—S接零保护系统,以保证施工过程中用电的安全性与可靠性。

根据现场实际情况,结合工程施工平面图布置图中对各加工作业区、办公区、生活区的划分与布置所确定的变压器、机械设备的位置及施工机具的负荷分布情况,本工程在××部位设置总配电室××间。在砂浆搅拌区、塔吊、钢筋制作车间、木工制作车间、机具维修间、各主体楼层(基础或地下室施工阶段用电)、办公区等处设置分配箱共××台,在各机械设备旁设置适合各机械设备容量的开关箱,按总配电柜→分配箱→用电设备逐级供电,实现三级配电的供电系统。所有配电柜(箱)电源线由VV型塑料或YC 型橡套五芯电力电缆埋地、架空或穿保护管敷设,开关箱至用电设备则根据实际需要使用五芯、四芯或三芯电缆(或导线)穿管敷设,确保TN—S接零保护系统的完整性。

配电原则:总箱配出线采用放射式和树干式相结合的配电方式,对负荷比较大的配电点可用单独回路配电,对负荷较远又比较小的配电点上的分箱可采用树干式配电方式,总箱中的一路配线先到较近负荷点的分配电箱,再到较远的负荷点分配电箱,一路线上带的分配电箱数量一般为2~3个,由分配电箱至设备开关箱配线采用放射式或链式配线,对重要负荷或较大负荷采用放射式单路直配,对较小的负荷可采用链式配线,但每路链接设备不宜超过5台,其总容量不宜超过10KW,对大容量的对焊机、塔吊可从总箱以放射式单回路形式直配。

总配电柜设置××个馈电回路,分别供给:A、塔吊分配箱NO.2—01;B、施工升降机

机NO.2—02;C、对焊机分配箱NO.2—03;D、钢筋棚、木工棚分配箱NO.2—04;

E、搅拌机分配箱NO.2—05;

F、生活区分配箱NO.2—06;

G、办公区分配箱NO.2—07;

H、机修间分配箱NO.2—08……(注:若分多个总配电柜,则需分别说明各个配电总柜的馈电回路)

四、电器设备的选择

(一).机械表

施工机械负荷统计表

施工组织设计设备

机具用表相一致。

五、负荷计算

(一)、配电箱负荷计算(注:若设置多个总配房,各个总配房需单独计算):

1、施工现场用电量统计表:

----------------------------------------------------------------

序号机具名称型号安装功率(kW) 数量合计功率(kW)

1 塔式起重机QTZ80 31.5 3 94.5

2 施工升降机SC200 3

3 3 37.5

3 木工平刨MB1043 3 1 3

4 圆盘锯MJ114 3 1 3

5 搅拌机Jzc350 7.5 3 22.5

6 钢筋弯曲机GJ5-8 5.5 2 11

7 钢筋切断机GJ5-40 7.5 2 15

8 电焊机BX300 25 1 25

9 对焊机UNI-80 100 1 100

10 竖向焊机SH-40 30 1 30

11 插入式振动器HZ69-70A 3 3 9

12 平板式振动器P2-50 3.5 2 7

13 蒸饭车9 1 9

14 开水器15 1 15

15 空调 1.5 55 82.5

2、确定用电负荷:

(1)、塔式起重机

Kx = 0.3 Cosφ = 0.7 tgφ = 1.02 Jc =40% Pn = 31.5kW

Pe = n×(J c/J c1)1/2×Pn =数量×(0.4/0.25)1/2×31.5 = 119.5kW

P js = Kx×Pe =0.3×119.5 = 35.86 kW

Q js = P js×tgφ=35.86×1.02 = 36.58 kvar

(2)施工升降机

Kx = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe = 0.7×数量×33 = 46.2 kW

Q js = P js×tgφ=46.2×1.02 =47.12 kvar

(3)、木工平刨

Kx = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe = 0.7×数量×3 = 2.1kW

Q js = P js×tgφ=2.1×1.02 = 2.14 kvar

(4)、圆盘锯

Kx = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe = 0.7×数量×3 =2.1 kW

Q js = P js×tgφ=2.1×1.02 =2.14 kvar

(5)、搅拌机

K x = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe = 0.7×数量×22.5= 15.75kW

Q js = P js×tgφ=15.75×1.02 =16.07kvar

(6)、钢筋棚机械

K x = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe =0.7×(5.5×数量+7.5×数量)=18.2kW Q js = P js×tgφ18.2×1.02 = 18.56kvar

(7)、电焊机

K x = 0.5 Cosφ = 0.45 tgφ = 1.984

将J c =50%统一换算到J c1 =100%的额定容量

P n = S n×Cosφ = 11.25kW

P e = n×(J c/J c1)1/2×P n=数量×(0.5/1)1/2×11.25 = 7.95kW P js = K x×P e =0.5×7.95 = 3.98 kW

Q js = P js×tgφ=3.98×1.984 = 7.9kvar

(8)、对焊机

K x = 0.5 Cosφ = 0.45 tgφ = 1.984

将J c =50%统一换算到J c1 =100%的额定容量

P n = S n×Cosφ = 45kW

P e = 数量×(J c/J c1)1/2×P n= 1×(0.5/1)1/2×45 =31.82kW

P js = K x×P e =0.5×31.82 = 15.91 kW

Q js = P js×tgφ=15.91×1.984 = 31.56kvar

(9)、竖向焊机

K x = 0.5 Cosφ = 0.45 tgφ = 1.984

将J c =50%统一换算到J c1 =100%的额定容量

P n = S n×Cosφ = 13.5kW

P e = n×(J c/J c1)1/2×P n=数量×(0.5/1)1/2×13.5 =9.55kW

P js = K x×P e =0.5×9.55 = 4.77 kW

Q js = P js×tgφ=4.77×1.984 = 9.47kvar

(10)、泥工机械

K x = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe= 0.7×(3×数量+3.5×数量)=11.2kW

Q js = P js×tgφ=11.2×1.02 =11.42 kvar

(11)、厨房设备

K x = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe= 0.7×(9+15)=16.8kW

Q js = P js×tgφ=16.8×1.02 =17.14 kvar

(12)、空调

因为空调是单相用电,三相平均分配取Pn=55/3(取整数)=19 K x = 0.7 Cosφ = 0.7 tgφ = 1.02

P js = Kx×∑Pe= 0.7×(数量×1.5)=19.95kW

Q js = P js×tgφ=19.95×1.02 =20.35 kvar

(13)、100m高扬程水泵

Kx = 0.75 Cosφ = 0.8 tgφ = 0.75

P js = Kx×∑Pe = 0.75×数量×20 = 15 kW

Q js = P js×tgφ=15×0.75 = 11.25 kvar

总的计算负荷计算,总箱同期系数取Kx = 0.9,照明按照总功率的10%计

总的有功功率

P js = K x×ΣP js

= 0.9×1.1×(35.86+26.25+2.1+2.1+15.75+18.2+3.98+15.91+4.77+11.2+16.8+19.95) = 172.87kW

总的无功功率

Q js = K x×ΣQ js

=0.9×1.1×

(36.58+26.78+2.14+2.14+16.07+18.56+7.9+31.56+9.47+11.42+17.14+20.35)

=200.11 kvar

总的视在功率

S js = ( P js2+Q js2 )1/2 = (172.872+200.112)1/2 =264.44kVA

总的计算电流计算

I js = S j s/(1.732×U e) =264.44/(1.732×0.38) =401.78 A

据计算负荷已装变压器容量满足机械设备的用电要求。

选择二根VV-3×95+2×50电缆为配电柜电源电缆。

选择总配电柜进线开关为HR5-400/3。

3.分路计算及电器选择

(1)塔式起重机回路

Ie=Pe/(1.732UeCosφ)=31.5/(1.732×0.38×0.85)=56.31 A

选择电缆为VV-5×16。

选择总柜分路开关及分配箱电电源开关为HR5-100。

选择总柜分路漏电保护器为DZ15L-100(100mA,≤0.2S)。

(2)施工升降机回路

Ie=Pe/(1.732UeCosφ)=15/(1.732×0.38×0.7)=32.5 A

选择电缆为VV-5×16。

选择总柜分路开关及分配箱电电源开关为HR5-100。

选择总柜分路漏电保护器为DZ15L-100(100mA,≤0.2S)。

(3)其它分路计算方法相同,计算书省略。

六、分配箱电缆选择

1#总配房出线

开关箱的配制

因每台开关箱只允许控制一台用电设备,所以可按各分配箱为单位,直接按用电设备的额定电流来选择电缆截面与开关及漏电保护器的容量。

七.安全用电组织措施

(1)、建立临时用电施工组织设计和安全用电技术措施的编制、审批制度,并建立相应的技术档案。

(2)、建立技术交底制度

向专业电工、各类用电人员介绍临时用电施工组织设计和安全用电技术措施的总体意图、技术内容和注意事项,并应在技术交底文字资料上履行交底人和被交底人的签字手续,注明交底日期。

(3)、建立安全检测制度

从临时用电工程竣工开始,定期对临时用电工程进行检测,主要内容是:接地电阻值,电气设备绝缘电阻值,漏电保护器动作参数等,以监视临时用电工程是否安全可靠,并做好检测记录。

(4)、建立电气维修制度

加强日常和定期维修工作,及时发现和消除隐患,并建立维修工作记录,记载维修时间、地点、设备、内容、技术措施、处理结果、维修人员、验收人员等。

(5)、建立工程拆除制度

建筑工程竣工后,临时用电工程的拆除应有统一的组织和指挥,并须规定拆除时间、人员、程序、方法、注意事项和防护措施等。

(6)、建立安全检查和评估制度

施工管理部门和企业要按照JGJ59-2011《建筑施工安全检查评分标准》定期对现场用电安全情况进行检查评估。

(7)、建立安全用电责任制

对临时用电工程各部位的操作、监护、维修分片、分块、分机落实到人,并辅以必要的奖惩。

(8)、建立安全教育和培训制度

定期对专业电工和各类用电人员进行用电安全教育和培训,凡上岗人员必须持有劳动部门核发的上岗证书,严禁无证上岗。

八、安全用电技术措施

(一)配电室的建造

1.配电室在临近变压器、进出线方便、无灰尘、无蒸汽、无腐蚀、无震动、不易积水的地方建造。

2.配电室建造的要求

(1)配电室一般不小于9m2,地坪上应铺设绝缘脚垫,配备绝缘用具和用品。

(2)做到“五防一通”,即防火、防雨、防雪、防汛、防小动物和通风良好。

(3)室门应向外开,有锁,金属门要做接地或接零保护。

(4)配电室的天棚距地面不低于3m,并装设工作照明及应急照明灯各一盏。

(5)配电室建筑物的耐火等级不应低于3级,室外墙上配置砂箱和绝缘灭火器。灭火机用干粉等灭火器,严禁使用导电灭火器,灭火器挂于门外便于使用,不得放在配电间。

3.配电屏(盘)及配电装置四周的安全距离

(1)配电屏(盘)正面操作通道宽度,单列布置或双列背对背布置不小于1.5m,双列面对面布置不小于2m;后面维护通道宽护通道宽度单列布置或列面对面布置不小于0.8m,双列背对背布置不小于1.5m。侧面维护通道宽度不小于1m。

(2)配电装置上端距天棚不小于0.5m。

(3)配电室内的裸线与地面垂直距离小于2.5m时,应采用遮栏隔离。