8D报告填写说明

8D报告填写说明
8D报告填写说明

8D 报告填写说明

PROBLEM STATEMENT/DESCRIPTION第一步:问题的识别和评估

This section should contain as much information possible about the concern encountered, the more detailed and accurate information obtained will help to give a better understanding of the problem and assist in investigations and resolution later on.

Example:

- Date(s) of failure(s).

- Quantity of discrepant/suspect reject parts.

- Where the problem was detected.

- If applicable, carryout is/is-not analysis and attach to 8D.

-Have we seen the problem before?

1.问题是什么或目前真实的情况?根据对象和缺陷来述。

2.最早问题在哪里发现的?

3.问题是如何发现的?

4.发生的问题与标准有什么不同?规格是什么?如何会产生不同的?(检验规、图纸、

CATIA 文件、或不良极限样品)

5.产生问题的项目如何测量的?测量系统是什么?测量系统出了什么问题?重复性?精

度?

6.目前的情况会影响多少产品或汽车?(VIN 编号,影响到的工厂顺序号或日期/时间和

班次)

7.目前在戴姆勒克莱斯勒的工厂中发生率是多少?在供应商工厂?良品数?不良品数?

第二步:

-

CONTAINMENT ACTION临时措施

Th is section should identify those actions that “contain” the problem, ensuring no further defects are made and the customer is protected until permanent corrective actions are in place, an example may be to “hold” all suspect stock or “100% sort” for the defect condition.

这一步应该识别包容问题的那些行动,保证不再产生进一步的不合格品并保护客户,直到永久措施有效,例:保持所有可疑库存或100% 挑选不合格品。

Containment actions must be recorded on the standard Containment Instruction sheet. This instruction must include a date when the containment must be carried out until and the relevant approval signatories as agreement.

临时措施应该记录在标准临时措施指导书中。作业指导书必须包含临时措施实行的日期直到相应的批准协议签字生效。

NB: CONTAINMENT ACTIONS MUST CONTINUE UNTIL CORRECTIVE ACTION HAS BEEN VERIFIED AND IMPLEMENTED.

临时措施必须一直采取直到纠正措施确认有效并实行。

Problem Effect: 问题的有效性

Specifiy the number of parts identifed throughout the containment activity.

说明通过临时措施发现的不合格零件数量

State the the total batch size inspected etc.说明检查的整个批次的数量

eg. 5/100 - 5 pcs defective out of 100 pcs如: 5/100 检查100个当中发现5个ROOT CAUSE ANALYSIS:根本原因

This section must include all those actions, or reference to an action plan stating analysis to be conducted to identify and replicate, where necessary, the problem. 应包括所有的措施,或参考一个行动计划,这个行动计划列出了针对问题所需要进行的分析试验,必要的话,应复制再现问题。

Different methods can be employed to identify the root cause - a simple and oftern effective way of identifiying the root cause is to ask WHY, WHY ... 5 times.

确定一个问题根源可以有很多不同的方法-一个简单而有效的方法就是去问5次:为什么,为什么。。。。。Following identification this section should include a statement of the root cause and state CLOSED in the target date box when this has been verified.

接下来这个部分必须包含对问题根源的述,以及当原因经过验证确认后,在目标日期的方框中注明“关闭“

Verification is very important. It’s important to demonstrate a logical and analytical approach to verifying the root cause so the customer understands what steps have been taken to resolve the issue.

验证非常重要。证明一个逻辑分析法能够查出根本原因是很重要的,这样客户才能够明白已经采取了哪些步骤来解决问题。

Examples:

例如:

-Physical verification: testing or showing that we can turn the problem on and off (this is the best verification)

--实地查核:试验或演示我们可以再现问题和解决问题(这是最好的查证)

- Logical verification using is/is-not, cause and effect, etc.

推理验证,可以运用是或不是,原因以及后果等等

Additional sheets should be added to statye actions taken and draw conclusions from testes etc.

附加页要阐述采取的措施,从测试中得到的结论等等

Contribution:

影响:

State the percentage contribution to the overall problem.

列出所有问题的百分比影响

There maybe a number of contributing factors in the root cause. If this is the case estimate the percentage contribution towards the problem.

一个根本原因下或许有很多的影响因素。在这种情况下,估计出对于这个问题影响的百分比。

Note: the Total must always add to 100%.

注意:总数通常是要加到100%

No. of Hours:所需时间

Confirm the number of hours and cost per hour for the customer containment. If not definative data is available obtain written statement from the Customer detailing estimated containment duration and cost/hour.

确认采取临时措施所需的时间和顾客每一小时的花费。如果无法得到顾客书面的明确的数据,就详细评估临时措施所需时间和每小时花费。

Customer Containment: 顾客的临时措施

Confirm whether the Customer has implemented any containment action. If so clarify what has been implemented and verify suitability.

确认顾客是否采取了一些临时措施。如果是,阐明采取了哪些措施并验证是否适当。Example will it affect the integrity of the part and/or effect the warranty.

例如,是否影响到部件的完整性和/或影响保质期。

POTENTIAL PERMANENT CORRECTIVE ACTIONS潜在永久纠错措施:

By definition a corrective action directly solves the problem identified. Actions proposed must ensure the defect cannot recur and the problem has been permanently resolved.

确定一个可以直接解决所发现的问题的纠正措施。提出的措施必须保证问题不会再次出现并永久的解决了这个问题。

The 8D Team, all disciplines, must identify all potential corrective actions that will resolve this problem and carryout verification of these actions prior to implementation to ensure effectiveness.

一个所有成员都经过培训的8D小组,必须确定可以解决这个问题的所有的潜在措施,并且在措施执行前完成对这些措施的验证,以保证这些措施的有效性。

All potential corrective actions can be listed or, as a minimum, those chosen to be verified.

所有的潜在纠错措施都应该列出来或者至少应列出挑选出来准备做验证的措施。

Verification that the corrective action is effective is very important and therefore must not be overlooked or assumed.

确认纠错措施的有效性是非常重要的,因此是不能忽略和假设的。

At this stage it may involve numerous actions / trials in attempt to identify those actions that will actually resolve the problem.

在这个阶段可能会涉及到大量的措施/实验,来确定真正可以解决问题的措施

Examples:例如

- A trial production run. Indicate quantity and results.

-进行试生产。表明数量和结果

- Demonstration of a poka-yoke, i.e. tried and failed to make a bad part etc. 防错措施的证实。如,故意试着做一个不良品,结果无法做。

The stated potential corrective actions may or may not be the Implemented Permanent

Corrective Actions, this can only done once the actions have been successfully verifie

规定的潜在纠错措施并不一定是长期执行的纠错措施,只有在成功验证后才可以作为永久措施。Effective有效性

State the percentage effectiveness of the corrective actions as part of the verification.

作为验证的一部分应当给出一个纠错措施的有效性百分比。

Actions that are not effective ie. Are not 100% should be reviewed and further action must be taken to ensure a satisfactory conclusion is acheived.

应该检查哪些无效的措施如非100%有效的措施,要采取进一步措施来保证或得满意的结论。IMPLEMENTED PERMANENT CORRECTIVE ACTIONS执行的永久纠错措施

This section should contain those corrective actions taken that have been verified as effective againist the stated problem.

这部分应该包含那些已经证实了可以解决问题的有效的纠错措施

All corrective actions must be tracked for progress and confirmed as implemented prior to removal of containment actions.

永久措施执行时,所有的纠错措施必须要有过程跟踪并确认后,才可以取消临时措施。

Containment action should be continued where possible for a period, as agreed with the team to confirm effective resolution of this problem.

临时措施应该一直延续到这个小组同意,解决问题的有效措施已确定。

Effective有效性

State the percentage effectiveness of the corrective actions as part of the verification.

作为验证的一部分,阐明纠正措施有效性的百分比。

Actions that are not effective ie. Are not 100% should be reviewed and further action must be taken to ensure a satisfactory conclusion is acheived.

应该检查哪些无效的措施如非100%有效的措施,要采取进一步措施来保证或得满意的结论。

OTHER PRODUCTS/PROCESSES AFFECTED:

其它受影响的产品/过程

Confirm all other similar products that could be affected by this problem have been considered as part of the corrective actions.

验证所有的其它可能受此问题影响的相似产品是整个纠错措施的一部分。

The originator must communicate to any other KA Plant representatives that maybe affected by this problem to ensure reoccurrences are prevented at other KA locations. 组织者必须同客户的其他工厂代表交流,这可以保证这个问题不会影响同一客户其它的区域。IMPLEMENTED ON SIMILAR PRODUCTS/PROCESSES AFFECTED:

在其它受影响的类似产品/过程中执行

Confirm all other similar products affected by this problem have corrective actions implemented.

确认所有其它受这个问题影响的相似产品也同样执行纠错措施

ACTION(S) TO PREVENT RECURRENCE

防止再发生的措施

The preventive action taken must address the potential for re-occurrence of the problem, what actually allowed for the problem to occur eg. a business process, document or training issue.

采取的预防措施必须针对问题再发生的潜在可能,究竟什么会引起问题再发生。例如,可以制定商业程序,文件或培训资料。

The documents, procedures and systems should be reviewed to reflect the necessary improvements and record the failure modes for future reference and product/process developments.

文件,程序和系统应该不断的检查,反映必要的改进,记录下错误的模式作为今后产品/过程开发的参考,ie. Design FMEA, Process FMEA, Control Plan, standard Operating Procedures, BMS proceduresetc.例:DFMEA,PFMEA,Control Plan,标准操作程序,BMS程序等

MPLEMENTATION DATE

执行日期

Planned date for introduction of preventive action

采取预防措施的计划时间

CONGRATULATE THE TEAM AND CLOSE祝贺这个小组和问题关闭

Track the progress of all the actions until they are closed.

追踪所有措施的进展直到全部关闭

Specifiy COMPLETE in the appropriate box against each of the actions once they are completed.

一旦某一措施完成,在相应的框格写上“完成“

Confirm the PPM figures have been adjusted at the Customer and internally. Send to Customer as final issue.

确认部的和顾客的PPM已经调整。作为最终的结果发送给客户

Sign once closure has been agreed with the 8D Team and forward for approval to appropriate line manager.

一旦8D小组认可问题已经关闭并签字,提交相关主管批准。

File signed-off copy in archive file

文件签字复印存档。

8D报告填写说明(DOC 7页)

8D 报告填写说明 PROBLEM STATEMENT/DESCRIPTION 第一步:问题的识别和评估 This section should contain as much information possible about the concern encountered, the more detailed and accurate information obtained will help to give a better understanding of the problem and assist in investigations and resolution later on. Example: 来自资料搜索网(https://www.sodocs.net/doc/ce10754170.html,) 海量资料下载 - Date(s) of failure(s). - Quantity of discrepant/suspect reject parts. - Where the problem was detected. - If applicable, carryout is/is-not analysis and attach to 8D. -Have we seen the problem before? 1.问题是什么或目前真实的情况?根据对象和缺陷来陈述。 2.最早问题在哪里发现的? 3.问题是如何发现的? 4.发生的问题与标准有什么不同?规格是什么?如何会产生不同的?(检验规范、图纸、 CA TIA 文件、或不良极限样品) 5.产生问题的项目如何测量的?测量系统是什么?测量系统出了什么问题?重复性?精 度? 6.目前的情况会影响多少产品或汽车?(VIN 编号,影响到的工厂顺序号或日期/时间和 班次) 7.目前在戴姆勒克莱斯勒的工厂中发生率是多少?在供应商工厂内?良品数?不良品 数? 第二步: - CONTAINMENT ACTION 临时措施 This section should identify those actions that “contain” the problem, ensuring no further defects

8D报告填写说明

编号
8-D 报告
8D 序号: 提出日期: D1 小组成员: 组长:组长应负责带领小组完成 8D 报告。组长的主要职责包含但不限于:带领小 组完成 8D、制定各项活动及会议日程并管理团队。 组员:组员负责响应小组各项活动。组员选择应基于其专业与技能。组员的主要责 任包含但不限于:问题调查、结论分析与措施执行。 D2 问题描述: 最后更新日期: 问题主题:
版本 修订日期
产品:
生产线:
问题定义应包含“4W2H” ,即 “ where,when,who,what,how many,how much”。即发生时间、发生地点、汇 ”以上信息需要在第一时间通知客户。问题描述需定义“是什么”或“不 报人、问题描述、不合格数量或价值。 是什么” 。 D3 制定短期纠正措施,也称为临时措施、围堵措施、遏制措施(ICA) : 短期纠正措施通常为筛选、返工、操作过程调整、更换库存等。短期措 施需执行临时标准。 D4 定义并验证根本原因: 根本原因定义前需要检验所有的潜在不合格原因并对相关数据进行分析(例如:根本原因消除前,不合格 产品比率为 22%而根本原因消除后,不合格产品比率为 0) 。为了找到根本原因,在原因分析阶段应使用 “五 个为什么?”工具,必要时,不限于究问五次为什么。哪里发生了变化?这是引起不合格的原因吗?消除这个 原因后, 不合格产品会消除吗?根本原因分析是否已经完成 (我们是否需要知道这个根本原因是怎么发生的) ? 只有当根本原因找到并消除时,不合格产品才能被消除。使用鱼骨图等工具进行的原因分类并不等同于根 本原因识别。 “大多数情况下,根本原因有两个类型。第一种根本原因较为明显:错误操作、设备损坏等,识 别该原因可促使加强硬件方面的重视。第二种根本原因是允许不良产品流向客户。 ” 综合以上两种情况进行分 析,是否根本原因覆盖了 100%的不良品? 验证根本原因:主要的根本原因验证方法包含但不限于:问题复现及相关问题分析等。 D5 选择和验证永久性纠正措施(PCA) : 为消除根本原因而制定最有效的永久性纠正措施。此处的永久性纠正措 施必须是针对根本原因并确保根本原因已经被消除。应确定措施责任人和时 间结点。永久性纠正措施验证应适度采用防错分析技术,如果无法采用防错, 需注明理由。 另外,改进措施中对质量管理和操作系统产生的更改需记录。这些质量 管理和操作系统包括:先期质量策划(APQP)文件,操作指导书,程序文件, 培训文件及控制计划等。 D6 实施和确认永久性纠正措施: 包含策划与实施永久性纠正措施。 “改进措施一旦制定便应立即执行。 ” “程序文件、工艺文件、操作指导 书、流程图、潜在失效模式及控制计划等文件都应根据改进措施而作出相应更改。停止执行遏止措施,监控长 期运行结果以验证永久性纠正措施。验证应覆盖所有关键过程,同时应采用 SPC 图、趋势图、检验报告、化验 报告、废品报告及过程审核等方式量化验证结果。 “不要利用客户抱怨来验证改进措施的有效性并以此确定永 久性改进措施。有效的永久性纠正措施确定应包含改进措施实施后的生产运行结果回顾。 ” 永久性纠正措施得到验证前可以关闭 8D 报告,前提是有方法验证永久性纠正措施并且保证该验证得到执 行。验证可以包含客户反馈跟踪。 D7 预防措施,防止系统性问题: 文件修订 是 否 责任人 完成日期 责任人 完成日期

8D报告(范本).doc

1.问题解决小组: 组成日期: 4/18/2012 ** 事业部部长 ** 品质部部长 ** 生产部部长 ** 技术科经理 ** VGS线产品工程师 2.问题描述: 2.1 问题陈述: 客户投诉4个产品短路。 3.临时性纠正措施: 3.1 库存/在制品检查: 1.对在制品进行抽样测试IR,设定为VR=410V;IR<5uA,失效率为 0/24K PCS. 2.对库存进行抽样测试IR, 设定为VR=410V;IR<5uA,失效率为 0/24K PCS. 3.2 工艺制程/OQC限制措施: 3.2.1查核2005年3月份PE1产品的可靠性监控情况,HTRB,PCT,TC和Forward Surge总共 各做了7个批次,每种试验的抽样量为315支,全部合格。 3.2.2 查核2005年3月份UF4004产品的OQC的检验情况,无电性不良记录。 3.2.3将该产品列入OQC加严检验清单中,OQC对UF4004产品连续10个批次执行加严检验 (3/28/2006)。 3.3 风险评估: 风险评估水平为一般(50),不需要采取强制对策。 4.根本原因分析:

4.1 退回样品的初始确认(外观/电性)(如适用): 参照VGSC失效分析报告T061120。 4.2 退回样品的失效分析: 4.2.1 失效分析结果总结: 4.2.1.1.典型IMC失效-表面有氧化层,导致芯片烧毁。 4.2.2 失效分析详细状况: 参照VGSC失效分析报告T061120。(参考VGST提供的UG2 IR不良模拟试验及FA报告) 4.3 失效原因: 4.3.1 失效机理: 由于焊接炉温异常,导致焊接材料产生”IMC”现象,在后期器件应用中发生失效. (参考VGST提供的UG2 IR不良模拟试验及FA报告) 4.3.2 可能的原因/要素: 4.3.2.1 焊接炉温异常,导致焊接材料产生”IMC”现象. 4.3.2.2晶粒制程异常,导致玻璃钝化层披覆不良 4.4 根本原因: 4.4.1 最可能原因的分析: 焊接炉温异常,导致焊接材料产生”IMC”现象. 4.4.2 根本原因的结论: 同4.3.2.1 经过模拟试验及排查, 最可能的原因是由于出炉材料在焊接炉出炉口未及时清理,导致焊接炉内部产生卡炉, 处于焊接炉高温区的材料产生”IMC”现象. 正常炉温曲线: 峰值温度365C.

8D报告范本

1.问题解决小组: 组成日期:4/18/2012 ** 事业部部长 **品质部部长 ** 生产部部长 **技术科经理 ** VGS线产品工程师 2.问题描述: 2.1 问题陈述: 客户投诉4个产品短路。 3.临时性纠正措施: 3.1 库存/在制品检查: 1.对在制品进行抽样测试IR,设定为VR=410V;IR<5uA,失效率为0/24K PCS. 2.对库存进行抽样测试IR,设定为VR=410V;IR<5uA,失效率为 0/24K PCS. 3.2 工艺制程/OQC限制措施: 3.2.1查核2005年3月份PE1产品的可靠性监控情况,HTRB,PCT,TC和Forward Surge 总共各做了7个批次,每种试验的抽样量为315支,全部合格。 3.2.2 查核2005年3月份UF4004产品的OQC的检验情况,无电性不良记录。 3.2.3将该产品列入OQC加严检验清单中,OQC对UF4004产品连续10个批次执行加严检验 (3/28/2006)。 3.3风险评估: 风险评估水平为一般(50),不需要采取强制对策。 4.根本原因分析:

4.1 退回样品的初始确认(外观/电性)(如适用): 参照VGSC失效分析报告T061120。 4.2退回样品的失效分析: 4.2.1失效分析结果总结: 4.2.1.1.典型IMC失效-表面有氧化层,导致芯片烧毁。 4.2.2 失效分析详细状况: 参照VGSC失效分析报告T061120。(参考VGST提供的UG2IR不良模拟试验及FA报告) 4.3 失效原因: 4.3.1失效机理: 由于焊接炉温异常,导致焊接材料产生”IMC”现象,在后期器件应用中发生失效. (参考VGST提供的UG2 IR不良模拟试验及FA报告) 4.3.2 可能的原因/要素: ?4.3.2.1 焊接炉温异常,导致焊接材料产生”IMC”现象. 4.3.2.2晶粒制程异常,导致玻璃钝化层披覆不良 4.4 根本原因: 4.4.1 最可能原因的分析: 焊接炉温异常,导致焊接材料产生”IMC”现象. 4.4.2 根本原因的结论: 同4.3.2.1 经过模拟试验及排查, 最可能的原因是由于出炉材料在焊接炉出炉口未及时清理,导致焊接炉内部产生卡炉,处于焊接炉高温区的材料产生”IMC”现象. 正常炉温曲线:峰值温度365C.

范本:8D报告格式及填写说明

Supplier:**CAR Number: PCN0601040 Part No.:1206-000300Description :T/F,SMD12,T52079(RoHS),30~60Vdc (input) :10Vdc@1.5A & 18Vdc@20mA (bias) 275KHz 200uH@0.7A(peak),SPEC LIN PO: Defect Q’TY:44pcs Total Q’TY:44pcs Defect Rate:100% Severity Level: □Cr ■Ma □Mi Login Date:2006/1/9 Source of Failure: □Acceptance Inspection ■Line Reject □Field Return □Other Closure Date:2005/1/12 Supplier Reference No: EIGHT DISCIPLINE WORKSHEET D1: DESCRIBE THE PROBLEM Date: 2006/1/9 此料在SMT ROHS制程过炉后本体保护胶带收缩并卷起.以下不良品图片 注:1.此不良将造成我司维修工时&费用将Charge贵司. 2.供应商必须在24小时内完成4D报告﹐并告知防堵对策﹔规定时间内回复完整8D报告﹐否则将给予逞罚性扣款(RMB1000.00元/天) D2: Team Building以4-10人为佳 Date: 1/9 Company Name Job Function *** SQE D3: Containment Action Date:紧急对策之日期

汽车行业8d报告格式

汽车行业8d报告格式 范本:8D报告格式及填写说明 篇二:福特8D报告 1解决方法 2方法简介 3适用范围 4实施步骤 5优缺点 6相关应用 解决方法编辑凡是做 FORD 的零件,必需采用 8D 作为品质改善的工具,目前有些企业并非 FORD 的供应商或汽车业的合作伙伴,也很喜欢用这个方便而有效的方法解决品质问题,成为一个固定而有共识的标准化问题解决步骤。 Discipline 1. 成立改善小组(Form the Team):由议题之相关人员组成,通常是跨功能性的,说明团队成员间的彼此分工方式或担任的责任与角色。 Discipline 2. 描述问题(Describe the Problem):将问题尽可能量化而清楚地表达,并能解决中长期的问题而不是只有眼前的问题。 Discipline 3. 实施及确认暂时性的 对策(Contain the Problem):对于解决 D2 之立即而短期行动,避免问题扩大或持续恶化,包含清库存、缩短PM时间、加派人力等。 Discipline 4. 原因分析及验证真因(Identify the Root Cause):发生 D2 问题的真正原因、说明分析方法、使用工具(品质工具)的应用。 Discipline 5. 选定及确认长期改善行动效果(Formulate and Verify

Corrective Actions):拟订改善计划、列出可能解决方案、选定与执行长期对策、验证改善措施,清除 D4 发生的真正原因,通常以一个步骤一个步骤的方式说明长期改善对策,可以应用专案计划甘特图(Gantt Chart),并说明品质手法的应用。 Discipline 6. 改善问题并确认最终效果(Correct the Problem and Confirm the Effects): 执行 D5 后的结果与成效验证。 Discipline 7. 预防再发生及标准化(Prevent the Problem):确保 D4 问题不会再次发生的后续行动方案,如人员教育训练、改善案例分享(Fan out) 、作业标准化、产出BKM、执行ECN 、分享知识和经验等。 Discipline 8. 恭喜小组及规划未来方向(Congratulate the Team):若上述步骤完成后问题已改善,肯定改善小组的努力,并规划未来改善方向。 方法简介编辑 8D又称团队导向问题解决方法、8D问题求解法(8D Problem Solving)是福特公司处理问题的一种方法,亦适用于制程能力指数低於其应有 值时有关问题的解决,它提供了一套符合逻辑的解决问题的方法,同时对於统计制程管制与实际的品质提升架起了一座桥梁。 二战期间,美国政府率先采用一种类似8D的流程——“军事标准1520”,又 称之为“不合格品的修正行动及部署系统”。 1987年,福特汽车公司首次用书面记录下8D法,在其一份课程手册中这一方法被命名为“团队导向的问题解决 法”(Team Oriented Pro blem Solving)。当时,福特的动力系统部门正被一些经年累月、反复出现的生产问题搞得焦头烂额,因此其管理层提请福特集团提供指导课程,帮助解决难题。 适用范围编辑 该方法适用于解决各类可能遇到的简单或复杂的问题;

2020年整理8D报告模板.pdf

8D工作方法 发表于2010年04月18日 16:31 阅读(1) 评论(0) 分类: 方法简介 8D又称团队导向问题解决方法、8D问题求解法(8D Problem Solving)是福特公司处理问题的一种方法,亦适用于制程能力指数低於其应有值时有关问题的解决,它提供了一套符合逻辑的解决问题的方法,同时对於统计制程管制与实际的品质提升架起了一座桥梁。 [编辑]8D工作方法的起源 二战期间,美国政府率先采用一种类似8D的流程——“军事标准1520”,又称之为“不合格品的修正行动及部署系统”。 1987年,福特汽车公司首次用书面记录下8D法,在其一份课程手册中这一方法被命名为“团队导向的问题解决法”(Team Oriented Problem Solving)。当时,福特的动力系统部门正被一些经年累月、反复出现的生产问题搞得焦头烂额,因此其管理层提请福特集团提供指导课程,帮助解决难题。 [编辑]8D适用范围 该方法适用于解决各类可能遇到的简单或复杂的问题; 8D方法就是要建立一个体系,让整个团队共享信息,努力达成目标。 8D本身不提供成功解决问题的方法或途径,但它是解决问题的一个很有用的工具; 亦适用于过程能力指数低于其应有值时有关问题的解决; 面对顾客投诉及重大不良时,提供解决问题的方法。 8D法是美国福特公司解决产品质量问题的一种方法,曾在供应商中广泛推行,现已成为国际汽车行业(特别是汽车零部件产家)广泛采用来解决产品质量问题最好的、有效的方法。 [编辑]8D的目标 提高解决问题的效率,积累解决问题的经验; 提供找出现存的与质量相关的框架; 杜绝或尽量减少重复问题出现; 8D格式的原则上针对出现的问题,找出问题产生的根本原因,提出短期,中期和长期对策并采取相应行动措施; 8D法可跨部门建立小组来加强部门间的协调,推进问题有效解决,从而改进整个过程的质量,防止相同或类似问题的再发生,以保证产品质量。 [编辑]8D工作方法的运用 不合格的产品问题。 顾客投诉问题。 反复频发问题。 需要团队作业的问题。

完整8D报告模板

8Dreport/Qualitycorrectiveactionreport 质量改进报告 编号: 版本:产品名称客户名称客户型号 ProductName CustomerName Customermodel 工厂产品型号客户订单号日期码 Positecmodel Orderno. Datecode 合同编号合同数量异常发生日期ContractNo. Quantity Complaintdate 发文部门异常信息来源要求完成时间 Dispatchedby Messagefrom Requiredcompleted ate DISCIPLINE1: UseTeamApproach ( 建立解决问题 小组 ) 质量改进小组组长:质量改进小组成员: □产品工程师_______________________ □品质工程师_______________________ □采购工程师/SQE___________________ □其他_____________________________ □研发工程师______________ □制程工程师______________ □生产主管________________ 填写人:日期: DISCIPLINE2: DescribeTheProble m( 问题等级______类(填写AorBorC) 问题描 述 ) □图片说明及详细信息描述: 填写人:日期: DISCIPLINE3: ImplementAndVerifyContainmentAction ( □返工/补充加工(QE/PE) 执行暂时 对策 ) □质量问题通知供应商(SQE或采购) □生产计划调整(QE) □(在线/在途/库存)零部件库存处理(PE) □通知客户/QA(公司QA或工厂QE) □国外产品处理(项目主管or品质经理) □其它 相应措施说明:

相关主题